Projects
62 taxpayer-funded projects: public projects worth $1 billion or more, plus the publicly funded projects on the federal Major Projects Office list.
62 of 62
- Alto high-speed railRail · FederalPlanning$3.5B+ (2015) → $60–90B (2025)17× (scope changed since the first price)Delayed 18 yr
- Trans MountainPipelines · FederalComplete$3.8B (2012) → $28.6B (2025)5.7× (scope changed since the first price)Delayed 6.4 yr
- Phoenix pay systemIT systems · FederalOperational$309M (2009) → $1.5B+ (2019)4.1×
- Mackenzie Valley HighwayRoads and bridges · Northwest TerritoriesPlanning$700M (2005) → $3.65B (2026)3.3× (scope changed since the first price)
- SAAQclicIT systems · QuébecOperational$200M (2015) → $638M (2017)3.1×
- Hamilton LRTTransit · OntarioProcurement$1B (2015) → $3.4B (2021)3×Delayed 3 yr
- Polar icebreakersDefence · FederalUnder construction$721M (2008) → $3.15B (2025)3× (scope changed since the first price)Delayed 13 yr
- Taltson hydro expansionHydro · Northwest TerritoriesPlanningup to $700M (2013) → $2–3B (2025)2.7× (scope changed since the first price)
- Contrecœur terminalPorts and other · QuébecUnder construction$750M (2019) → $2.3B (2025)2.5×Delayed 7 yr
- Roberts Bank T2Ports and other · British ColumbiaProcurement$1.9B (2015) → $5.9B (2026)2.3×Delayed 11 yr
- F-35 fightersDefence · FederalProcurement$9B (2010) → $27.7B (2025)2.2× (scope changed since the first price)Delayed 12 yr
- Scarborough subwayTransit · OntarioUnder construction$3.56B (2013) → $10.2B+ (2025)2.1× (scope changed since the first price)Delayed 7 yr
- Eglinton CrosstownTransit · OntarioOperational$2.2B (2007) → $5.3B (2015)2.1× (scope changed since the first price)Delayed 9.2 yr
- Quebec tramwayTransit · QuébecPlanning$3B (2018) → $7.6B (2024)2.1× (scope changed since the first price)Delayed 7 yr
- Bipole IIIEnergy · ManitobaComplete$2.2B (2007) → $5.04B (2018)1.9×Delayed 1 yr
- North Coast TransmissionEnergy · British ColumbiaUnder construction$3B (2023) → $6B (2025)1.9×
- Site C damHydro · British ColumbiaCompleteup to $6.6B (2007) → $16B (2021)1.9×Delayed 9 mo
- Massey Tunnel replacementRoads and bridges · British ColumbiaProcurement$3.5B (2017) → $8.5B (2026)1.9× (scope changed since the first price)Delayed 9 mo
- Muskrat FallsHydro · Newfoundland and LabradorComplete$5B (2010) → $10.1B (2017)1.8×Delayed 5.3 yr
- Gatineau tramwayTransit · QuébecPlanning$2.1B (2018) → up to $4.4B (2023)1.8×Delayed 6 yr
- Surrey-Langley SkyTrainTransit · British ColumbiaUnder construction$3.12B (2019) → $6B (2024)1.6×Delayed 10 mo
- Blue Line extensionTransit · QuébecUnder construction$3.9B (2018) → $7.6B (2024)1.6×Delayed 5 yr
- Surface combatantsDefence · FederalUnder construction$26.2B (2008) → $60B (2026)1.6×Delayed 1 yr
- Niagara TunnelHydro · OntarioComplete$985M (2005) → $1.6B (2010)1.5×Delayed 3.3 yr
- Joint support shipsDefence · FederalUnder construction$2.1B (2004) → $5B+ (2026)1.5× (scope changed since the first price)Delayed 15 yr
- Sturgeon RefineryEnergy · AlbertaOperational$5.7B (2012) → $8.5B (2013)1.5×
- Yonge North subwayTransit · OntarioProcurementup to $3B (2007) → $5.6B (2021)1.5× (scope changed since the first price)
- Grays Bay road and portRoads and bridges · NunavutPlanning$550M (2016) → $1B (2024)1.5×
- Iqaluit hydroHydro · NunavutPlanning$356M (2013) → up to $500M (2017)1.3× (scope changed since the first price)
- Ottawa LRT Stage 2Transit · OntarioUnder construction$3B (2015) → $4.91B (2023)1.3×Delayed 4 yr
- Keeyask damHydro · ManitobaComplete$5.6B (2011) → $8.7B (2021)1.3×Delayed 2.3 yr
- Nuclear waste repositoryEnergy · OntarioPlanning$16.9B (2003) → $26B (2021)1.3× (scope changed since the first price)
- Cyclone helicoptersDefence · FederalOperational$5.1B (2004) → $9B (2021)1.3×Delayed 6.5 yr
- Spadina subway extensionTransit · OntarioOperational$2.09B (2008) → $3.18B (2016)1.3×Delayed 2 yr
- Valley Line West LRTTransit · AlbertaUnder construction$1.8B (2011) → $2.6B (2020)1.3×
- REM (Montreal)Transit · QuébecUnder construction$5.5B (2016) → $8.3B (2024)1.2×
- Broadway SubwayTransit · British ColumbiaUnder construction$1.98B (2014) → $2.95B (2025)1.1×Delayed 2 yr
- Arctic patrol shipsDefence · FederalUnder construction$3.1B (2007) → $4.1B (2020)1.1× (scope changed since the first price)Delayed 5 yr
- Boundary Dam 3 CCSEnergy · SaskatchewanOperational$1.24B (2011) → $1.35B (2014)Up 9% as announced
- Green Line (Calgary)Transit · AlbertaUnder construction$4.65B (2017) → $6.25B (2026)Up 34% as announced
- Ottawa LRT Stage 1Transit · OntarioOperational$2.1B (2010) → $2.13B (2012)No increaseDelayed 9 mo
- Finch West LRTTransit · OntarioOperational$1.2B (2015) → $1.2B (2017)No increaseDelayed 2 yr
- Gordie Howe BridgeRoads and bridges · FederalOperational$5.7B (2018) → $6.4B (2024)Up 12% as announcedDelayed 1.6 yr
- Pattullo Bridge replacementRoads and bridges · British ColumbiaOperational$1.38B (2021) → $1.38B (2024)No increaseDelayed 2.2 yr
- Ottawa Civic campusHealth · OntarioProcurement$2.8B (2021) → $2.8B (2024)No increase
- Centre BlockPorts and other · FederalUnder construction$4.5–5B (2021) → $4.5–5B (2024)No increase
- Champlain BridgeRoads and bridges · FederalOperationalOn budget$5B (2011) → $4.23B (2015)Below the first priceDelayed 6 mo
- Port Lands flood protectionPorts and other · MultipleCompleteOn budget$1.25B (2016) → $1.25B (2024)On budget
- Arctic corridor roadRoads and bridges · Northwest TerritoriesPlanning$1.1B (2019)No new figure
- Darlington SMRsEnergy · OntarioUnder construction$20.9B (2025)No comparable figureDelayed 2 yr+
- West Coast pipelinePipelines · AlbertaPlanning$35.2–43.7B (2026)No new figure
- Ontario LineTransit · OntarioUnder construction$10.9B (2019)No comparable figureDelayed 4 yr
- New submarinesDefence · FederalProcurementup to $43B (2025)No new figure
- Churchill Falls and Gull IslandHydro · MultiplePlanning$33B+ (2024)No comparable figure
- Darlington refurbishmentEnergy · OntarioCompleteOn budget$12.8B (2016)No new figure
- Hurontario LRTTransit · OntarioUnder construction$1.6B (2015)No comparable figureDelayed 1.8 yr
- Point Lepreau refurbishmentEnergy · New BrunswickComplete$1.4B (2005)No new figure
- Regina BypassRoads and bridges · SaskatchewanCompleteOn budget$1.88B (2015)No comparable figureDelayed 1 mo
- Valley Line SoutheastTransit · AlbertaOperational$1.8B (2016)No new figureDelayed 2.9 yr
- P-8A patrol aircraftDefence · FederalProcurement$10.4B (2023)No new figure
- Pickering refurbishmentEnergy · OntarioApproved$26.8B (2025)No new figure
- QEII Halifax InfirmaryHealth · Nova ScotiaUnder construction$2B (2018)No comparable figure
Prices as announced. Change compares the latest official figure with the first one, after inflation. Delay is the latest target against the first one; a + means the latest target was withdrawn with no new date. * Scope changed after the first price. The first price still counts as the starting point.