CH-148 Cyclone

Twenty-eight Sikorsky maritime helicopters to replace the navy's 1960s Sea Kings. Contracted in 2004 for delivery from 2008; the first aircraft arrived in 2015.

CH-148 Cyclone was first priced at $5.1 billion in 2004 by the Government of Canada. The final cost was $9 billion (2021, Department of National Defence), 1.3 times the first price after adjusting for inflation. It opened 6 years, 6 months after the original first delivery target of 2008.

Also called: Maritime Helicopter Project, Sea King replacement

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.3×the first quoted price released to the public

First price 2004, Government of Canada
$8.3B
Final cost 2021, Department of National Defence
$11B
Watchdog estimate 2010, Auditor General of Canada
$8.3B

The most recent independent estimate (Auditor General of Canada, 2010) came out well before the latest official figure, so the two aren’t compared.

Adjusted for inflation to 2026 dollars.

Days since announced
8,733
Status
Operational
Owner
Government of Canada
Scope
Unchanged

Every estimate

Government Watchdog

4 public cost estimates from 2004 to 2021.

Left out because they measure something else: $1.9B acquisition, 2014; $3.2B acquisition, 2021.

Schedule

Original first delivery target
Set in 2004
2008
Opened
19 Jun 2015
Delay
6 years, 6 months

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 6 Dec 2021
    Cost

    DND: acquisition $3.2B

    Department of National DefenceDepartment of National Defence (Question Period note)[5]

  2. 6 Dec 2021
    Cost

    DND: $3.2B acquisition plus $5.8B support to 2038

    Department of National DefenceDepartment of National Defence (Question Period note)[5]Sum of $3.2B + $5.8B

  3. 19 Jun 2015
    Status

    First six Cyclones delivered

    Delivered seven years after the original 2008 target. Final delivery was planned for June 2022.

    SikorskyGlobal Trade Magazine[4]

  4. 23 Jun 2014
    Cost

    Acquisition $1.9B after the 2013-14 contract amendments

    Government of CanadaCBC News[3]

  5. 23 Jun 2014
    Cost

    Total budget $7.6B

    Government of CanadaCBC News[3]

  6. 26 Oct 2010
    Cost

    Auditor General: about $5.7B

    Auditor General of Canada (Sheila Fraser)CBC News[1]

  7. 2008
    Schedule

    Delivery deadline moved to November 2010

    Government of Canada and SikorskyCBC News[2]

  8. Jul 2004
    Cost

    Sikorsky contract for 28 Cyclones: $5.1B

    Government of CanadaCBC News[2]First price

  9. Jul 2004
    Schedule

    First helicopter due 2008

    Government of CanadaCBC News[2]

  10. 2003
    Announcement

    Martin pegs the helicopters at $2.8B, before maintenance

    Shown on the timeline but not used as the cost baseline: it covered acquisition only, while the 2004 contract and every later total include in-service support. Editorial decision, 2026-10-06.

    Government of Canada (Prime Minister Paul Martin)CBC News[1]

Sources

  1. CBC News, 11 Apr 2012
    “In 2003, Paul Martin pegged the program at $2.8 billion, which did not include long-term maintenance.”
    “Former Auditor General Sheila Fraser said the cost of the program had grown to about $5.7 billion, up from an initial estimates of $5.1 billion.”
  2. CBC News, 26 Oct 2010
    “The contract for 28 Cyclone helicopters was awarded to the U.S-based Sikorsky in July 2004 in a deal valued at $5.1 billion.”
    “The first helicopter was to be delivered in 2008, with another helicopter to be delivered every 27 months.”
    “Sikorsky and the federal government negotiated a new deadline delivery of November 2010 after the original 2008 target was missed.”
  3. CBC News, 23 Jun 2014
    “In fact, the total budget is $7.6 billion - $5.7 billion for in-service support, including the amendments to the contract, and $1.9 billion for the acquisition of the helicopters.”
  4. Global Trade Magazine, 24 Jun 2015
    “The Royal Canadian Air Force (RCAF) has taken delivery of six Sikorsky-made CH-148 Cyclone maritime patrol helicopters.”
  5. Department of National Defence (Question Period note), 6 Dec 2021
    “Background: Quick Facts Fleet procurement: * CH-148 Cyclone fleet: 28 aircraft procured * Acquisition cost: $3.2 billion * Cost for major in-service support until 2038: $5.8 billion.”

How we count