Cost overruns on Canadian public projects: the numbers
How far over budget Canada’s biggest taxpayer-funded projects have gone, from transit and hydro dams to defence procurement and IT systems. Figures cover 62 major public projects and are in 2026 dollars.
- went over budget
- 79%
- went over budget
- over first prices
- $223B
- over first prices
- typical project
- 1.5×
- typical project
- typical delay
- 3 years, 2 months
- typical delay
How much have Canada's major public projects gone over budget?
Across the 48 major Canadian public projects where a later official estimate can be compared with the first price, the first prices add up to $247B and the latest estimates to $470B, in 2026 dollars. That is $223B more than first announced, or 1.9× the original total.
One project does a lot of that: Alto high-speed rail alone accounts for $75B. Without it, the remaining projects are still $148B over their first prices.
How many Canadian public projects go over budget?
Most of them. Of the 48 projects with a comparable later estimate, 38 (79%) grew by more than 5% after adjusting for inflation, and 14 at least doubled. The typical (median) project now costs 1.5× its first price. Among projects that grew, the median increase is 79%.
What is the biggest cost overrun in Canada?
Alto high-speed rail. Its latest estimate is 17× its first price after inflation, from $3.5B+ to $60–90B.
The next largest overruns are Trans Mountain (5.7×), Phoenix pay system (4.1×) and Mackenzie Valley Highway (3.3×). See every project ranked.
Which kinds of projects have the worst cost overruns?
Median latest cost as a multiple of the first price, after inflation, for sectors with at least two comparable projects:
- Government IT systems: 3.6× (2 projects)
- Hydro dams: 1.6× (6 projects)
- Ports and other projects: 1.6× (4 projects)
- Defence procurement: 1.5× (6 projects)
- Energy projects: 1.5× (5 projects)
- Public transit: 1.4× (16 projects)
- Roads and bridges: 1.2× (6 projects)
The government IT systems figure rests on only 2 projects, so treat it as a warning sign rather than a rule.
How late are Canada's major infrastructure projects?
Of the 41 projects with a published opening or completion target, 36 have slipped. The median delay is 3 years, 2 months. Delays are counted against the first target for the same milestone, and read in the project’s favour when a date is given only as a year.
Do any Canadian megaprojects finish on budget?
Some do. 10 of the 48 comparable projects are within 5% of their first price after inflation, and 4 finished at or under their first price in dollars as announced: Champlain Bridge, Darlington refurbishment, Port Lands flood protection and Regina Bypass.
Are cost overruns the same as government waste?
Not necessarily. An overrun measures how far the cost moved from the first price made public, not whether the money was well spent. Some growth comes from bigger scope (16 of the 48 comparable projects changed scope after their first price), from early prices given before design work was done, or from construction costs rising faster than general inflation.
But a first price is what taxpayers and legislators are asked to approve. A large gap between that number and the final bill matters for public spending either way, which is why we track it.
What is the Major Projects Office, and which of its projects use public money?
The Major Projects Office is a federal agency, set up in August 2025 in the Privy Council Office, to fast-track projects of national interest. Many of the projects referred to it are private. We track the ones funded or led by government: Arctic Economic and Security Corridor, Contrecœur container terminal, Darlington SMRs, Deep geological repository, Grays Bay road and port, Iqaluit hydro, Mackenzie Valley Highway, North Coast Transmission, Roberts Bank Terminal 2, Taltson hydro expansion, West Coast Oil Pipeline and Alto high-speed rail.
How are these numbers calculated?
Each project’s overrun compares the first cost made public by the government, project owner or a regulator with the newest official estimate that covers the same thing. Both are adjusted to 2026 dollars with Statistics Canada’s Consumer Price Index, and ranges use their midpoint. Totals and medians include only the 48 of 62 tracked projects that have a comparable later estimate. Every figure links to its source. How we count.