Phoenix Pay System

The federal government's public service payroll system, introduced in 2009 at a build cost of $309 million. It began paying employees in 2016, caused widespread pay errors, and is being replaced by Dayforce.

Phoenix Pay System was first priced at $309 million in 2009 by the Government of Canada. The latest official estimate is $1.5 billion or more (2019, the Government of Canada), 4.1 times the first price after adjusting for inflation.

Also called: Phoenix payroll, Phénix

Reviewed monthly. Last review: 5 Nov 2026. How we update

4.1×the first quoted price released to the public

First price 2009, Government of Canada
$460M
Latest estimate 2019, Government of Canada
$1.9B+
Watchdog estimate 2019, Parliamentary Budget Officer
up to $3.3B

The watchdog’s figure is 73% higher than the latest official estimate.

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
6,541
Status
Operational
Owner
Public Services and Procurement Canada
Scope
Unchanged

Every estimate

Government Watchdog Other

5 public cost estimates from 2009 to 2024.

Left out because they measure something else: $2.2B projected unplanned costs to 2023, 2018; $5.1B cost of fixing errors (excludes original build), 2025; $4.2B+ replacement system (Dayforce), 2026.

Route

No location on file.

Timeline

  1. 23 Mar 2026
    Cost

    Replacement with Dayforce: over $4.2B

    Separate from the cost of Phoenix. The Auditor General called the estimate rough and expects the actual cost to be higher.

    Government of Canada (as reported by the Auditor General)The Canadian Press, via CP24[7]

  2. 25 Aug 2025
    Status

    In use since 2016, being replaced by Dayforce

    Government is paying to run Phoenix and its replacement at the same time.

    Government of CanadaThe Canadian Press, via The Globe and Mail[1]

  3. 23 Jun 2025
    Cost

    Cost of fixing Phoenix: about $5.1B

    Counts only the cost of fixing errors, so it is not compared with the $309M budget. The $309M build cost is on top.

    Public Services and Procurement Canada (Alex Benay)The Canadian Press, via The Globe and Mail[6]

  4. 9 Jul 2024
    Cost

    $3.5B spent so far

    Unattributed running total reported by The Canadian Press; shown as a media figure, not the headline.

    The Canadian PressThe Canadian Press, via rdnewsnow.com[5]

  5. 16 May 2019
    Cost

    Spent or planned: over $1.5B

    Government of Canada (federal budget)CBC News[4]

  6. 16 May 2019
    Cost

    PBO: final cost could reach $2.6B

    The PBO said the replacement system would likely not be ready until 2023 at the earliest.

    Parliamentary Budget OfficerCBC News[4]

  7. 31 Jul 2018
    Cost

    Senate: $2.2B in unplanned costs by 2023

    The same report put the cost to date at $954 million, including the $309 million originally budgeted. The $2.2B is on top of the original budget.

    Senate Standing Committee on National FinanceThe Globe and Mail[3]

  8. 26 Mar 2018
    Cost

    Building and fixing now over $1B

    The department's own tally, in a graph of investments, was $1.192 billion.

    Public Services and Procurement CanadaCBC News[2]

  9. 2009
    Cost

    Introduced in 2009 at $309M

    The budget for the whole system. Later totals count the combined cost of building and fixing it, which is what the system has actually cost.

    Government of CanadaThe Canadian Press, via The Globe and Mail[1]First price

Sources

  1. The Canadian Press, via The Globe and Mail, 25 Aug 2025
    “The Phoenix pay system was introduced in 2009 at an initial cost of $309 million and began processing public servants’ pay in 2016.”
  2. CBC News, 26 Mar 2018
    “The department in charge of the federal government's Phoenix pay system now says the combined cost of implementing and fixing the ailing program has exceeded $1 billion.”
  3. The Globe and Mail, 31 Jul 2018
    “The $2.2-billion to operate and stabilize the pay system by 2023 includes funding for increased processing at the Public Pay Service Centre and money for reviewing employee pay files.”
  4. CBC News, 16 May 2019
    “The government has spent or plans to spend more than $1.5 billion so far, according to the latest federal budget.”
    “the final cost of the system, which has improperly paid tens of thousands of public servants since launching in 2016, could be as high as $2.6 billion.”
  5. The Canadian Press, via rdnewsnow.com, 9 Jul 2024
    “The Phoenix pay system debacle has so far cost the federal government $3.5 billion — a number that could continue to grow as the backlog gets dealt with.”
  6. The Canadian Press, via The Globe and Mail, 23 Jun 2025
    “Benay said taxpayers likely spent about $5.1-billion to process the backlog of Phoenix errors that caused some public servants to be paid incorrectly – or sometimes not paid at all.”
  7. The Canadian Press, via CP24, 23 Mar 2026
    “The report also said that while the government has estimated replacing Phoenix with Dayforce will cost more than $4.2 billion, preliminary estimates did not include costs for departments and agencies to transition to the new system.”

How we count