How we count

Independent and non-partisan

Overruns is independent. It isn’t funded by or affiliated with any political party, government, advocacy group or company.

The projects span federal, provincial and territorial governments led by different parties over two decades. The same rules, below, apply to every one of them.

Sister site: Where It Goes

Overruns tracks what big projects end up costing. Its sister site, Where It Goes, tracks where federal money goes in the first place. It turns each federal budget and the audited Public Accounts into charts: what Ottawa spends per taxpayer, by program and theme, and in each province.

Both sites come from the same publisher and follow the same rules: independent, non-partisan, and every figure linked to its source. They’re separate projects with separate data, built for the same question: what is government doing with your money?

WhereItGoes

Which projects

Canadian government-funded or government-led projects costing $1 billion or more, back to the mid-2000s, plus the publicly funded projects on the federal Major Projects Office list. Private projects aren’t included.

Every number has a source

Each figure links to its source and quotes it word for word. Software confirms the quote is on that page and contains the number. If it can’t be confirmed, it isn’t published.

The first price is the baseline

Overruns are measured from the first cost made public by the government, the project owner or a regulator. Only those sources count as the first price or the latest estimate.

The latest estimate

The latest estimate is the newest official figure, or the final cost once a project is done. Estimates from a watchdog like the Parliamentary Budget Officer or a named outside expert are shown beside it. If one is more than a year older than the official figure, we don’t compare the two.

Like with like

We only compare figures that cover the same thing. A purchase price is never compared with a lifetime cost that adds financing or maintenance.

Scope changes don’t reset the count

When a project grows or changes, we flag it and keep measuring from the first price. Proposed changes get an asterisk and don’t count until they’re decided.

Ranges stay ranges

“$60–90 billion” is shown as a range. Comparisons use the midpoint.

Adjusted for inflation

Costs are shown in 2026 dollars using Statistics Canada’s Consumer Price Index (table 18-10-0004-01, data to October 2026). Switch to “As announced” to see the original figures.

today’s dollars = announced cost × CPI now ÷ CPI in the year it was said

Delays

We compare deadlines for the same milestone. Once a project opens or finishes, the delay runs to that date. When a deadline is given only as a year, we read it in the project’s favour, so a delay is never overstated. When a proponent says a deadline will be missed but gives no new date, we show no current target and the delay as a minimum (for example “2 years+”) until a new date is announced.

Updates

Every project is reviewed monthly. A person approves each new figure before it goes up. Each project page says when it was last checked for new figures, even when nothing changed.

All the data is free to download as CSV or JSON, with every source and quote: see the data page.

Corrections

Spotted a figure we got wrong or missed? Tell us and we’ll check it against the source and fix it.