Overruns

Cost overruns on Canada’s biggest taxpayer-funded projects

We track every publicly available cost estimate, from the first price announced to the most recent estimate.

  1. Alto high-speed rail
    $4.7B → $79B 2015–2025
    17× (scope changed since the first price)
    Planning
  2. Trans Mountain
    $5.3B → $30B 2012–2025
    5.7× (scope changed since the first price)
    Complete
  3. Phoenix pay system
    $460M → $1.9B 2009–2019
    4.1×
    Operational
  4. Mackenzie Valley Highway
    $1.1B → $3.7B 2005–2026
    3.3× (scope changed since the first price)
    Planning
  5. SAAQclic
    $269M → $834M 2015–2017
    3.1×
    Operational

First price Growth sinceAdjusted for inflation to 2026 dollars.* Scope changed after the first price. The first price still counts as the starting point.

First price against latest estimate

Each dot is a project, in 2026 dollars. Dots on the diagonal cost what was first announced; the higher above it, the bigger the overrun. Both scales are logarithmic, so every step is three times the last.

Cost grewAt or below the first priceScope changed since the first price

14 projects have no comparable later estimate yet and are not shown. Every figure is in the table below.

The biggest overruns

ProjectLatestAfter inflation
Alto high-speed rail$60–90B (2025)17× (scope changed since the first price)
Trans Mountain$28.6B (2025)5.7× (scope changed since the first price)
Phoenix pay system$1.5B+ (2019)4.1×
Mackenzie Valley Highway$3.65B (2026)3.3× (scope changed since the first price)
SAAQclic$638M (2017)3.1×
Hamilton LRT$3.4B (2021)3×
Polar icebreakers$3.15B (2025)3× (scope changed since the first price)
Taltson hydro expansion$2–3B (2025)2.7× (scope changed since the first price)
Contrecœur terminal$2.3B (2025)2.5×
Roberts Bank T2$5.9B (2026)2.3×
F-35 fighters$27.7B (2025)2.2× (scope changed since the first price)
Scarborough subway$10.2B+ (2025)2.1× (scope changed since the first price)
Eglinton Crosstown$5.3B (2015)2.1× (scope changed since the first price)
Quebec tramway$7.6B (2024)2.1× (scope changed since the first price)
Bipole III$5.04B (2018)1.9×
North Coast Transmission$6B (2025)1.9×
Site C dam$16B (2021)1.9×
Massey Tunnel replacement$8.5B (2026)1.9× (scope changed since the first price)
Muskrat Falls$10.1B (2017)1.8×
Gatineau tramwayup to $4.4B (2023)1.8×
Surrey-Langley SkyTrain$6B (2024)1.6×
Blue Line extension$7.6B (2024)1.6×
Surface combatants$60B (2026)1.6×
Niagara Tunnel$1.6B (2010)1.5×
Joint support ships$5B+ (2026)1.5× (scope changed since the first price)
Sturgeon Refinery$8.5B (2013)1.5×
Yonge North subway$5.6B (2021)1.5× (scope changed since the first price)
Grays Bay road and port$1B (2024)1.5×
Iqaluit hydroup to $500M (2017)1.3× (scope changed since the first price)
Ottawa LRT Stage 2$4.91B (2023)1.3×
Keeyask dam$8.7B (2021)1.3×
Nuclear waste repository$26B (2021)1.3× (scope changed since the first price)
Cyclone helicopters$9B (2021)1.3×
Spadina subway extension$3.18B (2016)1.3×
Valley Line West LRT$2.6B (2020)1.3×
REM (Montreal)$8.3B (2024)1.2×
Broadway Subway$2.95B (2025)1.1×
Arctic patrol ships$4.1B (2020)1.1× (scope changed since the first price)

Figures as announced. The multiple compares the latest official estimate with the first price, both in 2026 dollars. * Scope changed after the first price. The first price still counts as the starting point. All projects