Cost overruns on Canada’s biggest taxpayer-funded projects
We track every publicly available cost estimate, from the first price announced to the most recent estimate.
- Alto high-speed rail$4.7B → $79B 2015–2025Planning
- Trans Mountain$5.3B → $30B 2012–2025Complete
- Phoenix pay system$460M → $1.9B 2009–2019Operational
- Mackenzie Valley Highway$1.1B → $3.7B 2005–2026Planning
- SAAQclic$269M → $834M 2015–2017Operational
First price Growth sinceAdjusted for inflation to 2026 dollars.* Scope changed after the first price. The first price still counts as the starting point.
First price against latest estimate
Each dot is a project, in 2026 dollars. Dots on the diagonal cost what was first announced; the higher above it, the bigger the overrun. Both scales are logarithmic, so every step is three times the last.
14 projects have no comparable later estimate yet and are not shown. Every figure is in the table below.
The biggest overruns
| Project | Latest | After inflation |
|---|---|---|
| Alto high-speed rail | $60–90B (2025) | 17× (scope changed since the first price) first price |
| Trans Mountain | $28.6B (2025) | 5.7× (scope changed since the first price) first price |
| Phoenix pay system | $1.5B+ (2019) | 4.1× first price |
| Mackenzie Valley Highway | $3.65B (2026) | 3.3× (scope changed since the first price) first price |
| SAAQclic | $638M (2017) | 3.1× first price |
| Hamilton LRT | $3.4B (2021) | 3× first price |
| Polar icebreakers | $3.15B (2025) | 3× (scope changed since the first price) first price |
| Taltson hydro expansion | $2–3B (2025) | 2.7× (scope changed since the first price) first price |
| Contrecœur terminal | $2.3B (2025) | 2.5× first price |
| Roberts Bank T2 | $5.9B (2026) | 2.3× first price |
| F-35 fighters | $27.7B (2025) | 2.2× (scope changed since the first price) first price |
| Scarborough subway | $10.2B+ (2025) | 2.1× (scope changed since the first price) first price |
| Eglinton Crosstown | $5.3B (2015) | 2.1× (scope changed since the first price) first price |
| Quebec tramway | $7.6B (2024) | 2.1× (scope changed since the first price) first price |
| Bipole III | $5.04B (2018) | 1.9× first price |
| North Coast Transmission | $6B (2025) | 1.9× first price |
| Site C dam | $16B (2021) | 1.9× first price |
| Massey Tunnel replacement | $8.5B (2026) | 1.9× (scope changed since the first price) first price |
| Muskrat Falls | $10.1B (2017) | 1.8× first price |
| Gatineau tramway | up to $4.4B (2023) | 1.8× first price |
| Surrey-Langley SkyTrain | $6B (2024) | 1.6× first price |
| Blue Line extension | $7.6B (2024) | 1.6× first price |
| Surface combatants | $60B (2026) | 1.6× first price |
| Niagara Tunnel | $1.6B (2010) | 1.5× first price |
| Joint support ships | $5B+ (2026) | 1.5× (scope changed since the first price) first price |
| Sturgeon Refinery | $8.5B (2013) | 1.5× first price |
| Yonge North subway | $5.6B (2021) | 1.5× (scope changed since the first price) first price |
| Grays Bay road and port | $1B (2024) | 1.5× first price |
| Iqaluit hydro | up to $500M (2017) | 1.3× (scope changed since the first price) first price |
| Ottawa LRT Stage 2 | $4.91B (2023) | 1.3× first price |
| Keeyask dam | $8.7B (2021) | 1.3× first price |
| Nuclear waste repository | $26B (2021) | 1.3× (scope changed since the first price) first price |
| Cyclone helicopters | $9B (2021) | 1.3× first price |
| Spadina subway extension | $3.18B (2016) | 1.3× first price |
| Valley Line West LRT | $2.6B (2020) | 1.3× first price |
| REM (Montreal) | $8.3B (2024) | 1.2× first price |
| Broadway Subway | $2.95B (2025) | 1.1× first price |
| Arctic patrol ships | $4.1B (2020) | 1.1× (scope changed since the first price) first price |
Figures as announced. The multiple compares the latest official estimate with the first price, both in 2026 dollars. * Scope changed after the first price. The first price still counts as the starting point. All projects