Future Fighter Capability Project
Replacing the RCAF's CF-18 Hornets. Announced in 2010 as a sole-source buy of 65 F-35s, reset in 2012, relaunched in 2017 as an open competition for 88 jets, and won by the F-35 in 2022. The full purchase has been under review since March 2025.
Future Fighter Capability Project was first priced at $9 billion in 2010 by the Government of Canada. The latest official estimate is $27.7 billion (2025, National Defence), 2.2 times the first price after adjusting for inflation. The first delivery target has moved 12 years, from 2016 to 2028.
Also called: F-35 purchase, CF-18 replacement
Reviewed monthly. Last review: 5 Nov 2026. How we update
2.2×the first quoted price released to the public
- First price 2010, Government of Canada
- Latest estimate 2025, National Defence
- Watchdog estimate 2023, Parliamentary Budget Officer
The most recent independent estimate (Parliamentary Budget Officer, 2023) came out well before the latest official figure, so the two aren’t compared.
Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,980
- Status
- Procurement
- Owner
- Government of Canada
- Scope
- Changed in 2017
Every estimate
Government Watchdog
6 public cost estimates from 2010 to 2025.
Left out because they measure something else: $29.3B lifecycle, 2011; $25B lifecycle, 2012; $44B lifecycle, 2012; $45.8B lifecycle, 2012; up to $73.9B lifecycle, 2023.
Schedule
- Original first delivery targetSet in 2010
- 2016
- Current first delivery targetSet in 2025
- 2028
- Delay
- 12 years
A target given only as a year counts as the end of that year.
Location
Timeline
- 22 Oct 2026Milestone
First two F-35s delivered in Arizona, full order still under review
The jets are at Luke Air Force Base for training, not in Canada. The review of the full 88-aircraft order continues.
Royal Canadian Air ForceThe Aviationist[15]
- 27 Apr 2026Milestone
Review continues with no end date
Defence Minister David McGuintyAeroTime[14]
- 10 Jun 2025Cost
National Defence's own estimate: $27.7B
Revealed in the Auditor General's audit. Bases, weapons and other items add at least $5.5B more.
National Defence (estimate reported by the Auditor General)CBC News[11]The Canadian Press, via National Newswatch[12]Office of the Auditor General of Canada[13]
- 10 Jun 2025Schedule
First jets in Canada in 2028
The first jets go to Arizona for pilot training in 2026.
Auditor General of CanadaOffice of the Auditor General of Canada[13]
- 14 Mar 2025Milestone
Ottawa reopens the F-35 decision
Defence Minister Bill BlairCBC News[10]
- 2 Nov 2023Cost
Budget officer: $19.8B acquisition phase
Parliamentary Budget Officer (Yves Giroux)CBC News[9]
- 2 Nov 2023Cost
Budget officer: up to $73.9B over the fleet's life
Parliamentary Budget Officer (Yves Giroux)CBC News[9]Lifecycle cost
- 9 Jan 2023Cost
Contract signed; budget $19B
Government of Canada (Defence Minister Anita Anand)CBC News[8]
- 9 Jan 2023Schedule
First delivery slips to 2026
National Defence (senior officials, technical briefing)CBC News[8]
- 21 Dec 2022Schedule
Replacement complete by 2032
Government of CanadaThe Canadian Press, via CBC News[7]
- 28 Mar 2022Milestone
F-35 wins the competition
Government of CanadaCBC News[6]
- 12 Dec 2017Scope
Open competition for 88 jets
Fleet raised from 65 to 88 jets and bought through an open competition, with 18 used Australian F-18s as an interim fleet.
Government of CanadaGlobal News[5]
- 12 Dec 2017Cost
$15-19B set aside for 88 jets
Government of Canada (officials)Global News[5]
- 12 Dec 2017Schedule
First new jet by 2025
Government of CanadaGlobal News[5]
- 12 Dec 2012Cost
Defence: about $44B over 42 years
Department of National DefenceCBC News[4]Lifecycle cost
- 12 Dec 2012Cost
KPMG: $45.8B over 42 years
KPMG (independent review commissioned by the government)CBC News[4]Lifecycle cost
- 12 Dec 2012Status
Plan 'reset': no decision until a full options review
Government of CanadaCBC News[4]
- 3 Apr 2012Cost
Auditor general: Defence's own 20-year figure was $25B
Auditor General of Canada (Michael Ferguson)CBC News[3]Lifecycle cost
- 10 Mar 2011Cost
Budget officer: $9.7B to buy
Parliamentary Budget Officer (Kevin Page)CBC News[2]
- 10 Mar 2011Cost
Budget officer: $29.3B over 30 years
Parliamentary Budget Officer (Kevin Page)CBC News[2]Lifecycle cost
- 16 Jul 2010Cost
$9B for 65 F-35s
Purchase only. Operating and maintenance costs were not included.
Government of Canada (Defence Minister Peter MacKay)Aviation International News[1]CBC News[2]First price
- 16 Jul 2010Schedule
First jet delivered in 2016
Government of CanadaAviation International News[1]
Sources
- Aviation International News, 18 Jul 2010
“The $9 billion commitment covers 65 JSFs.”
“The first is due for delivery in 2016 to begin replacement of the CF-18 Hornet fleet.”
- CBC News, 10 Mar 2011
“It says it has committed $9-billion to buy the 65 planes and they will cost around $70 million each.”
“Page estimates the acquisition cost for the fleet at $9.7 billion and the ongoing sustainment cost for it at $19.6 billion.”
“Parliamentary Budget Officer Kevin Page said in a report Thursday that his $29.3 billion estimate covers the purchase price and sustainment costs for the fleet over 30 years.”
- CBC News, 12 Apr 2012
“Ferguson says the department's own estimate puts personnel, operating and maintenance costs at $16 billion, for a total 20-year cost of $25 billion for the F-35s.”
- CBC News, 12 Dec 2012
“Wednesday, a Department of National Defence report assessed the new longer costs at about $44 billion.”
“It also tacked on another billion dollars in costs to account for aircraft losses over the years, setting the final cost for 65 aircraft, maintenance, operating costs and sustainment at $45.8 billon.”
“The federal government says it won't make a final decision on which fighter jet to buy until it completes every step of the complex process it laid out last spring following a blistering report from the auditor general about the escalating costs attached to the F-35.”
- Global News, 12 Dec 2017
“The Canadian government is launching a competition to buy a new fleet of 88 fighter jets and officials confirmed Tuesday they will also be buying an interim fleet of 18 jets from Australia rather than Boeing.”
“Officials said Tuesday the cost is being estimated at roughly half a billion dollars for the interim replacement, while roughly $15 billion to $19 billion will be set aside for the full competition.”
“A contract award is expected in 2022 and the government says it expects to have the first aircraft resulting from the award of the contract in its possession by 2025.”
- CBC News, 28 Mar 2022
“The Canadian government has chosen the F-35 as its preferred replacement for the air force's four-decade-old CF-18 fighters and will open negotiations with the stealth jet's manufacturer, Lockheed Martin.”
- The Canadian Press, via CBC News, 21 Dec 2022
“While the federal government has said it plans to buy 88 new fighter jets to replace its aging CF-18s between 2026 and 2032, the sources said Canada will be purchasing F-35s in blocks over the next few years.”
- CBC News, 9 Jan 2023
“The project's budget of $19 billion remains the same as originally forecast by the Liberal government when it signalled the purchase last year.”
“won't see its first delivery until 2026 and the first F-35 squadrons will not be operational until 2029, senior defence officials said during a technical briefing before the minister's announcement.”
- CBC News, 2 Nov 2023
“"The total cost of the acquisition phase, including not just the purchase cost of the fighter jets but all acquisition phase activities, is projected to be $19.8 billion, according to our analysis,"”
“Owning and operating a fleet of F-35 fighter jets over the next four and a half decades is expected to cost Canadian taxpayers as much as $73.9 billion, the Parliamentary Budget Officer said Thursday in a new report.”
- CBC News, 14 Mar 2025
“Canada is actively looking at potential alternatives to the U.S.-built F-35 stealth fighter and will hold conversations with rival aircraft makers, Defence Minister Bill Blair said late Friday, just hours after being reappointed to the post as part of Prime Minister Mark Carney's new cabinet.”
- CBC News, 10 Jun 2025
“According to the report, the cost of the F-35 program has risen to $27.7 billion — up from the $19 billion National Defence announced in 2023.”
- The Canadian Press, via National Newswatch, 10 Jun 2025
“Just two years later, the number has climbed to $27.7 billion.”
- Office of the Auditor General of Canada, 7 Oct 2025
“The audit found that this figure was based on outdated information and that by 2024, the projected costs had increased to $27.7 billion—almost 50% more than the original estimate.”
“Based on the current plan, Canada’s first CF‑35s will be sent to Luke Air Force Base in Arizona in 2026 to support pilot training, while the first aircraft will arrive in Canada in 2028.”
- AeroTime, 28 Apr 2026
“Canada’s defense minister has confirmed that Ottawa’s review of its plan to purchase 88 Lockheed Martin F-35 fighter jets is still ongoing, with no timeline given for a final decision.”
- The Aviationist, 26 Oct 2026
“The aircraft arrived at Luke Air Force Base, Arizona, on Oct. 22, 2026, where they will support the initial phase of the country's F-35 program.”