Trans Mountain Expansion Project

A second oil pipeline alongside the 1950s Trans Mountain line from the Edmonton area to Burnaby, B.C., nearly tripling capacity. Ottawa bought the line and the project in 2018 and finished it as owner.

Trans Mountain Expansion Project was first priced at $3.8 billion in 2012 by Kinder Morgan Energy Partners. The final cost was $28.6 billion (2025, Trans Mountain Corporation), 5.7 times the first price after adjusting for inflation. It was completed 6 years, 5 months after the original completion target of 2017.

Also called: TMX, Trans Mountain pipeline expansion

Reviewed monthly. Last review: 5 Nov 2026. How we update

5.7×the first quoted price released to the public

First price 2012, Kinder Morgan Energy Partners
$5.3B
Final cost 2025, Trans Mountain Corporation
$30B
Watchdog estimate 2019, Parliamentary Budget Officer
$12B

The most recent independent estimate (Parliamentary Budget Officer, 2019) came out well before the latest official figure, so the two aren’t compared.

Adjusted for inflation to 2026 dollars.

Days since announced
5,520
Status
Complete
Owner
Government of Canada
Scope
Changed in 2013

Every estimate

Project owner Watchdog

13 public cost estimates from 2012 to 2025.

Schedule

Original completion target
Set in 2012
2017
Completed
1 May 2024
Delay
6 years, 5 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 6 Mar 2025
    Cost

    Final construction cost: $28.6B

    Actual spending reported after completion. Another $5.1B in financing costs was capitalized, for $33.7B in all. The first figure, in 2012, was a construction cost, so the construction figure is the one compared.

    Trans Mountain CorporationTrans Mountain Corporation (Management Report, year ended Dec. 31, 2024)[23]

  2. 8 Nov 2024
    Cost

    Total cost estimate rises to $34.2B

    Trans Mountain's own estimate, reported by the Parliamentary Budget Officer.

    Trans Mountain Corporation (estimate reported by the Parliamentary Budget Officer)Office of the Parliamentary Budget Officer[24]

  3. 1 May 2024
    Status

    Expanded pipeline enters commercial service

    Trans Mountain CorporationTrans Mountain Corporation (Management Report, year ended Dec. 31, 2024)[23]

  4. 26 Feb 2024
    Schedule

    Firm service from May 1, 2024

    Trans Mountain Corporation (filing to the Canada Energy Regulator)Reuters, via BOE Report[22]

  5. 10 Mar 2023
    Cost
  6. 10 Mar 2023
    Schedule

    In service in Q1 2024

    Trans Mountain CorporationReuters, via Kitco News[20]

  7. 18 Feb 2022
    Cost

    $21.4B; Ottawa says no more public money

    Trans Mountain CorporationTrans Mountain Corporation (project update)[18]Global News[19]

  8. 18 Feb 2022
    Schedule

    Mechanical completion in Q3 2023

    Trans Mountain CorporationTrans Mountain Corporation (project update)[18]Global News[19]

  9. 7 Feb 2020
    Cost

    Crown corporation's first estimate: $12.6B

    Trans Mountain CorporationDepartment of Finance Canada[11]The Canadian Press, via CFJC Today[17]

  10. 7 Feb 2020
    Schedule

    In service by December 2022

    Trans Mountain Corporation (Ian Anderson, CEO)The Canadian Press, via CFJC Today[17]

  11. 18 Jun 2019
    Status

    Cabinet approves the project a second time

    Government of Canada (Prime Minister Justin Trudeau)CBC News[16]

  12. 31 Jan 2019
    Cost

    Budget officer: $9.3B if finished by end of 2021

    Parliamentary Budget OfficerThe Canadian Press, via CHEK News[15]

  13. 30 Aug 2018
    Status

    Court quashes the approval; Ottawa closes the purchase

    Federal Court of AppealCBC News[14]

  14. 7 Aug 2018
    Cost

    Sale documents show scenarios up to $9.3B

    The highest of several scenarios. A finance official said it didn't reflect the expected final cost.

    Kinder Morgan Canada (SEC filing for the sale)The Canadian Press, via CBC News[13]

  15. 7 Aug 2018
    Schedule

    Construction complete December 2021

    Kinder Morgan Canada (SEC filing for the sale)The Canadian Press, via CBC News[13]

  16. 29 May 2018
    Milestone

    Ottawa agrees to buy the pipeline

    The price covered the existing pipeline and the expansion, so it isn't a construction cost.

    Department of Finance CanadaDepartment of Finance Canada[12]

  17. 9 Mar 2017
    Cost

    $7.4B, including financing

    This figure included financing costs.

    Kinder MorganThe Globe and Mail[10]Department of Finance Canada[11]

  18. 9 Mar 2017
    Schedule

    In service by December 2019

    Kinder MorganDepartment of Finance Canada[11]The Globe and Mail[10]

  19. 29 Nov 2016
    Status

    Federal cabinet approves the expansion

    Government of Canada (Prime Minister Justin Trudeau)CBC News[9]

  20. 21 Oct 2015
    Cost

    "Looking more like $6.8 billion"

    Said on an Oct. 21, 2015 analyst call.

    Kinder Morgan Canada (Ian Anderson, president)The Canadian Press, via CBC News[8]

  21. Dec 2013
    Milestone

    Application filed with the National Energy Board

    Kinder Morgan CanadaThe Canadian Press, via CBC News[8]

  22. 10 Jan 2013
    Cost
  23. 10 Jan 2013
    Scope

    Capacity raised to 890,000 barrels a day

    Planned capacity raised from 750,000 to 890,000 barrels a day.

    Kinder Morgan CanadaThe Canadian Press, via CBC News[6]

  24. 18 Jul 2012
    Cost

    Trimmed to $4.1B for 750,000 barrels a day

    Kinder Morgan Energy PartnersKinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)[5]

  25. 12 Apr 2012
    Cost

    Formal launch at about $5B, for 850,000 barrels a day

    Kinder Morgan Canada (Ian Anderson, president)CBC News[3]Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)[4]

  26. 12 Apr 2012
    Schedule

    In operation by 2017

    Kinder Morgan Canada (Ian Anderson, president)CBC News[3]

  27. 21 Feb 2012
    Cost

    About $3.8B

    For a twin line carrying over 600,000 barrels a day, from Kinder Morgan's annual report. The currency isn't stated; treated as Canadian dollars.

    Kinder Morgan Energy PartnersKinder Morgan Energy Partners (SEC Form 10-K, 2011)[2]First price

  28. 19 Oct 2011
    Announcement

    Kinder Morgan tests shipper demand for a bigger Trans Mountain

    Kinder Morgan's first public notice of the expansion. No cost given.

    Kinder Morgan Energy PartnersKinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)[1]

Sources

  1. Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1), 19 Oct 2011
    “Trans Mountain pipeline plans to conduct a binding public open season beginning Oct. 20 and ending Jan. 19, 2012, to assess shipper interest to expand the pipeline.”
  2. Kinder Morgan Energy Partners (SEC Form 10-K, 2011), 21 Feb 2012
    “Based on shipper response, we would construct a twin pipeline that could boost system capacity to over 600,000 barrels per day. Our current estimate of total construction costs on the project is approximately $3.8 billion.”
  3. CBC News, 12 Apr 2012
    “The Kinder Morgan pipeline company is rolling out plans to spend $5 billion to nearly triple the capacity of its Trans Mountain pipeline that carries crude oil from the Alberta oilsands to tankers in Vancouver.”
    “If our application is approved, construction is currently forecast to commence in 2016 with the proposed project operating by 2017," said Anderson.”
  4. Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1), 18 Apr 2012
    “The approximately $5 billion project (which is larger than initially anticipated due to strong binding customer support)”
  5. Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1), 18 Jul 2012
    “The proposed $4.1 billion expansion would increase capacity on Trans Mountain from 300,000 bpd to 750,000 bpd.”
  6. The Canadian Press, via CBC News, 10 Jan 2013
    “The expansion represents a capital investment of $5.4 billion and will complete the twinning of the existing pipeline from Strathcona County, Alta., to Burnaby, B.C.”
    “Subsidiary Kinder Morgan Canada said Thursday that increased long-term commitments from shippers have convinced it to ramp up the proposed expansion capacity to 890,000 barrels per day from a previously planned 750,000.”
  7. Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1), 16 Jan 2013
    “These additional commitments will result in an increase in the proposed expansion capacity from 750,000 bpd to 890,000 bpd and increase the capital investment in the project from $4.1 billion to $5.4 billion.”
  8. The Canadian Press, via CBC News, 20 Nov 2015
    “Kinder Morgan, the company behind the pipeline project, doesn't yet have a formal estimate of how the price tag has changed since its regulatory application was filed in December 2013.”
    “But on a conference call with analysts and investors last month, Kinder Morgan Canada president Ian Anderson said it's looking more like $6.8 billion”
  9. CBC News, 29 Nov 2016
    “Prime Minister Justin Trudeau announces his government is approving Kinder Morgan's proposal to triple the capacity of its Trans Mountain pipeline from Alberta to Burnaby, B.C.”
  10. The Globe and Mail, 9 Mar 2017
    “The price tag for Kinder Morgan Inc.'s Trans Mountain expansion has increased again, this time to $7.4-billion – but the company says it still has strong commercial support for the long-awaited project.”
    “Construction is set to begin this fall, according to the company, with an in-service date slated for late 2019.”
  11. Department of Finance Canada, 7 Feb 2020
    “In 2017, Kinder Morgan publicly announced a Project cost estimate of $7.4 billion (including financing costs), with an estimated in-service date of December 2019.”
    “On February 3, 2020, the Trans Mountain Corporation’s (TMC) Board of Directors approved a total cost estimate of $12.6 billion to bring the Trans Mountain Expansion Project into service by the end of 2022.”
  12. Department of Finance Canada, 29 May 2018
    “In addition, the Government of Canada has reached an agreement with Kinder Morgan to purchase the company's Trans Mountain Expansion Project and related pipeline and terminal assets for $4.5 billion.”
  13. The Canadian Press, via CBC News, 7 Aug 2018
    “Kinder Morgan has long said it would cost $7.4 billion to build a second pipeline parallel to the first in order to triple its capacity, but the financial documents present a number of different construction cost scenarios, with the highest one being $9.3 billion.”
    “The documents also suggest construction won't be complete until December 2021 — a full year beyond its previous projection of December 2020.”
  14. CBC News, 30 Aug 2018
    “The vote came just 30 minutes after the Federal Court of Appeal quashed the federal government's approvals to build the massive project, handing a huge victory to Indigenous groups and environmentalists opposed to it.”
  15. The Canadian Press, via CHEK News, 31 Jan 2019
    “Expanding the pipeline’s capacity will come at an estimated cost of $9.3 billion if the project is completed by Dec. 31, 2021, the PBO estimates.”
  16. CBC News, 18 Jun 2019
    “Prime Minister Justin Trudeau and his cabinet have again approved the Trans Mountain expansion project, a crucial next step for the much-delayed pipeline project designed to carry nearly a million barrels of oil from Alberta's oilpatch to the B.C.”
  17. The Canadian Press, via CFJC Today, 7 Feb 2020
    “The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.”
    “He says the project is now expected to be in service by December 2022.”
  18. Trans Mountain Corporation (project update), 18 Feb 2022
    “The increase in costs, from $12.6 billion to $21.4 billion, can be attributed to five broad categories”
    “Mechanical completion of the Project is anticipated to occur in the third quarter of 2023.”
  19. Global News, 18 Feb 2022
    “But Canada’s oil and gas industry remains staunchly behind a project it says remains essential to the national interest, in spite of newly disclosed budget overruns that peg the new cost of the Trans Mountain expansion at $21.4 billion, up from an earlier estimate of $12.6 billion.”
    “The company also pushed back the projected completion date to the third quarter of 2023.”
  20. Reuters, via Kitco News, 10 Mar 2023
    “The total cost is now estimated at approximately $30.9 billion, the company said in a press release, adding, "Trans Mountain is in the process of securing external financing to fund the remaining cost."”
    “March 10 (Reuters) - Canada's government-owned Trans Mountain Corp on Friday announced that the Trans Mountain Expansion Project pipeline will be in service by the first quarter of 2024.”
  21. The Canadian Press, via Global News, 10 Mar 2023
    “The estimated cost of the Trans Mountain pipeline expansion project has increased once again, this time to $30.9 billion.”
  22. Reuters, via BOE Report, 27 Feb 2024
    “Trans Mountain said in the filing on Monday to the Canada Energy Regulator, however, that commencement for firm service contracts with shippers is May 1.”
  23. Trans Mountain Corporation (Management Report, year ended Dec. 31, 2024), 6 Mar 2025
    “The commercial commencement date for the Expanded System was May 1, 2024.”
    “Since the inception of the project, $28.6 billion in construction capital spending has been incurred plus $5.1 billion in financial carrying costs have been capitalized.”
  24. Office of the Parliamentary Budget Officer, 8 Nov 2024
    “the total project cost estimate for the TMEP increased from $21.4 billion to $34.2 billion.”

How we count