Site C dam
A 1,100-megawatt hydroelectric dam on the Peace River near Fort St. John, B.C., built by the provincial Crown utility BC Hydro. Renamed the John Horgan Dam in 2026.
Site C dam was first priced at up to $6.6 billion in 2007 by BC Hydro. The latest official estimate is $16 billion (2021, the Government of British Columbia), 1.9 times the first price after adjusting for inflation. It was completed 9 months after the original completion target of Nov 2024.
Also called: Site C Clean Energy Project
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.9×the first quoted price released to the public
- First price 2007, BC Hydro
- Latest estimate 2021, Government of British Columbia
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 7,272
- Status
- Complete
- Owner
- BC Hydro
- Scope
- Unchanged
Every estimate
Government Project owner
5 public cost estimates from 2007 to 2021.
Schedule
- Original completion targetSet in 2014
- Nov 2024
- Completed
- 9 Aug 2025
- Delay
- 9 months
A target given only as a year counts as the end of that year.
Location
Timeline
- 9 Aug 2025Status
All six generating units in service
BC HydroBC Hydro[6]
- 26 Feb 2021Cost
$16B and a year late
Blamed on geotechnical problems on the dam's right bank and the pandemic.
Government of British ColumbiaGlobal News[5]
- 26 Feb 2021Schedule
Completion pushed to 2025
Government of British ColumbiaGlobal News[5]
- 11 Dec 2017Cost
New government continues the dam at $10.7B
Government of British Columbia (Premier John Horgan)Daily Hive[4]
- 16 Dec 2014Cost
Approved at $8.8B
Includes a $440M project reserve on top of the $8.335B estimate.
Government of British Columbia (Premier Christy Clark)CBC News[3]
- 16 Dec 2014Schedule
Completion set for November 2024
The schedule set at approval in 2014.
Government of British ColumbiaDaily Hive[4]
- 20 May 2011Cost
$7.9B in regulatory filings
BC HydroPrince George Citizen[2]
- 2007Cost
Feasibility study: up to $6.6B
BC Hydro's 2007 feasibility work, the first figure for the revived project. A 1980s version of the dam was rejected in 1983 and is treated as a separate proposal.
BC Hydro (feasibility study)The Canadian Press, via CBC News[1]First price
Sources
- The Canadian Press, via CBC News, 25 Aug 2024
“Liberal government and has seen cost estimates spike from up to $6.6 billion in 2007 to $16 billion in 2021.”
- Prince George Citizen, 20 May 2011
“Hydro has filed submissions with the provincial and federal regulators on its Site C Dam project in northern B.C. which comes with a $2-billion increased price tag to $7.9 billion.”
- CBC News, 16 Dec 2014
“B.C. has approved the $8.8 billion Site C dam — a massive hydroelectric project that would flood a large area of the Peace River Valley in northeastern B.C.”
- Daily Hive, 12 Dec 2017
“The BCUC report, released last month, warned that the project is unlikely to meet its November 2024 completion and could cost 20% to 50% more when fully complete.”
“As well, the latest official project budget has risen from $8.8 billion to $10.7 billion.”
- Global News, 26 Feb 2021
“The B.C. government reported on Friday the project will now cost an estimated $16 billion to complete, up from the previous estimate of $10.7 billion.”
“The project is now expected to be completed in 2025, a year after its original completion date.”
- BC Hydro, 9 Aug 2025
“With all six units now in service, Site C has the capacity to generate more than 1,100 megawatts of electricity, and enough energy to reliably power about 500,000 homes annually.”