Site C dam

A 1,100-megawatt hydroelectric dam on the Peace River near Fort St. John, B.C., built by the provincial Crown utility BC Hydro. Renamed the John Horgan Dam in 2026.

Site C dam was first priced at up to $6.6 billion in 2007 by BC Hydro. The latest official estimate is $16 billion (2021, the Government of British Columbia), 1.9 times the first price after adjusting for inflation. It was completed 9 months after the original completion target of Nov 2024.

Also called: Site C Clean Energy Project

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.9×the first quoted price released to the public

First price 2007, BC Hydro
up to $10B
Latest estimate 2021, Government of British Columbia
$19B

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
7,272
Status
Complete
Owner
BC Hydro
Scope
Unchanged

Every estimate

Government Project owner

5 public cost estimates from 2007 to 2021.

Schedule

Original completion target
Set in 2014
Nov 2024
Completed
9 Aug 2025
Delay
9 months

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 9 Aug 2025
    Status

    All six generating units in service

    BC HydroBC Hydro[6]

  2. 26 Feb 2021
    Cost

    $16B and a year late

    Blamed on geotechnical problems on the dam's right bank and the pandemic.

    Government of British ColumbiaGlobal News[5]

  3. 26 Feb 2021
    Schedule

    Completion pushed to 2025

    Government of British ColumbiaGlobal News[5]

  4. 11 Dec 2017
    Cost

    New government continues the dam at $10.7B

    Government of British Columbia (Premier John Horgan)Daily Hive[4]

  5. 16 Dec 2014
    Cost

    Approved at $8.8B

    Includes a $440M project reserve on top of the $8.335B estimate.

    Government of British Columbia (Premier Christy Clark)CBC News[3]

  6. 16 Dec 2014
    Schedule

    Completion set for November 2024

    The schedule set at approval in 2014.

    Government of British ColumbiaDaily Hive[4]

  7. 20 May 2011
    Cost

    $7.9B in regulatory filings

    BC HydroPrince George Citizen[2]

  8. 2007
    Cost

    Feasibility study: up to $6.6B

    BC Hydro's 2007 feasibility work, the first figure for the revived project. A 1980s version of the dam was rejected in 1983 and is treated as a separate proposal.

    BC Hydro (feasibility study)The Canadian Press, via CBC News[1]First price

Sources

  1. The Canadian Press, via CBC News, 25 Aug 2024
    “Liberal government and has seen cost estimates spike from up to $6.6 billion in 2007 to $16 billion in 2021.”
  2. Prince George Citizen, 20 May 2011
    “Hydro has filed submissions with the provincial and federal regulators on its Site C Dam project in northern B.C. which comes with a $2-billion increased price tag to $7.9 billion.”
  3. CBC News, 16 Dec 2014
    “B.C. has approved the $8.8 billion Site C dam — a massive hydroelectric project that would flood a large area of the Peace River Valley in northeastern B.C.”
  4. Daily Hive, 12 Dec 2017
    “The BCUC report, released last month, warned that the project is unlikely to meet its November 2024 completion and could cost 20% to 50% more when fully complete.”
    “As well, the latest official project budget has risen from $8.8 billion to $10.7 billion.”
  5. Global News, 26 Feb 2021
    “The B.C. government reported on Friday the project will now cost an estimated $16 billion to complete, up from the previous estimate of $10.7 billion.”
    “The project is now expected to be completed in 2025, a year after its original completion date.”
  6. BC Hydro, 9 Aug 2025
    “With all six units now in service, Site C has the capacity to generate more than 1,100 megawatts of electricity, and enough energy to reliably power about 500,000 homes annually.”