Ottawa LRT Stage 2

The second stage of Ottawa's O-Train system, extending Line 1 east to Trim and west to Moodie and extending Line 2 (Trillium Line) south to Limebank and north to Bayview. Owned by the City of Ottawa with federal and provincial funding.

Ottawa LRT Stage 2 was first priced at $3 billion in 2015 by the City of Ottawa. The latest official estimate is $4.91 billion (2023, the City of Ottawa), 1.3 times the first price after adjusting for inflation. The completion target has moved 4 years, from 2023 to 2027.

Also called: O-Train Stage 2, Confederation Line extension, Trillium Line extension

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.3×the first quoted price released to the public

First price 2015, City of Ottawa
$4B
Latest estimate 2023, City of Ottawa
$5.3B

Adjusted for inflation to 2026 dollars.

Days since announced
4,350
Status
Under construction
Owner
City of Ottawa
Scope
Unchanged

Every estimate

Government Project owner

3 public cost estimates from 2015 to 2023.

Schedule

Original completion target
Set in 2017
2023
Current completion target
Set in 2026
2027
Delay
4 years

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 5 Aug 2026
    Schedule

    Line 1 west extension now slated for 2027

    Flood damage is being assessed.

    OC Transpo (director of rail construction Richard Holder)CTV News Ottawa[7]

  2. 6 Dec 2024
    Milestone

    Line 2 south extension to open in stages from Jan. 6, 2025

    The first section of Stage 2 to open. The line grows from 8 km to 23 km with 11 stations, according to CBC.

    OC TranspoCBC News[6]

  3. 17 Nov 2023
    Cost

    Funding plan reaches $4.91B

    Includes unforeseen costs above the contingency fund. CBC reports the report suggested further city investment might be necessary.

    City of Ottawa (staff report)CBC News[5]

  4. Nov 2023
    Schedule

    East extension early 2025, west late 2026

    The target date shown is for the west extension, the later of the two.

    City of Ottawa (staff)CBC News[5]

  5. 6 Mar 2019
    Cost

    Council approves $4.66B

    The project had grown from 30 km of track to 44 km and from 19 stations to 24, according to CBC.

    City of Ottawa (council)Global News[4]CBC News[5]

  6. 22 Feb 2019
    Schedule

    Completion pushed to 2025

    CBC reported the Trillium Line would open first, in fall 2022, with the east extension by fall 2024 and the west extension in spring 2025.

    City of Ottawa (staff)CTV News Ottawa[3]

  7. Mar 2017
    Schedule

    Line 1 west extension to open by 2023

    Staggered openings were planned: Line 2 south in 2021, Line 1 east in 2022 and Line 1 west in 2023.

    City of Ottawa (council)Railway Track & Structures[1]CTV News Ottawa[3]

  8. 2015
    Cost

    Council approves $3B for Stage 2

    Earliest figure found. Global News later reported the project was initially pegged at $3.4 billion and CTV Ottawa reported $3.6 billion, so reporting of the starting figure differs.

    City of Ottawa (council)Railway Track & Structures[1]Railway Track & Structures[2]First price

In the news

Links to outside coverage. All news

Sources

  1. Railway Track & Structures, 9 Mar 2017
    “The budget for the Stage 2 LRT project remains CA$3 billion (US$2.2 billion), as approved in 2015.”
    “The Stage 2 project is planned to proceed with staggered openings to allow for faster expansions to LRT service and will see the Trillium Line South extension opening in 2021, the Confederation Line East including Trim opening in 2022 and the Confederation Line West to Moodie opening by 2023.”
  2. Railway Track & Structures, 21 Feb 2017
    “The Stage 2 LRT Project budget is CA$3 billion (US$2.28 billion) and excludes the Trim Extension with one station at CA$160 million (US$121.6 million) and the Airport Rail Link with two stations at CA$155 million (US$117.8 million).”
  3. CTV News Ottawa, 22 Feb 2019
    “The Director of O-Train Planning, Chris Swail, says the original deadline of 2023 was an ‘aggressive target’ set in 2017.”
    “The project, which will see LRT taken west to Moodie, east to Trim Rd., and extend the O-Train Trillium Line to Riverside South, is also delayed by two years to 2025.”
  4. Global News, 6 Mar 2019
    “The $4.66-billion project was initially pegged at $3.4 billion, a shift of over $1.2 billion.”
  5. CBC News, 17 Nov 2023
    “That was already out the window by the time council approved the $4.66-billion budget in 2019.”
    “The latest report to councillors confirms the situation has grown worse, with the city now on the hook for 51 per cent of the $4.91-billion funding plan.”
    “Ottawa's light-rail transit system is again bursting beyond its budget, with members of the city's finance committee meeting to rubber stamp an additional $152 million based on new, unforeseen costs.”
    “It will also extend the eastern and western ends of the Confederation Line, with the completion of those projects now set for early 2025 and late 2026, respectively.”
  6. CBC News, 6 Dec 2024
    “Trillium Line to reopen in stages starting Monday, Jan. 6”
    “The Trillium Line was originally meant to reopen in 2022 but has faced numerous delays.”
  7. CTV News Ottawa, 6 Aug 2026
    “Speaking to CTV News Ottawa’s Leah Larocque on Wednesday, director of rail construction Richard Holder said OC Transpo and the constructor, KEV, continue to assess the damage caused by the storm and are considering options for the line, which is currently slated to open sometime in 2027.”