Ottawa LRT Stage 2
The second stage of Ottawa's O-Train system, extending Line 1 east to Trim and west to Moodie and extending Line 2 (Trillium Line) south to Limebank and north to Bayview. Owned by the City of Ottawa with federal and provincial funding.
Ottawa LRT Stage 2 was first priced at $3 billion in 2015 by the City of Ottawa. The latest official estimate is $4.91 billion (2023, the City of Ottawa), 1.3 times the first price after adjusting for inflation. The completion target has moved 4 years, from 2023 to 2027.
Also called: O-Train Stage 2, Confederation Line extension, Trillium Line extension
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.3×the first quoted price released to the public
- First price 2015, City of Ottawa
- Latest estimate 2023, City of Ottawa
Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,350
- Status
- Under construction
- Owner
- City of Ottawa
- Scope
- Unchanged
Every estimate
Government Project owner
3 public cost estimates from 2015 to 2023.
Schedule
- Original completion targetSet in 2017
- 2023
- Current completion targetSet in 2026
- 2027
- Delay
- 4 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 5 Aug 2026Schedule
Line 1 west extension now slated for 2027
Flood damage is being assessed.
OC Transpo (director of rail construction Richard Holder)CTV News Ottawa[7]
- 6 Dec 2024Milestone
Line 2 south extension to open in stages from Jan. 6, 2025
The first section of Stage 2 to open. The line grows from 8 km to 23 km with 11 stations, according to CBC.
OC TranspoCBC News[6]
- 17 Nov 2023Cost
Funding plan reaches $4.91B
Includes unforeseen costs above the contingency fund. CBC reports the report suggested further city investment might be necessary.
City of Ottawa (staff report)CBC News[5]
- Nov 2023Schedule
East extension early 2025, west late 2026
The target date shown is for the west extension, the later of the two.
City of Ottawa (staff)CBC News[5]
- 6 Mar 2019Cost
Council approves $4.66B
The project had grown from 30 km of track to 44 km and from 19 stations to 24, according to CBC.
City of Ottawa (council)Global News[4]CBC News[5]
- 22 Feb 2019Schedule
Completion pushed to 2025
CBC reported the Trillium Line would open first, in fall 2022, with the east extension by fall 2024 and the west extension in spring 2025.
City of Ottawa (staff)CTV News Ottawa[3]
- Mar 2017Schedule
Line 1 west extension to open by 2023
Staggered openings were planned: Line 2 south in 2021, Line 1 east in 2022 and Line 1 west in 2023.
City of Ottawa (council)Railway Track & Structures[1]CTV News Ottawa[3]
- 2015Cost
Council approves $3B for Stage 2
Earliest figure found. Global News later reported the project was initially pegged at $3.4 billion and CTV Ottawa reported $3.6 billion, so reporting of the starting figure differs.
City of Ottawa (council)Railway Track & Structures[1]Railway Track & Structures[2]First price
In the news
- Track upgrades needed prior to pre-trial running for O-Train Line 1 East Extension: OC Transpo
CTV News, 18 Nov 2026
- All Line 1 trains to do test runs to Trim station starting Nov. 22
CBC News, 5 Nov 2026
Links to outside coverage. All news
Sources
- Railway Track & Structures, 9 Mar 2017
“The budget for the Stage 2 LRT project remains CA$3 billion (US$2.2 billion), as approved in 2015.”
“The Stage 2 project is planned to proceed with staggered openings to allow for faster expansions to LRT service and will see the Trillium Line South extension opening in 2021, the Confederation Line East including Trim opening in 2022 and the Confederation Line West to Moodie opening by 2023.”
- Railway Track & Structures, 21 Feb 2017
“The Stage 2 LRT Project budget is CA$3 billion (US$2.28 billion) and excludes the Trim Extension with one station at CA$160 million (US$121.6 million) and the Airport Rail Link with two stations at CA$155 million (US$117.8 million).”
- CTV News Ottawa, 22 Feb 2019
“The Director of O-Train Planning, Chris Swail, says the original deadline of 2023 was an ‘aggressive target’ set in 2017.”
“The project, which will see LRT taken west to Moodie, east to Trim Rd., and extend the O-Train Trillium Line to Riverside South, is also delayed by two years to 2025.”
- Global News, 6 Mar 2019
“The $4.66-billion project was initially pegged at $3.4 billion, a shift of over $1.2 billion.”
- CBC News, 17 Nov 2023
“That was already out the window by the time council approved the $4.66-billion budget in 2019.”
“The latest report to councillors confirms the situation has grown worse, with the city now on the hook for 51 per cent of the $4.91-billion funding plan.”
“Ottawa's light-rail transit system is again bursting beyond its budget, with members of the city's finance committee meeting to rubber stamp an additional $152 million based on new, unforeseen costs.”
“It will also extend the eastern and western ends of the Confederation Line, with the completion of those projects now set for early 2025 and late 2026, respectively.”
- CBC News, 6 Dec 2024
“Trillium Line to reopen in stages starting Monday, Jan. 6”
“The Trillium Line was originally meant to reopen in 2022 but has faced numerous delays.”
- CTV News Ottawa, 6 Aug 2026
“Speaking to CTV News Ottawa’s Leah Larocque on Wednesday, director of rail construction Richard Holder said OC Transpo and the constructor, KEV, continue to assess the damage caused by the storm and are considering options for the line, which is currently slated to open sometime in 2027.”