Mackenzie Valley Highway

An all-season road down the Mackenzie Valley from Wrigley, N.W.T., replacing winter roads: first 321 km to Norman Wells, then on to Inuvik. Proposed in some form for over 50 years; the Government of the Northwest Territories is the proponent.

Mackenzie Valley Highway was first priced at $700 million in 2005 by the Government of the Northwest Territories. The latest official estimate is $3.65 billion (2026, the Government of the Northwest Territories), 3.3 times the first price after adjusting for inflation.

Also called: Mackenzie Valley all-season road

Reviewed monthly. Last review: 5 Nov 2026. How we update

3.3×the first quoted price released to the public

First price 2005, Government of the Northwest Territories
$1.1B
Latest estimate 2026, Government of the Northwest Territories
$3.7B

Adjusted for inflation to 2026 dollars.

Days since announced
8,002
Status
Planning
Owner
Government of the Northwest Territories, with federal funding
Scope
Changed in 2013

Every estimate

Government

4 public cost estimates from 2005 to 2026.

Schedule

Opening target
Set in 2026
2032
Delay
None so far

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 8 Sep 2026
    Milestone

    $405M federal, the largest yet

    Government of Canada (Ministers MacKinnon and Alty)Cabin Radio[8]

  2. 8 Sep 2026
    Schedule

    Open by 2032 (Wrigley-Norman Wells)

    First phase, to Norman Wells. The Inuvik section has no date.

    Government of the Northwest TerritoriesCabin Radio[8]

  3. 4 Mar 2026
    Cost

    $1.65B to Norman Wells plus about $2B to Inuvik

    Both phases added together, to compare with earlier whole-route estimates.

    Government of the Northwest Territories (presenters at community meetings)CBC News[7]Sum of $1.65B + $2B

  4. 27 Jun 2018
    Milestone

    $102.5M federal: Great Bear River bridge and first 15 km

    Government of CanadaCBC News[6]

  5. 9 Oct 2013
    Scope

    Tuktoyaktuk leg split off as its own road

    The Inuvik-Tuktoyaktuk section was built as a separate highway (opened 2017). The remaining project runs from Wrigley to the Dempster Highway/Inuvik.

    Government of the Northwest TerritoriesCBC News[4]CBC News[5]

  6. 6 Jun 2013
    Cost

    $1.7B to complete (2012 dollars)

    Government of the Northwest Territories (Corridors for Canada III)GNWT, Corridors for Canada III (tabled document 102-17(4))[3]CBC News[4]

  7. 16 Sep 2009
    Cost

    $1.67B, Wrigley to Tuktoyaktuk

    GNWT Department of TransportationGNWT Department of Transportation (Mackenzie Valley All-Weather Road Economic Analysis)[2]

  8. 2005
    Cost

    $700M

    From the territory's 2005 'Connecting Canada' proposal, as reported later. It then included the road on to Tuktoyaktuk.

    Government of the Northwest Territories ('Connecting Canada', 2005)Alan Windhorst, University of Alberta (conference paper), citing GNWT[1]First price

Sources

  1. Alan Windhorst, University of Alberta (conference paper), citing GNWT, 13 Jul 2006
    “The GNWT (Connecting Canada, 2005, p.6) estimates the costs to be $700 million.”
  2. GNWT Department of Transportation (Mackenzie Valley All-Weather Road Economic Analysis), 16 Sep 2009
    “The total estimated cost of building the AWR including costs for engineering design is approximately $1.67 billion, of which $1.3 billion is for road building, $223 million is for bridge construction, and $178 million is for engineering.”
  3. GNWT, Corridors for Canada III (tabled document 102-17(4)), 6 Jun 2013
    “Continued support for the Mackenzie Valley Highway project, a major corridor estimated to cost $1.7 billion to complete (2012 $s), is crucial to ensure resource development in the NWT contributes to selfreliant communities and a strong and prosperous nation”
  4. CBC News, 9 Oct 2013
    “The Government of the Northwest Territories says it will cost about $1.7 billion to extend the Mackenzie Valley Highway to the Dempster Highway.”
  5. CBC News, 14 Sep 2016
    “The $300-million highway to Tuktoyaktuk is still expected to open in the fall of 2017, after some summer 2017 construction work to finalize the grading and install the road's grav”
  6. CBC News, 27 Jun 2018
    “The federal government has announced it is investing $102.5 million in Northwest Territories' Mackenzie Valley Highway project, aimed to construct a bridge over the Great Bear River as well as an all-weather road.”
  7. CBC News, 5 Mar 2026
    “The cost for the first phase to Norman Wells is estimated at $1.65 billion. An additional $2 billion could be needed to complete planning and construction to Inuvik.”
  8. Cabin Radio, 8 Sep 2026
    “The federal government is investing $405 million to advance design work on the Mackenzie Valley Highway and the building of related bridges – the biggest investment yet in the project.”
    “Under the GNWT’s proposed schedule, the Mackenzie Valley Highway could be fully constructed and open for use by 2032, meaning construction would begin in 2028.”

How we count