Montreal Metro Blue Line extension

A 5.8 km, five-station eastward extension of the Montreal Metro's Blue Line from Saint-Michel to Anjou, built by the STM with provincial and federal money.

Montreal Metro Blue Line extension was first priced at $3.9 billion in 2018 by Governments of Canada and Quebec, City of Montreal. The latest official estimate is $7.6 billion (2024, Société de transport de Montréal), 1.6 times the first price after adjusting for inflation. The opening target has moved 5 years, from 2026 to 2031.

Also called: ligne bleue, prolongement de la ligne bleue

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.6×the first quoted price released to the public

First price 2018, Governments of Canada and Quebec, City of Montreal
$5B
Latest estimate 2024, Société de transport de Montréal
$8.1B

Adjusted for inflation to 2026 dollars.

Days since announced
3,156
Status
Under construction
Owner
Société de transport de Montréal
Scope
Unchanged

Every estimate

Government Project owner Other

4 public cost estimates from 2018 to 2024.

Schedule

Original opening target
Set in 2018
2026
Current opening target
Set in 2024
2031
Delay
5 years

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 4 Sep 2024
    Status

    Main construction begins

    Société de transport de MontréalThe Suburban[4]

  2. 23 Aug 2024
    Cost

    STM: $7.6B

    Société de transport de MontréalThe Suburban[4]

  3. 23 Aug 2024
    Schedule

    Trains now expected in 2031

    Société de transport de MontréalThe Suburban[4]

  4. 18 Mar 2022
    Cost

    $6.4B

    Government of QuebecCBC News[3]

  5. 18 Mar 2022
    Schedule

    Opening 2029

    Government of QuebecThe Canadian Press, via The Globe and Mail[1]

  6. 12 May 2021
    Cost

    Documents: about $6B

    Radio-Canada (internal documents)CBC News[2]

  7. 9 Apr 2018
    Cost

    Announced: five stations for $3.9B

    The extension was also announced in 2009 and 2013; earlier figures are not yet sourced (see RESEARCH_TODO).

    Governments of Canada and Quebec, City of MontrealThe Canadian Press, via The Globe and Mail[1]First price

  8. 9 Apr 2018
    Schedule

    Opening by 2026

    Governments of Canada and Quebec, City of MontrealThe Canadian Press, via The Globe and Mail[1]

Sources

  1. The Canadian Press, via The Globe and Mail, 18 Mar 2022
    “Four years ago, then-premier Philippe Couillard was accompanied by Ms. Plante, Mr. Rodriguez and Prime Minister Justin Trudeau to announce that five stations serving the city’s east end would be complete by 2026 at a cost of $3.9-billion.”
    “The long-planned extension of a Montreal subway line will open in 2029 and cost some $6.4-billion, government officials said Friday.”
  2. CBC News, 12 May 2021
    “According to documents obtained by Radio-Canada, the updated price tag is estimated around $6 billion as sky-high expropriation costs put the future of the project in question.”
  3. CBC News, 18 Mar 2022
    “The cost of the Blue line extension has ballooned, now estimated to be $6.4 billion, and construction is expected to be completed in 2029.”
  4. The Suburban, 4 Sep 2024
    “The STM also told reporters that the price tag has gone up more than $1 billion since its last estimate, and the project, expected to service almost 70,000 passengers daily, and feature up to 2,000 workers, is now expected to cost $7.6 billion.”
    “The Société de transport de Montréal (STM) announced last week that the project, first envisioned some 36 year ago and slated for completion in 2026, and since twice delayed, has been delayed another year with train cars expected to roll in 2031.”
    “It all comes with a fair share of detours as digging begins this month, and Jean-Talon traffic will be exacerbated for at least the next 24 months, as new structures are constructed at Langelier, Lacordaire and Pie-IX.”