Montreal Metro Blue Line extension
A 5.8 km, five-station eastward extension of the Montreal Metro's Blue Line from Saint-Michel to Anjou, built by the STM with provincial and federal money.
Montreal Metro Blue Line extension was first priced at $3.9 billion in 2018 by Governments of Canada and Quebec, City of Montreal. The latest official estimate is $7.6 billion (2024, Société de transport de Montréal), 1.6 times the first price after adjusting for inflation. The opening target has moved 5 years, from 2026 to 2031.
Also called: ligne bleue, prolongement de la ligne bleue
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.6×the first quoted price released to the public
- First price 2018, Governments of Canada and Quebec, City of Montreal
- Latest estimate 2024, Société de transport de Montréal
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,156
- Status
- Under construction
- Owner
- Société de transport de Montréal
- Scope
- Unchanged
Every estimate
Government Project owner Other
4 public cost estimates from 2018 to 2024.
Schedule
- Original opening targetSet in 2018
- 2026
- Current opening targetSet in 2024
- 2031
- Delay
- 5 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 4 Sep 2024Status
Main construction begins
Société de transport de MontréalThe Suburban[4]
- 23 Aug 2024Cost
STM: $7.6B
Société de transport de MontréalThe Suburban[4]
- 23 Aug 2024Schedule
Trains now expected in 2031
Société de transport de MontréalThe Suburban[4]
- 18 Mar 2022Cost
$6.4B
Government of QuebecCBC News[3]
- 18 Mar 2022Schedule
Opening 2029
Government of QuebecThe Canadian Press, via The Globe and Mail[1]
- 12 May 2021Cost
Documents: about $6B
Radio-Canada (internal documents)CBC News[2]
- 9 Apr 2018Cost
Announced: five stations for $3.9B
The extension was also announced in 2009 and 2013; earlier figures are not yet sourced (see RESEARCH_TODO).
Governments of Canada and Quebec, City of MontrealThe Canadian Press, via The Globe and Mail[1]First price
- 9 Apr 2018Schedule
Opening by 2026
Governments of Canada and Quebec, City of MontrealThe Canadian Press, via The Globe and Mail[1]
Sources
- The Canadian Press, via The Globe and Mail, 18 Mar 2022
“Four years ago, then-premier Philippe Couillard was accompanied by Ms. Plante, Mr. Rodriguez and Prime Minister Justin Trudeau to announce that five stations serving the city’s east end would be complete by 2026 at a cost of $3.9-billion.”
“The long-planned extension of a Montreal subway line will open in 2029 and cost some $6.4-billion, government officials said Friday.”
- CBC News, 12 May 2021
“According to documents obtained by Radio-Canada, the updated price tag is estimated around $6 billion as sky-high expropriation costs put the future of the project in question.”
- CBC News, 18 Mar 2022
“The cost of the Blue line extension has ballooned, now estimated to be $6.4 billion, and construction is expected to be completed in 2029.”
- The Suburban, 4 Sep 2024
“The STM also told reporters that the price tag has gone up more than $1 billion since its last estimate, and the project, expected to service almost 70,000 passengers daily, and feature up to 2,000 workers, is now expected to cost $7.6 billion.”
“The Société de transport de Montréal (STM) announced last week that the project, first envisioned some 36 year ago and slated for completion in 2026, and since twice delayed, has been delayed another year with train cars expected to roll in 2031.”
“It all comes with a fair share of detours as digging begins this month, and Jean-Talon traffic will be exacerbated for at least the next 24 months, as new structures are constructed at Langelier, Lacordaire and Pie-IX.”