Scarborough Subway Extension
A 7.8 km, three-stop extension of Toronto's Line 2 subway into Scarborough, replacing the Scarborough RT. Chosen by city council over a funded LRT in 2013, cut to one stop, then taken over by the province in 2019.
Scarborough Subway Extension was first priced at $3.56 billion in 2013 by the City of Toronto and TTC. The latest official estimate is $10.2 billion or more (2025, Metrolinx), 2.1 times the first price after adjusting for inflation. The opening target has moved 7 years, from 2023 to 2030.
Also called: Line 2 East Extension, SSE
Reviewed monthly. Last review: 5 Nov 2026. How we update
2.1×the first quoted price released to the public
- First price 2013, City of Toronto and TTC
- Latest estimate 2025, Metrolinx
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,805
- Status
- Under construction
- Owner
- Metrolinx
- Scope
- Changed in 2017, 2019
Every estimate
Government Project owner
2 public cost estimates from 2013 to 2025.
Left out because they measure something else: $5.5B construction cost, 2019.
Schedule
- Original opening targetSet in 2013
- 2023
- Current opening targetSet in 2025
- 2030
- Delay
- 7 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 24 Jun 2025Cost
Metrolinx: more than $10.2B
MetrolinxCTV News Toronto, via CP24[1]
- 24 Jun 2025Schedule
Service expected in 2030
MetrolinxCTV News Toronto, via CP24[1]
- 10 Apr 2019Scope
Province takes over, back to three stops
The province took over the project and restored three stops (Lawrence East, Scarborough Town Centre, McCowan).
Province of OntarioblogTO[3]
- 10 Apr 2019Cost
Province: $5.5B
Metrolinx later said this figure covered construction only.
Province of OntarioblogTO[3]
- 10 Apr 2019Schedule
Opening "before 2030"
Stored as 2030, which gives the project the benefit of the doubt.
Province of OntarioblogTO[3]
- 2017Scope
- 2013Cost
Three-stop subway first estimated at $3.56B
City figure in year-of-expenditure dollars (it allows for future inflation). Council chose the subway over a funded LRT.
City of Toronto and TTCCTV News Toronto, via CP24[1]First price
- 2013Schedule
Opening planned for 2023
From the TTC's capital plans, as analysed by transit writer Steve Munro.
Sources
- CTV News Toronto, via CP24, 24 Jun 2025
“The initial estimate for building the three-station project when it was first proposed back in 2013 was $3.56 billion.”
“Scarborough’s subway extension will cost more than $10.2 billion, nearly double the initial estimate announced by the province six years ago, according to updated figures from Metrolinx.”
“The transit line isn’t expected to be up and running until 2030, but a progress report on the project says the tunnel’s boring machine, dubbed “Diggy Scardust,” is progressing well and averaging 12 metres per day.”
- Steve Munro, 3 Mar 2017
“This corresponds to the original scheme to open the line in 2023, but not to the current fleet plan.”
- blogTO, 10 Apr 2019
“And then how, in 2017, they voted again to scale the extension back to just one station?”
“Set to open sometime "before 2030," the new extension will cost $5.5 billion to build and will include stops at Lawrence East Station, Scarborough Town Centre Station and McCowan Station, according to the province.”