Scarborough Subway Extension

A 7.8 km, three-stop extension of Toronto's Line 2 subway into Scarborough, replacing the Scarborough RT. Chosen by city council over a funded LRT in 2013, cut to one stop, then taken over by the province in 2019.

Scarborough Subway Extension was first priced at $3.56 billion in 2013 by the City of Toronto and TTC. The latest official estimate is $10.2 billion or more (2025, Metrolinx), 2.1 times the first price after adjusting for inflation. The opening target has moved 7 years, from 2023 to 2030.

Also called: Line 2 East Extension, SSE

Reviewed monthly. Last review: 5 Nov 2026. How we update

2.1×the first quoted price released to the public

First price 2013, City of Toronto and TTC
$4.9B
Latest estimate 2025, Metrolinx
$11B+

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
4,805
Status
Under construction
Owner
Metrolinx
Scope
Changed in 2017, 2019

Every estimate

Government Project owner

2 public cost estimates from 2013 to 2025.

Left out because they measure something else: $5.5B construction cost, 2019.

Schedule

Original opening target
Set in 2013
2023
Current opening target
Set in 2025
2030
Delay
7 years

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 24 Jun 2025
    Cost

    Metrolinx: more than $10.2B

    MetrolinxCTV News Toronto, via CP24[1]

  2. 24 Jun 2025
    Schedule

    Service expected in 2030

    MetrolinxCTV News Toronto, via CP24[1]

  3. 10 Apr 2019
    Scope

    Province takes over, back to three stops

    The province took over the project and restored three stops (Lawrence East, Scarborough Town Centre, McCowan).

    Province of OntarioblogTO[3]

  4. 10 Apr 2019
    Cost

    Province: $5.5B

    Metrolinx later said this figure covered construction only.

    Province of OntarioblogTO[3]

  5. 10 Apr 2019
    Schedule

    Opening "before 2030"

    Stored as 2030, which gives the project the benefit of the doubt.

    Province of OntarioblogTO[3]

  6. 2017
    Scope

    Cut to one stop

    Cut back to a single stop at Scarborough Town Centre.

    Toronto City CouncilblogTO[3]

  7. 2013
    Cost

    Three-stop subway first estimated at $3.56B

    City figure in year-of-expenditure dollars (it allows for future inflation). Council chose the subway over a funded LRT.

    City of Toronto and TTCCTV News Toronto, via CP24[1]First price

  8. 2013
    Schedule

    Opening planned for 2023

    From the TTC's capital plans, as analysed by transit writer Steve Munro.

    TTCSteve Munro[2]

Sources

  1. CTV News Toronto, via CP24, 24 Jun 2025
    “The initial estimate for building the three-station project when it was first proposed back in 2013 was $3.56 billion.”
    “Scarborough’s subway extension will cost more than $10.2 billion, nearly double the initial estimate announced by the province six years ago, according to updated figures from Metrolinx.”
    “The transit line isn’t expected to be up and running until 2030, but a progress report on the project says the tunnel’s boring machine, dubbed “Diggy Scardust,” is progressing well and averaging 12 metres per day.”
  2. Steve Munro, 3 Mar 2017
    “This corresponds to the original scheme to open the line in 2023, but not to the current fleet plan.”
  3. blogTO, 10 Apr 2019
    “And then how, in 2017, they voted again to scale the extension back to just one station?”
    “Set to open sometime "before 2030," the new extension will cost $5.5 billion to build and will include stops at Lawrence East Station, Scarborough Town Centre Station and McCowan Station, according to the province.”