Bipole III transmission line
A 500-kilovolt direct current transmission line of about 1,400 km running from northern Manitoba down the west side of the province to the Riel converter station near Winnipeg, built by Manitoba Hydro. It entered service in 2018.
Bipole III transmission line was first priced at $2.2 billion in 2007 by Manitoba Hydro. The final cost was $5.04 billion (2018, Manitoba Hydro), 1.9 times the first price after adjusting for inflation. It was completed 1 year after the original completion target of 2017.
Also called: Bipole 3
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.9×the first quoted price released to the public
- First price 2007, Manitoba Hydro
- Final cost 2018, Manitoba Hydro
Adjusted for inflation to 2026 dollars.
- Days since announced
- 7,272
- Status
- Complete
- Owner
- Manitoba Hydro
- Scope
- Unchanged
Every estimate
Project owner
6 public cost estimates from 2007 to 2018.
Schedule
- Original completion targetSet in 2010
- 2017
- Completed
- 2018
- Delay
- 1 year
A target given only as a year counts as the end of that year.
Route
Timeline
- 2018Cost
Final estimate: $5.04B
From the 2017-18 annual report, after the line entered service.
Manitoba Hydro (2017-18 annual report)CBC News[1]
- 2018Status
Line completed in 2018
Manitoba HydroCBC News[1]
- 19 Jun 2017Schedule
In service by July 2018
Manitoba HydroSteinbachOnline[6]
- 21 Sep 2016Cost
Board review: $4.9B to $5B
The same review projected a delay of 12 to 15 months.
Manitoba Hydro-Electric Board (review)Government of Manitoba[5]
- 22 Sep 2014Cost
Budget raised to $4.65B
Reported at the time as $4.6B. The province later cited the exact budget as $4.65B.
Manitoba HydromySteinbach[4]Government of Manitoba[5]
- 31 Mar 2011Cost
Revised to $3.28B
Includes the line and the two converter stations, whose estimate rose from $1.16B to $1.83B.
Manitoba HydroCanadian Centre for Policy Alternatives[3]
- 22 Sep 2010Schedule
In service by 2017
From Manitoba Hydro's published project schedule, with construction to start in late 2012.
Manitoba HydroCanadian Centre for Policy Alternatives[2]
- 25 Aug 2010Cost
West route still put at $2.247B
From a letter by Hydro's CEO to the Brandon Sun. Leaked internal documents at the time put the cost near $4B, which Hydro denied.
Manitoba Hydro (Bob Brennan, CEO)Canadian Centre for Policy Alternatives[2]
- 2007Cost
First estimate: $2.2B
The figure in place when the province directed Hydro to route the line down the west side of Manitoba.
Manitoba HydroCBC News[1]First price
Sources
- CBC News, 31 Oct 2019
“The cost for the project was originally pegged in 2007 at $2.2 billion.”
“In its 2018 annual report, Hydro said the total estimated cost was $5.04 billion”
“The Bipole III transmission line was completed in 2018”
- Canadian Centre for Policy Alternatives, 22 Sep 2010
““In fact, Manitoba Hydro has estimated that the west side route will be $2.247 billion, while the cost of an east side route would be $1,837 billion.”
“In-service Date: 2017”
- Canadian Centre for Policy Alternatives, 7 Apr 2011
“The revised estimate raised the total cost from $2.24 billion to $3.28 billion.”
- mySteinbach, 22 Sep 2014
“Steinbach MLA, Kelvin Goertzen, says the acknowledgement that the Bipole III hydro transmission line has now doubled in price to $4.6 billion is a further insult to the residents of the southeast and to all Manitobans who will be forced to pay for this boondoggle for years to come.”
- Government of Manitoba, 21 Sep 2016
“the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion”
- SteinbachOnline, 19 Jun 2017
“The anticipated in-service date for Bipole III is July 2018.”