SAAQclic

The Quebec auto insurance board's IT overhaul, including the SAAQclic online platform. Its 2023 launch caused months of disruption and led to a public inquiry, the Gallant commission.

SAAQclic was first priced at $200 million in 2015 by SAAQ. The latest official estimate is $638 million (2017, SAAQ), 3.1 times the first price after adjusting for inflation.

Also called: CASA, Gallant commission

Reviewed monthly. Last review: 5 Nov 2026. How we update

3.1×the first quoted price released to the public

First price 2015, SAAQ
$269M
Latest estimate 2017, SAAQ
$834M
Watchdog estimate 2025, Auditor General of Quebec
$1.1B+

The watchdog’s figure is 37% higher than the latest official estimate.

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
4,260
Status
Operational
Owner
Société de l'assurance automobile du Québec
Scope
Unchanged

Every estimate

Project owner Watchdog

3 public cost estimates from 2015 to 2025.

Location

Timeline

  1. 20 Feb 2025
    Cost

    Auditor General: over $1.1B

    Auditor General of Quebec (Guylaine Leclerc)CBC News[2]

  2. 2023
    Status

    SAAQclic launched, with major disruptions

    SAAQInsurance Business[3]

  3. 2017
    Cost

    Budget set at $638M

    SAAQCBC News[2]

  4. Apr 2015
    Cost

    First estimate: $200M over 10 years

    From the SAAQ's April 2015 request to the Treasury Board, made public at the Gallant inquiry in 2025.

    SAAQ (CEO Nathalie Tremblay) and Quebec Transport Minister Robert PoëtiLa Presse canadienne, via Noovo Info[1]First price

Sources

  1. La Presse canadienne, via Noovo Info, 1 May 2025
    “Selon la demande signée par la PDG de la SAAQ et le ministre des Transports de l'époque, Nathalie Tremblay et Robert Poëti, la modernisation des systèmes informatiques de l'organisation était évaluée à 200 millions $ sur 10 ans.”
  2. CBC News, 20 Feb 2025
    “Leclerc found that in 2017, when the SAAQ began an attempt to digitize its services, it budgeted $638 million over a 10-year period to, among other things, build the online SAAQclic platform.”
    “The true cost of the SAAQ's digitization attempt is now likely to climb over $1.1 billion, Leclerc found.”
  3. Insurance Business, 29 Apr 2025
    “Instead, its launch in 2023 led to widespread service disruptions, including long wait times at in-person service centres.”

How we count