Taltson Hydro Expansion
Expanding the Taltson hydro plant south of Great Slave Lake to about 60 MW and linking it to the Snare/Yellowknife grid with a cable under the lake. Pursued in several forms since the 2000s by the Government of the Northwest Territories and its power corporation.
Taltson Hydro Expansion was first priced at up to $700 million in 2013 by the Government of the Northwest Territories. The latest official estimate is $2 billion to $3 billion (2025, Strategic Infrastructure Minister Caroline Wawzonek), 2.7 times the first price after adjusting for inflation.
Reviewed monthly. Last review: 5 Nov 2026. How we update
2.7×the first quoted price released to the public
- First price 2013, Government of the Northwest Territories
- Latest estimate 2025, Strategic Infrastructure Minister Caroline Wawzonek
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 6,163
- Status
- Planning
- Owner
- Government of the Northwest Territories
- Scope
- Changed in 2013, 2025
Every estimate
Government Project owner Other
5 public cost estimates from 2010 to 2025.
Schedule
- Completion targetSet in 2024
- 2033
- Delay
- None so far
A target given only as a year counts as the end of that year.
Route
Timeline
- 9 Jun 2025Cost
Now $2-3B
Strategic Infrastructure Minister Caroline WawzonekCabin Radio[8]CBC News[9]
- 9 Jun 2025Scope
Current scope: tripled capacity and a link to the Snare grid
Expand generation to about 60 MW and connect the Taltson and Snare grids with a cable under Great Slave Lake.
Government of the Northwest TerritoriesCanada's National Observer[10]
- 13 Nov 2024Schedule
In operation by 2033
GNWT (David Mahon, senior engineer)Cabin Radio[7]
- 23 Jan 2019Status
Studies restart with $1.2M
Governments of Canada and the N.W.T.CBC News[6]
- 11 Mar 2016Cost
Saskatchewan option: 'over $500 million'
N.W.T. Power Corporation (Sebert)CBC News[5]
- 27 Oct 2014Cost
Business case: $1.2B, 'not economically viable'
Finance Minister Michael Miltenberger (business case)CBC News[4]
- 27 Oct 2014Status
Plan shelved
Finance Minister Michael MiltenbergerCBC News[4]
- 18 Oct 2013Cost
Up to $700M to expand Taltson
The first figure from the government, given by the premier and finance minister.
Government of the Northwest TerritoriesCBC News[3]First price
- 18 Oct 2013Scope
Goal shifts to linking northern hydro with the southern grid
Rescoped from powering the diamond mines to connecting N.W.T. hydro with grids to the south.
Premier Bob McLeodCBC News[3]
- 2 Mar 2011Status
Dezé project put on hold
Premier Floyd RolandCBC News[2]
- 14 Jan 2010Cost
Dezé plan: $500-600M with a line to the diamond mines
Not attributed to anyone, so not used as the first price. Proposed by Dezé Energy, part-owned by the territory's power corporation.
CBC News (estimator not named; Dezé Energy proposal)CBC News[1]
Sources
- CBC News, 14 Jan 2010
“Expanding the dam, as well as building a power line that would connect the facility to the N.W.T.'s diamond mines, is estimated to cost between $500 million and $600 million.”
- CBC News, 2 Mar 2011
“A major hydroelectric expansion project in the Northwest Territories is being put on hold because it is not viable at this time, says Premier Floyd Roland.”
- CBC News, 18 Oct 2013
“Hydro expansion in the South Slave could cost as much as $700 million, but the territory doesn't have enough borrowing power to start another mega project now.”
“Bob McLeod says building transmission lines to connect northern power with the southern grid will be the territorial government's biggest project in the second half of its term.”
- CBC News, 27 Oct 2014
“Officials completed a business case this year and found it would cost $1.2 billion, more than double what was initially estimated.”
“"But at $1.2 billion, it's just not economically viable for us so we have to look at a plan B.””
- CBC News, 11 Mar 2016
“"The likely cost of the project would probably be over $500 million, perhaps between that and a billion dollars," said Sebert.”
- CBC News, 23 Jan 2019
“The federal and Northwest Territories governments are investing $1.2 million into preliminary work for a proposed expansion of the Taltson Hydroelectricity Expansion Project.”
- Cabin Radio, 13 Nov 2024
“Senior GNWT engineer David Mahon, elaborating on a possible timeline, said: “We would like to be in operation in 2033.””
- Cabin Radio, 10 Jun 2025
“One of the NWT government’s signature infrastructure projects is now expected to cost between $2 billion and $3 billion, Caroline Wawzonek told Yellowknife city council on Monday.”
- CBC News, 11 Jun 2025
“"I mean, we're into the billions, somewhere between $2 billion and $3 billion,"”
- Canada's National Observer, 30 Mar 2026
“The expansion project is estimated to cost between $2 and $3 billion and include two initiatives: nearly tripling the generation station's capacity to 60 MW, which could be enough to power between 32,000 and 70,000 homes, and connecting the Taltson grid to the Snare grid through an underwater cable across Great Slave Lake.”