Toronto-York Spadina Subway Extension
An 8.6 km, six-station extension of Toronto's Line 1 subway from Downsview to Vaughan Metropolitan Centre, built by the TTC with federal, provincial, Toronto and York Region money.
Toronto-York Spadina Subway Extension was first priced at $2.09 billion in 2008 by TTC. The latest official estimate is $3.18 billion (2016, TTC), 1.3 times the first price after adjusting for inflation. It opened 2 years after the original opening target of 2015.
Also called: TYSSE
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.3×the first quoted price released to the public
- First price 2008, TTC
- Latest estimate 2016, TTC
Adjusted for inflation to 2026 dollars.
- Days since announced
- 6,847
- Status
- Operational
- Owner
- TTC
- Scope
- Unchanged
Every estimate
Government
2 public cost estimates from 2008 to 2016.
Schedule
- Original opening targetSet in 2008
- 2015
- Opened
- 17 Dec 2017
- Delay
- 2 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 17 Dec 2017Status
Opened to the public
- 15 Jan 2016Cost
Budget now $3.18B
TTC (CEO Andy Byford)CBC News[2]
- 15 Jan 2016Schedule
Now December 31, 2017
TTC (CEO Andy Byford)CBC News[2]
- Dec 2014Schedule
Now fall 2016
TTC (CEO's report)Steve Munro (quoting the TTC CEO's report)[1]
- Mar 2008Cost
Estimated at $2.09B (2006 dollars)
From the TTC's March 2008 report on project delivery. The same report put the cost at $2.633B in year-of-expenditure dollars.
TTCSteve Munro (quoting the TTC's March 2008 report)[1]First price
- 2008Schedule
Opening expected 2015
Sources
- Steve Munro (quoting the TTC's March 2008 report), 14 Mar 2015
“The estimated cost of the Project, unescalated (July 2006$), is $2.090 billion.”
“The line was originally expected to open in 2015, even in early rosy estimates before the Pan Am Games, but now will not be in service until 2017.”
“The in-service date is targeted for the fall of 2016 however the project is facing a serious schedule challenge.”
- CBC News, 15 Jan 2016
“Total budget now $3.184 billion.”
“BREAKING: TTC says an additional $400 million needed to complete York-Spadina extension by Dec 31 2017.”
- CP24, via City of Vaughan news clippings, 17 Dec 2017
“Toronto-York Spadina Subway Extension officially opens to public Cp24.com Codi Wilson Dec. 17, 2017 A new subway that will take commuters from Vaughan to Union Station in an estimated 42 minutes officially opened to the public today.”