Contrecœur Container Terminal

A new container terminal for the Port of Montréal at Contrecœur, about 40 km downstream, on federal land managed by the Montreal Port Authority. In-water works began in October 2025; commercial operations are targeted for 2030.

Contrecœur Container Terminal was first priced at $750 million in 2019 by Montreal Port Authority. The latest official estimate is $2.3 billion (2025, Minister Dominic LeBlanc), 2.5 times the first price after adjusting for inflation. The completion target has moved 7 years, from 2023 to 2030.

Also called: Port of Montreal Contrecœur expansion, terminal de Contrecœur

Reviewed monthly. Last review: 5 Nov 2026. How we update

2.5×the first quoted price released to the public

First price 2019, Montreal Port Authority
$940M
Latest estimate 2025, Minister Dominic LeBlanc
$2.4B

Adjusted for inflation to 2026 dollars.

Days since announced
2,664
Status
Under construction
Owner
Montreal Port Authority
Scope
Unchanged

Every estimate

Government Project owner Other

5 public cost estimates from 2019 to 2025.

Schedule

Original completion target
Set in 2019
2023
Current completion target
Set in 2026
2030
Delay
7 years

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 6 Apr 2026
    Milestone

    $1.16B federal loan

    Canada Infrastructure BankCanada Infrastructure Bank[10]

  2. 6 Apr 2026
    Schedule

    Commercial operations targeted for 2030

    Canada Infrastructure BankCanada Infrastructure Bank[10]

  3. Oct 2025
    Status

    In-water construction begins

    Montreal Port AuthorityCanada Infrastructure Bank[10]

  4. 11 Sep 2025
    Cost

    Ottawa: $2.3B

    The port authority wouldn't confirm it, but said electrification had been added.

    Minister Dominic LeBlancBloomberg, via Transport Topics[8]Noovo Info[9]

  5. 11 Sep 2025
    Schedule

    Finished by 2030

    Minister Dominic LeBlancNoovo Info[9]

  6. 17 Feb 2025
    Cost

    Québec: 'a $1.5-billion project'

    Other outlets reported $1.6B the same day.

    Premier François Legault (Québec)Radio-Canada[7]

  7. 10 Oct 2023
    Milestone

    Ottawa adds up to $150M

    Transport CanadaThe Globe and Mail[6]

  8. 27 Apr 2023
    Announcement

    CEO: the 2019 estimate of $950M no longer holds

    He declined to confirm the $1.4B reported by The Globe and Mail.

    Montreal Port Authority (Martin Imbleau, CEO)Radio-Canada[4]

  9. 27 Apr 2023
    Cost

    Reported: about $1.4B

    From unnamed sources, not the port authority, so not used as the official figure.

    The Globe and Mail (unnamed sources)The Canadian Press, via CBC News[5]The Globe and Mail[6]

  10. 9 Jul 2021
    Cost

    $750M-950M

    Montreal Port AuthorityRadio-Canada[3]

  11. 9 Jul 2021
    Schedule

    In service by end of 2025

    Montreal Port AuthorityRadio-Canada[3]

  12. 2 Mar 2021
    Status

    Federal environmental approval

    Minister of Environment and Climate Change (Jonathan Wilkinson)CBC News[2]

  13. 2 Mar 2021
    Schedule

    Operational by 2024

    Montreal Port AuthorityCBC News[2]

  14. 14 Aug 2019
    Cost

    $750M

    Announced with a $300M Canada Infrastructure Bank loan. The port has since said its 2019 ceiling was $950M.

    Montreal Port Authority (with the Canada Infrastructure Bank)Maritime Magazine[1]First price

  15. 14 Aug 2019
    Schedule

    Terminal complete by 2023

    Montreal Port AuthorityMaritime Magazine[1]

Sources

  1. Maritime Magazine, 14 Aug 2019
    “The project is valued at $750 million.”
    “Once final regulatory approvals are made and a full financing package (involving the port, government and industry stakeholders) is assembled, the Montreal Port Authority would set the wheels in motion for new terminal completion by 2023,”
  2. CBC News, 2 Mar 2021
    “Wilkinson's approval was the last step of many in getting the project authorized, and now the port authority is ready to make a call for tenders with an aim to get the facility operational by 2024.”
  3. Radio-Canada, 9 Jul 2021
    “Le coût du nouveau terminal, estimé entre 750 et 950 millions de dollars, sera assumé en partie par la Banque de l’infrastructure du Canada, qui versera 300 millions de dollars, et par le gouvernement du Québec qui a promis 55 millions.”
    “Au moins trois consortiums seraient en lice pour décrocher la construction du nouveau terminal, dont la mise en service est prévue pour la fin de 2025.”
  4. Radio-Canada, 27 Apr 2023
    “En entrevue à l'émission Zone économie, le PDG du Port de Montréal, Martin Imbleau, a affirmé que l'estimation faite en 2019, soit un investissement de 950 millions de dollars, ne tenait plus.”
  5. The Canadian Press, via CBC News, 27 Apr 2023
    “The cost of the expansion of the Port of Montreal with a new terminal at Contrecoeur has risen from a $950-million ceiling to about $1.4 billion as a result of inflation, sources say.”
  6. The Globe and Mail, 10 Oct 2023
    “Lawrence River have ballooned to $1.4-billion, roughly 50 per cent more than the maximum $950-million calculated in 2019 before the COVID-19 crisis.”
    “The Port of Montreal has secured up to $150-million in federal funding for its container terminal expansion project in Contrecoeur, a key piece of transportation infrastructure needed to service markets in Quebec, Ontario and the U.S.”
  7. Radio-Canada, 17 Feb 2025
    “Mais c'est un projet de 1,5 milliard $ où le gouvernement du Québec met 130 millions $, donc...”
  8. Bloomberg, via Transport Topics, 11 Sep 2025
    “The cost of a new Port of Montreal terminal that Canadian Prime Minister Mark Carney says is in the national interest has soared to C$2.3 billion ($1.7 billion), according to a Cabinet minister.”
  9. Noovo Info, 11 Sep 2025
    “Jeudi, en annonçant que ce projet était maintenant inclus dans la liste des projets soutenus par le Bureau des grands projets, liste présentée à Edmonton par le premier ministre Mark Carney, le ministre Dominic LeBlanc a parlé à deux reprises d’un projet de 2,3 milliards $, soit une augmentation de 700 millions $ ou près de 44 %.”
    “On reconnaît qu'il y a un élément de financement public pour combler les montants nécessaires pour arriver à 2,3 milliards $ pour finir le projet d'ici 2030.”
  10. Canada Infrastructure Bank, 6 Apr 2026
    “Construction of critical in-water works including dredging, quay wall construction and other infrastructure required for vessel access and operations began in October 2025 and is being delivered by a joint venture between Aecon and Pomerleau.”
    “CONTRECŒUR – Canada’s largest east coast port expansion moves forward as the Canada Infrastructure Bank (CIB) is supporting the new Contrecoeur container terminal by loaning $1.16 billion to the Montreal Port Authority (MPA).”
    “Construction is expected to begin in 2027 on building out terminal and logistics infrastructure, with commercial operations targeted for 2030.”

How we count