Réseau express métropolitain
A 67-kilometre automated light-rail network linking downtown Montreal to the South Shore, Deux-Montagnes, the West Island and the airport. It is public money: CDPQ Infra is a subsidiary of Quebec's public pension fund manager (the Caisse), and Quebec and Canada contributed funding, including a $1.28B Canada Infrastructure Bank loan.
Réseau express métropolitain was first priced at $5.5 billion in 2016 by CDPQ Infra. The latest official estimate is $8.3 billion (2024, CDPQ Infra), 1.2 times the first price after adjusting for inflation.
Also called: REM Montreal light rail
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.2×the first quoted price released to the public
- First price 2016, CDPQ Infra
- Latest estimate 2024, CDPQ Infra
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,869
- Status
- Under construction
- Owner
- CDPQ Infra
- Scope
- Unchanged
Every estimate
Project owner
4 public cost estimates from 2016 to 2024.
Left out because they measure something else: $9.4B total project cost per Auditor General of Quebec, 2024.
Schedule
- Opening targetSet in 2016
- 2020
- Delay
- None so far
A target given only as a year counts as the end of that year.
Route
Timeline
- 8 Jun 2026Schedule
Airport branch due 2027
Three of four segments are in service. The airport station is being built by Aéroports de Montréal.
CDPQ InfraCDPQ Infra[9]
- 18 May 2026Milestone
Anse-à-l'Orme branch opens
CDPQ InfraMass Transit[8]
- 14 Nov 2025Milestone
Deux-Montagnes branch opens
Passenger service began on Nov. 17, 2025.
Government of Canada (Prime Minister)Prime Minister of Canada[7]
- 20 Nov 2024Cost
Auditor General: $9.4B
The Auditor General's series starts from $7B in 2018 and is not the same measure as CDPQ Infra's capital cost figures.
Auditor General of Quebec (Guylaine Leclerc)The Canadian Press, via CTV News[6]
- 14 Nov 2024Cost
Cost now $8.3B
CDPQ InfraCBC News[5]
- 13 Sep 2023Cost
Cost rises to $7.95B
CBC reports CDPQ Infra attributed the increase to the COVID-19 pandemic and inflation.
CDPQ InfraCBC News[4]
- 27 Jul 2023Milestone
South Shore branch opens to passengers
CDPQ InfraThe Globe and Mail[3]
- 8 Feb 2018Cost
Cost raised to $6.7B
- 26 Apr 2016Cost
Announced: about $5.5B
Announced by CDPQ Infra, a subsidiary of Quebec's public pension fund manager. The release said the financing would also require investments from the governments of Quebec and Canada.
CDPQ InfraCDPQ (La Caisse) news release[1]First price
- 26 Apr 2016Schedule
First trains by end of 2020
CDPQ InfraCDPQ (La Caisse) news release[1]
Sources
- CDPQ (La Caisse) news release, 26 Apr 2016
“The new network represents an investment of approximately $5.5 billion.”
“If all these steps are taken successfully, construction is currently expected to begin in the spring of 2017, so that the first trains can be in service towards the end of 2020.”
- Infrastructure Canada, Question Period Note, 21 Sep 2020
“On February 8, 2018, CDPQ Infra announced the selected consortia for the project's two main contracts, as well as an increase of $300 million to the total project cost, which is now $6.7 billion.”
- The Globe and Mail, 27 Jul 2023
“The first 17-kilometre branch of the Caisse’s Réseau express métropolitain (REM) light rail line will welcome dignitaries and media Friday and its first paying customers Monday”
- CBC News, 13 Sep 2023
“Montreal's REM cost rises 26% to $7.95B”
- CBC News, 14 Nov 2024
“CDPQ Infra said the total cost of the project is now $8.3 billion, up five per cent from last year.”
- The Canadian Press, via CTV News, 20 Nov 2024
“The estimated cost of the project has risen from $7 billion in 2018 to $9.4 billion in 2024, according to Quebec auditor general Guylaine Leclerc.”
- Prime Minister of Canada, 14 Nov 2025
“Stretching from downtown Montréal to Deux-Montagnes, the new 30-kilometre extension adds 14 stations to the network, expanding REM service to nearly 50 kilometres and a total of 19 stations.”
- Mass Transit, 20 May 2026
“The Anse-à-l’Orme branch began passenger service on the Réseau express métropolitain on May 18.”
- CDPQ Infra, 8 Jun 2026
“The last commissioning is scheduled for 2027 and will extend to the Montréal-Trudeau International Airport.”