Joint Support Ships

Two naval supply ships, HMCS Protecteur and HMCS Preserver, being built by Seaspan in Vancouver to replace the navy's ageing replenishment ships. The program was announced in 2004 for three ships, cancelled in 2008, and restarted for two.

Joint Support Ships was first priced at $2.1 billion in 2004 by the Government of Canada. The latest official estimate is $5 billion or more (2026, National Defence), 1.5 times the first price after adjusting for inflation. The first delivery target has moved 15 years, from 2012 to 2027.

Also called: JSS, Protecteur-class supply ships

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.5×the first quoted price released to the public

First price 2004, Government of Canada
$3.4B
Latest estimate 2026, National Defence
$5.1B+
Watchdog estimate 2013, Parliamentary Budget Officer
$5.7B

The most recent independent estimate (Parliamentary Budget Officer, 2013) came out well before the latest official figure, so the two aren’t compared.

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
8,368
Status
Under construction
Owner
National Defence
Scope
Changed in 2009

Every estimate

Government Watchdog

5 public cost estimates from 2004 to 2026.

Schedule

Original first delivery target
Set in 2004
2012
Current first delivery target
Set in 2026
2027
Delay
15 years

A target given only as a year counts as the end of that year.

Route

No location on file.

Timeline

  1. Oct 2026
    Cost

    National Defence: funding over $5B

    The department's project page gives a funding band rather than a point estimate. The page is undated; the date shown is when it was checked.

    National DefenceNational Defence, Defence Capabilities Blueprint[7]

  2. Oct 2026
    Schedule

    First delivery now in fiscal 2027-28

    Fiscal 2027-28 runs from April 2027 to March 2028. The page is undated; the date shown is when it was checked.

    National DefenceNational Defence, Defence Capabilities Blueprint[7]

  3. Dec 2024
    Schedule

    HMCS Protecteur launched, delivery end of 2025

    Naval News reports the first ship had been expected in 2023 and was delayed by a year at the time of the 2024 launch.

    Seaspan Shipyards / Royal Canadian NavyBaird Maritime[6]

  4. 15 Jun 2020
    Cost

    Total project cost now $4.1B

    Reported as the third figure after $2.3B in 2011 and $3.4B. The Naval News breakdown is $3.1B to buy the two ships and spares plus $1B for design, project management and contingency.

    National DefenceNaval News[4]The Canadian Press, via CHEK News[5]

  5. 15 Jun 2020
    Schedule

    First ship now due in 2023

    National DefenceThe Canadian Press, via CHEK News[5]

  6. 20 Jan 2014
    Schedule

    First delivery hoped for 2018-19

    National DefenceThe Canadian Press, via Global News[2]

  7. 28 Feb 2013
    Cost

    PBO: budget should be $4.13B

    Compared with the program's original budget, $1.5B more.

    Parliamentary Budget OfficerThe Canadian Press, via CBC News[3]

  8. 2009
    Scope

    Cut from three ships to two

    Number of ships reduced from three to two, delivery dates pushed out and requirements changed.

    Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]

  9. 2009
    Cost

    Relaunched with a $2.6B budget for two ships

    Two ships instead of three. The figure is in fixed nominal dollars with no adjustment for inflation.

    Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]

  10. 2008
    Milestone

    Cancelled in 2008 when bids ran over budget

    It was later folded into the National Shipbuilding Strategy and relaunched.

    Government of CanadaThe Canadian Press, via Global News[2]

  11. 2004
    Cost

    $2.1B allocated for three ships

    The replacement was announced in 2004. The PBO report that describes this figure was published in 2013.

    Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]First price

  12. 2004
    Schedule

    First of three ships due in 2012

    Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]

Sources

  1. Marine Log (quoting a Parliamentary Budget Officer report), 28 Feb 2013
    “The Government allocated $2.1 billion to design, develop, and acquire the three ships.”
    “Three Joint Support Ships (JSS) were proposed, with a contract to be awarded in 2008, the first ship delivered in 2012, and the project completed in 2016.”
    “In 2009, however, the Government found that the three ships would not fit within the $2.1 billion budget. In response, the number of ships was reduced to two, delivery dates pushed out, and requirements changed.”
    “The new budget was set at $2.60 billion in fixed nominal dollars.”
  2. The Canadian Press, via Global News, 20 Jan 2014
    “The program was shut down in 2008, on the eve of the election that year, when the bids exceeded the Harper government’s cost limits.”
    “One of the companies that received payment has subsequently been hired to work with Vancouver-based Seaspan Shipyards to provide the design for the new program, which hopes to deliver vessels by 2018-19.”
  3. The Canadian Press, via CBC News, 28 Feb 2013
    “Parliamentary Budget Officer Kevin Page recommended Thursday that the government budget $4.13 billion for purchasing the two new ships, $1.5 billion more than the program's original budget.”
  4. Naval News, 16 Dec 2024
    “The total JSS budget includes $3.1 billion for the purchase of the two ships and initial spares, as well as $1 billion for design and production engineering work, project management and associated contingency costs, resulting in a total value of $4.1B.”
  5. The Canadian Press, via CHEK News, 15 Jun 2020
    “That figure was later revised up to $3.4 billion before today’s announcement, which brings the total cost to $4.1 billion.”
    “Work on the first of the two ships has already started and the government says it expects the vessel to be delivered in 2023, four years later than originally planned.”
  6. Baird Maritime, 16 Dec 2024
    “The ship is scheduled to be delivered to the RCN at the end of 2025.”
  7. National Defence, Defence Capabilities Blueprint, 2 Oct 2026
    “Funding Range Greater than $5 billion Anticipated Timeline (Fiscal Year) Options Analysis Phase Completed Definition Phase Completed Implementation Phase In Progress Initial Delivery 2027/2028 Final Delivery 2027/2028”

How we count