Joint Support Ships
Two naval supply ships, HMCS Protecteur and HMCS Preserver, being built by Seaspan in Vancouver to replace the navy's ageing replenishment ships. The program was announced in 2004 for three ships, cancelled in 2008, and restarted for two.
Joint Support Ships was first priced at $2.1 billion in 2004 by the Government of Canada. The latest official estimate is $5 billion or more (2026, National Defence), 1.5 times the first price after adjusting for inflation. The first delivery target has moved 15 years, from 2012 to 2027.
Also called: JSS, Protecteur-class supply ships
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.5×the first quoted price released to the public
- First price 2004, Government of Canada
- Latest estimate 2026, National Defence
- Watchdog estimate 2013, Parliamentary Budget Officer
The most recent independent estimate (Parliamentary Budget Officer, 2013) came out well before the latest official figure, so the two aren’t compared.
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 8,368
- Status
- Under construction
- Owner
- National Defence
- Scope
- Changed in 2009
Every estimate
Government Watchdog
5 public cost estimates from 2004 to 2026.
Schedule
- Original first delivery targetSet in 2004
- 2012
- Current first delivery targetSet in 2026
- 2027
- Delay
- 15 years
A target given only as a year counts as the end of that year.
Route
No location on file.
Timeline
- Oct 2026Cost
National Defence: funding over $5B
The department's project page gives a funding band rather than a point estimate. The page is undated; the date shown is when it was checked.
National DefenceNational Defence, Defence Capabilities Blueprint[7]
- Oct 2026Schedule
First delivery now in fiscal 2027-28
Fiscal 2027-28 runs from April 2027 to March 2028. The page is undated; the date shown is when it was checked.
National DefenceNational Defence, Defence Capabilities Blueprint[7]
- Dec 2024Schedule
HMCS Protecteur launched, delivery end of 2025
Naval News reports the first ship had been expected in 2023 and was delayed by a year at the time of the 2024 launch.
Seaspan Shipyards / Royal Canadian NavyBaird Maritime[6]
- 15 Jun 2020Cost
Total project cost now $4.1B
Reported as the third figure after $2.3B in 2011 and $3.4B. The Naval News breakdown is $3.1B to buy the two ships and spares plus $1B for design, project management and contingency.
National DefenceNaval News[4]The Canadian Press, via CHEK News[5]
- 15 Jun 2020Schedule
First ship now due in 2023
National DefenceThe Canadian Press, via CHEK News[5]
- 20 Jan 2014Schedule
First delivery hoped for 2018-19
National DefenceThe Canadian Press, via Global News[2]
- 28 Feb 2013Cost
PBO: budget should be $4.13B
Compared with the program's original budget, $1.5B more.
Parliamentary Budget OfficerThe Canadian Press, via CBC News[3]
- 2009Scope
Cut from three ships to two
Number of ships reduced from three to two, delivery dates pushed out and requirements changed.
Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]
- 2009Cost
Relaunched with a $2.6B budget for two ships
Two ships instead of three. The figure is in fixed nominal dollars with no adjustment for inflation.
Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]
- 2008Milestone
Cancelled in 2008 when bids ran over budget
It was later folded into the National Shipbuilding Strategy and relaunched.
Government of CanadaThe Canadian Press, via Global News[2]
- 2004Cost
$2.1B allocated for three ships
The replacement was announced in 2004. The PBO report that describes this figure was published in 2013.
Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]First price
- 2004Schedule
First of three ships due in 2012
Government of CanadaMarine Log (quoting a Parliamentary Budget Officer report)[1]
Sources
- Marine Log (quoting a Parliamentary Budget Officer report), 28 Feb 2013
“The Government allocated $2.1 billion to design, develop, and acquire the three ships.”
“Three Joint Support Ships (JSS) were proposed, with a contract to be awarded in 2008, the first ship delivered in 2012, and the project completed in 2016.”
“In 2009, however, the Government found that the three ships would not fit within the $2.1 billion budget. In response, the number of ships was reduced to two, delivery dates pushed out, and requirements changed.”
“The new budget was set at $2.60 billion in fixed nominal dollars.”
- The Canadian Press, via Global News, 20 Jan 2014
“The program was shut down in 2008, on the eve of the election that year, when the bids exceeded the Harper government’s cost limits.”
“One of the companies that received payment has subsequently been hired to work with Vancouver-based Seaspan Shipyards to provide the design for the new program, which hopes to deliver vessels by 2018-19.”
- The Canadian Press, via CBC News, 28 Feb 2013
“Parliamentary Budget Officer Kevin Page recommended Thursday that the government budget $4.13 billion for purchasing the two new ships, $1.5 billion more than the program's original budget.”
- Naval News, 16 Dec 2024
“The total JSS budget includes $3.1 billion for the purchase of the two ships and initial spares, as well as $1 billion for design and production engineering work, project management and associated contingency costs, resulting in a total value of $4.1B.”
- The Canadian Press, via CHEK News, 15 Jun 2020
“That figure was later revised up to $3.4 billion before today’s announcement, which brings the total cost to $4.1 billion.”
“Work on the first of the two ships has already started and the government says it expects the vessel to be delivered in 2023, four years later than originally planned.”
- Baird Maritime, 16 Dec 2024
“The ship is scheduled to be delivered to the RCN at the end of 2025.”
- National Defence, Defence Capabilities Blueprint, 2 Oct 2026
“Funding Range Greater than $5 billion Anticipated Timeline (Fiscal Year) Options Analysis Phase Completed Definition Phase Completed Implementation Phase In Progress Initial Delivery 2027/2028 Final Delivery 2027/2028”