Valley Line West LRT
A 14-kilometre, mostly street-level LRT from downtown Edmonton to Lewis Farms in the west end, the second stage of the Valley Line. Built by Marigold Infrastructure Partners under a design-build-partially-finance contract signed in December 2020.
Valley Line West LRT was first priced at $1.8 billion in 2011 by the City of Edmonton. The latest official estimate is $2.6 billion (2020, the City of Edmonton), 1.3 times the first price after adjusting for inflation.
Also called: West LRT, Valley Line West
Checked for new figures on 19 Nov 2026. How we update
1.3×the first quoted price released to the public
- First price 2011, City of Edmonton
- Latest estimate 2020, City of Edmonton
Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,810
- Status
- Under construction
- Owner
- City of Edmonton
- Scope
- Unchanged
Every estimate
Government Other
4 public cost estimates from 2011 to 2020.
Route
Timeline
- 23 Dec 2020Status
Contract signed with Marigold
City of EdmontonCity of Edmonton[3]
- 13 Mar 2020Cost
$2.6B at procurement
City of EdmontonCity of Edmonton[3]
- 23 Mar 2018Cost
Council drops an underpass: about $2B
The report does not say who gave the estimate, so it is not used as the official figure.
Global News (unattributed)Global News[2]
- 13 Mar 2018Cost
City report: $2.24B with seven design changes
Includes inflation, assuming construction from 2019.
City of EdmontonGlobal News[1]
- 2011Cost
$1.8B under the 2011 recommendations
Dated to the 2011 design recommendations the city's 2018 report compared against. The original 2011 document is not yet sourced.
City of EdmontonGlobal News[1]First price
Sources
- Global News, 13 Mar 2018
“Changing the design at a couple of intersection crossings in the west, compared to the 2011 recommendations, will increase the cost from $1.8 billion to $2.24 billion.”
““The Valley Line West capital construction cost is currently estimated at $2.24 billion. This project cost estimate includes the seven design recommendations noted above and factors in inflation, assuming a construction start in 2019.””
- Global News, 23 Mar 2018
“The cost for the western leg of the Valley Line is now estimated to be about $2 billion and the city said the project could be ready for procurement by the end of the year.”
- City of Edmonton, 13 Mar 2020
“March 2020: Procurement Update The City has shortlisted 3 teams to participate in the next stage of its procurement competition for the contract to design, build and partially finance the $2.6 billion Valley Line West LRT.”
“On December 23, 2020, the City reached financial close with Marigold Infrastructure Partners, which was selected as the preferred proponent to design, build and partially finance the $2.6-billion Valley Line West LRT.”