Heavy icebreakers for the Canadian Coast Guard. Announced in 2008 as one ship, the CCGS John G. Diefenbaker, for delivery by 2017; now two ships being built by Seaspan and Davie.

Polar icebreakers was first priced at $721 million in 2008 by the Government of Canada. The latest official estimate is $3.15 billion (2025, Public Services and Procurement Canada), 3 times the first price after adjusting for inflation. The first delivery target has moved 13 years, from 2017 to 2030.

Also called: CCGS John G. Diefenbaker, Polar Max

Reviewed monthly. Last review: 5 Nov 2026. How we update

3×the first quoted price released to the public

First price 2008, Government of Canada
$1.1B
Latest estimate 2025, Public Services and Procurement Canada
$3.3B

Adjusted for inflation to 2026 dollars.

Days since announced
6,907
Status
Under construction
Owner
Government of Canada
Scope
Changed in 2021

Every estimate

Government

3 public cost estimates from 2008 to 2025.

Left out because they measure something else: $6.4B two polar icebreakers (construction contracts), 2025.

Schedule

Original first delivery target
Set in 2008
2017
Current first delivery target
Set in 2025
2030
Delay
13 years

A target given only as a year counts as the end of that year.

Location

Timeline

  1. Jul 2025
    Status

    Construction under way

    Public Services and Procurement CanadaPublic Services and Procurement Canada (Question Period note)[2]

  2. 8 Mar 2025
    Cost

    Both ships: $6.4B in construction contracts

    Public Services and Procurement CanadaPublic Services and Procurement Canada (Question Period note)[2]Sum of $3.15B + $3.25B

  3. 8 Mar 2025
    Schedule

    Davie's Polar Max due by 2030

    Government of CanadaWorkBoat[3]

  4. 7 Mar 2025
    Cost

    Seaspan's ship contracted at $3.15B

    Construction contract value before tax for the ship that replaced the Diefenbaker order at Seaspan. Davie's second ship is $3.25B.

    Public Services and Procurement CanadaPublic Services and Procurement Canada (Question Period note)[2]

  5. 6 May 2021
    Scope

    Now two icebreakers

    Two polar icebreakers instead of one: one built by Seaspan in Vancouver, one by Davie in Lévis.

    Government of CanadaThe Canadian Press, via Global News[1]

  6. 2013
    Cost

    Budget raised to $1.3B

    Government of CanadaThe Canadian Press, via Global News[1]

  7. 2008
    Cost

    Announced: $721M for the CCGS John G. Diefenbaker

    Government of CanadaThe Canadian Press, via Global News[1]First price

  8. 2008
    Schedule

    Delivery by 2017

    Government of CanadaThe Canadian Press, via Global News[1]

Sources

  1. The Canadian Press, via Global News, 6 May 2021
    “Originally budgeted at $721 million, the icebreaker was supposed to be delivered by 2017 and replace the Coast Guard’s flagship, the CCGS Louis S.”
    “St-Laurent.But scheduling conflicts, technical problems and other issues scuttled the timeline and budget — which was increased to $1.3 billion in 2013 — before the Trudeau government quietly lifted the ship from Seaspan’s order book in August 2019.”
    “Ottawa doubling icebreaker orders as one ship goes to Quebec yard, another to Vancouver”
  2. Public Services and Procurement Canada (Question Period note), 29 Aug 2025
    “On March 7, 2025, Seaspan’s Vancouver Shipyards was awarded a $3.15-billion contract (excluding taxes) to build one polar icebreaker.”
    “On March 7, 2025, Seaspan’s Vancouver Shipyards was awarded a $3.15-billion contract (excluding taxes) to build one polar icebreaker. On March 8, 2025, Chantier Davie Canada Inc. was awarded a $3.25-billion contract (excluding taxes) to build the other polar icebreaker.”
    “Full-rate production of the future CCGS Imnaryuaq started in July 2025 at Seaspan’s Vancouver Shipyards, while steel cutting for the future CCGS Arpatuuq took place in August 2025 at the Canadian-owned Helsinki Shipyard in Finland, marking the start of its construction phase Background: The National Shipbuilding Strategy is a long-term plan to renew the Royal Canadian Navy and Canadian Coast Guard fleets.”
  3. WorkBoat, 10 Mar 2025
    “The vessel, Polar Max, is expected to be delivered by 2030.Meanwhile, Seaspan Shipyards, North Vancouver, British Columbia, has been awarded a $3.15 billion contract to construct the other polar icebreaker.”

How we count