Eglinton Crosstown LRT

A 19 km light rail line along Eglinton Avenue in Toronto, about 10 km of it underground, from Mount Dennis to Kennedy. Built by Metrolinx under a public-private partnership and run by the TTC as Line 5.

Eglinton Crosstown LRT was first priced at $2.2 billion in 2007 by Toronto Transit Commission and City of Toronto. The latest official estimate is $5.3 billion (2015, the Government of Ontario), 2.1 times the first price after adjusting for inflation. It opened 9 years, 2 months after the original opening target of 2016.

Also called: Line 5 Eglinton, Eglinton LRT

Reviewed monthly. Last review: 5 Nov 2026. How we update

2.1×the first quoted price released to the public

First price 2007, Toronto Transit Commission and City of Toronto
$3.4B
Latest estimate 2015, Government of Ontario
$7.1B

Adjusted for inflation to 2026 dollars.

Days since announced
7,213
Status
Operational
Owner
Metrolinx
Scope
Changed in 2010

Every estimate

Government Project owner

3 public cost estimates from 2007 to 2015.

Left out because they measure something else: $11.78B total including financing and 30-year maintenance, 2018; $12.81B total including financing and 30-year maintenance, 2022; $13.08B total including financing and 30-year maintenance, 2025.

Schedule

Original opening target
Set in 2009
2016
Opened
8 Feb 2026
Delay
9 years, 2 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 8 Feb 2026
    Status

    Opens as TTC Line 5

    Opened about six years after the 2020 target, with reduced hours at first.

    Toronto Transit CommissionCBC News[4]

  2. 30 Oct 2025
    Cost

    $13.08B including 30 years of maintenance

    MetrolinxThe Globe and Mail[1]CBC News[4]

  3. 8 Dec 2022
    Cost

    Approved budget reaches $12.81B

    Metrolinx (internal documents)CBC News[8]

  4. Dec 2021
    Schedule

    Service pushed to 2023

    Set after a legal settlement with the builder. Metrolinx later stopped giving target dates until testing was done.

    MetrolinxToronto Star[9]

  5. 2018
    Cost

    Budget $11.78B with 30 years of upkeep

    Not comparable with the capital-only figures: includes financing and 30 years of maintenance.

    MetrolinxCBC News[8]

  6. 3 Nov 2015
    Cost

    Contract signed, $5.3B of it capital

    Capital share of the $9.1B, 30-year contract with Crosslinx Transit Solutions. The rest covers financing, maintenance and lifecycle.

    Government of Ontario (Transportation Minister Steven Del Duca)Toronto Star[5]CBC News[6]

  7. 3 Nov 2015
    Schedule

    Opening slips to 2021

    Government of OntarioThe Globe and Mail[7]

  8. Mar 2010
    Scope

    Line cut to 19 km

    Provincial funding cut in the 2010 budget shortened the line to 19 km, Mount Dennis area to Kennedy, dropping the section to Pearson Airport.

    Government of OntarioThe Globe and Mail[1]

  9. Mar 2010
    Schedule

    Shortened line due by 2020

    Metrolinx and Toronto Transit CommissionThe Globe and Mail[1]CBC News[4]

  10. 1 Apr 2009
    Cost

    Province funds the line at $4.6B

    For a 31 km line from Kennedy to Pearson Airport.

    Government of Ontario (Premier Dalton McGuinty)Spacing Toronto (citing The Globe and Mail)[2]CBC News[3]

  11. 1 Apr 2009
    Schedule

    Completion expected in 2016

    Government of OntarioThe Globe and Mail[1]

  12. Mar 2007
    Cost

    Transit City plan: $2.2B

    First figure for the Eglinton line, then planned from Kingston Road to Pearson Airport. The Globe reports it was not fully developed and left out items such as vehicle storage.

    Toronto Transit Commission and City of Toronto (Transit City plan)The Globe and Mail[1]First price

Sources

  1. The Globe and Mail, 30 Oct 2025
    “March, 2007 Transit City plans unveiled Mayor David Miller and the Toronto Transit Commission reveal their “Transit City” plan for new light-rail lines, including a partly tunnelled line along Eglinton Avenue, from Kingston Road in the east to Pearson Airport in the west, with an initial estimated cost of just $2.2-billion.”
    “The plan includes a 31-kilometre partly tunnelled Eglinton line running from Kennedy Road in the east all the way to Pearson International Airport in the west, with a price tag of $4.6-billion and an “expected completion date” of 2016.”
    “Later that year, the TTC and Metrolinx would agree on today’s shortened, 19-kilometre Eglinton line, pledging to have it done by 2020.”
    “The now 19-kilometre Eglinton line was to be completed by 2019-2020.”
    “The bill for this partially tunnelled, 19-kilometre light-rail line is currently pegged at $13.08-billion, including 30 years of maintenance – around $8-billion more than estimated back when construction began.”
  2. Spacing Toronto (citing The Globe and Mail), 1 Apr 2009
    “The Eglinton rapid transit line will be the most expensive among the projects, costing about $4.6-billion.”
  3. CBC News, 4 Jan 2011
    “The $4.6-billion Eglinton Crosstown LRT line, as it is currently envisioned, stretches from the Scarborough Town Centre in the east to Pearson International Airport westward.”
  4. CBC News, 8 Feb 2026
    “Though the network was eliminated, the Eglinton project persisted with a ground-breaking ceremony held at Mount Dennis in 2011, with promises for a completed line by late 2020.”
    “As of last fall, the project had amassed a price tag of over $13 billion, according to a report from Metrolinx, an increase from the $11.78 billion projected in 2018.”
    “People ride the Eglinton Crosstown LRT on its first day of service in Toronto on Feb. 8, 2026.”
  5. Toronto Star, 3 Nov 2015
    “Of the $9.1 billion, $5.3 billion is capital.”
  6. CBC News, 18 Feb 2020
    “In a statement released Tuesday, Metrolinx president and CEO Phil Verster attributed much of the delay to the group of private companies building the $5.3-billion project in partnership with the province, Crosslinx Transit Solutions (CTS).”
  7. The Globe and Mail, 3 Nov 2015
    “It survived the anti-LRT mood of the last city council and is due to enter service in 2021, a year behind schedule.”
  8. CBC News, 8 Dec 2022
    “The budget for the project was $11.78 billion in 2018, which included the design, construction, financing and 30-year maintenance of the light rail transit (LRT) system.”
    “They detail the status of the project and show the current approved budget to be $12.81 billion.”
  9. Toronto Star, 8 Dec 2022
    “In December 2021, Metrolinx said the transit line would be complete by September 2022 and ready for service in 2023”

How we count