Yonge North Subway Extension

An extension of Toronto's Line 1 subway north from Finch station into Markham and Richmond Hill, led by Metrolinx.

Yonge North Subway Extension was first priced at up to $3 billion in 2007 by TTC and York Region. The latest official estimate is $5.6 billion (2021, Metrolinx), 1.5 times the first price after adjusting for inflation.

Also called: YNSE

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.5×the first quoted price released to the public

First price 2007, TTC and York Region
up to $4.6B
Latest estimate 2021, Metrolinx
$6.7B

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
7,121
Status
Procurement
Owner
Metrolinx
Scope
Changed in 2021

Every estimate

Government Project owner

3 public cost estimates from 2007 to 2021.

Schedule

Opening target
Set in 2021
2029
Delay
None so far

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 6 Aug 2025
    Milestone

    $1.44B tunnelling contract awarded

    Metrolinx and Infrastructure OntarioUrbanToronto[4]

  2. 18 Mar 2021
    Scope

    Fewer stations to fit the budget

    Cut from six stations to five, with sections above ground, to fit a $5.6B budget.

    MetrolinxCBC News[2]

  3. 18 Mar 2021
    Cost

    Budget $5.6B after cuts

    Metrolinx (initial business case)Mass Transit[3]

  4. 18 Mar 2021
    Schedule

    Service 2029 to 2030

    Metrolinx (initial business case)Mass Transit[3]

  5. 2019
    Cost

    TTC: $9.3B for the six-station plan

    TTCCBC News[2]

  6. 2007
    Cost

    2007 plan: under $3B

    TTC and York Region (2007 approved plan)Steve Munro[1]First price

Sources

  1. Steve Munro, 20 Mar 2021
    “The fundamental problem which the IBC and its supplement seek to address is that the cost of the extension had grown to $9 billion in 2019 from an original estimate in the 2007 approved plan of less than $3 billion.”
  2. CBC News, 19 Mar 2021
    “The analysis shows that if the six-station plan were to go ahead as planned, the price of the project would reach $9.3 billion, as estimated by the TTC in 2019.”
    “The province's provisional budget is $5.6 billion.”
  3. Mass Transit, 19 Mar 2021
    “Within the document, Metrolinx says it is “committed to delivering a YNSE that offers an optimized program within the available funding envelope” of C$5.6 billion (US$4.48 billion).”
    “The schedule included in the document estimates a contract could be awarded in September 2023 with construction starting in 2024 and the line entering service between 2029 and 2030.”
  4. UrbanToronto, 6 Aug 2025
    “The Yonge Line 1 North Subway Extension is taking a major step forward, as Infrastructure Ontario and Metrolinx have awarded a $1.44 billion contract for the project’s advance tunnelling phase.”