Iqaluit Nukkiksautiit Hydro Project

A hydroelectric plant on the Kuugaluk River about 60 km from Iqaluit to replace the city's diesel power. Started by Nunavut's Crown utility Qulliq Energy, shelved in 2014, and revived by the Inuit-owned Nunavut Nukkiksautiit Corp.; Ottawa is expected to be the main funder.

Iqaluit Nukkiksautiit Hydro Project was first priced at $356 million in 2013 by Qulliq Energy Corporation. The latest official estimate is up to $500 million (2017, Johnny Mike, minister responsible for Qulliq Energy Corporation), 1.3 times the first price after adjusting for inflation.

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.3×the first quoted price released to the public

First price 2013, Qulliq Energy Corporation
$494M
Latest estimate 2017, Johnny Mike, minister responsible for Qulliq Energy Corporation
up to $653M

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
5,080
Status
Planning
Owner
Nunavut Nukkiksautiit Corporation
Scope
Changed in 2023

Every estimate

Government Project owner Other

3 public cost estimates from 2013 to 2024.

Schedule

Original completion target
Set in 2025
2033
Current completion target
Set in 2025
2030
Delay
3 years early

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 14 Nov 2025
    Schedule

    Commissioning targeted for 2030 after fast-tracking

    Nunavut Nukkiksautiit Corporation (Heather Shilton)Nunatsiaq News[4]

  2. 13 Nov 2025
    Milestone

    $26M federal for design; referred to the Major Projects Office

    Government of CanadaCanada's National Observer[5]

  3. 7 Nov 2025
    Schedule

    Proponent: operational by 2033

    Nunavut Nukkiksautiit CorporationNunatsiaq News[2]Nunatsiaq News[4]

  4. Oct 2024
    Cost

    Reported: $400-500M

    CBC didn't say who estimated it, so it isn't used as the official figure.

    CBC News (estimator not named)CBC News[3]

  5. 2023
    Scope

    New owner, new site: Kuugaluk River

    Project taken over by Nunavut Nukkiksautiit Corp. and moved from the Jaynes Inlet/Armshow South sites to the Kuugaluk River.

    Nunavut Nukkiksautiit CorporationCBC News[3]

  6. 2017
    Cost

    Approaching $500M

    Told to Nunavut's legislative assembly.

    Johnny Mike, minister responsible for Qulliq Energy CorporationNunatsiaq News[2]

  7. 2014
    Status
  8. 2013
    Cost

    About $356M for two sites

    Jaynes Inlet and Armshow South.

    Qulliq Energy Corporation (Government of Nunavut)Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))[1]First price

Sources

  1. Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3)), 8 Jun 2017
    “As of 2013, the total cost of the project is estimated at approximately $356 million to construct both hydro development sites.”
    “A 2013 capital estimate quoted the price of constructing the first phase of the hydro development at Jaynes Inlet to be $211.5 million and the second phase at Armshow South to be $144.5 million.”
    “In 2014, the Iqaluit Hydroelectric project was put on hold due to the large capital investment required to proceed with the project which is beyond QEC’s funding and borrowing ability.”
  2. Nunatsiaq News, 7 Nov 2025
    “In 2017, its cost was estimated to be “approaching $500 million,” Johnny Mike, then-minister for QEC, told the legislative assembly.”
    “It would include an approximately 50-metre-high dam and a powerhouse and could be operational by 2033 generating 15 megawatts for about 100 years.”
  3. CBC News, 4 Feb 2025
    “Nunavut Nukkiksautiit Corporation identified the Kuugaluk River (McKeand River South), 60 kilometres northwest of Iqaluit, as a possible site for the project after doing community consultations in 2023.”
    “As of last fall, the project's price tag was between $400 and $500 million.”
  4. Nunatsiaq News, 14 Nov 2025
    “Originally, proponents hoped to have the plant running by 2033.”
    ““We would be looking at a three-year construction window, so 2030 would be the target for commissioning,””
  5. Canada's National Observer, 14 Nov 2025
    “Since February 2025, the federal government has allocated $26 million toward design, data collection and public engagement.”

How we count