Iqaluit Nukkiksautiit Hydro Project
A hydroelectric plant on the Kuugaluk River about 60 km from Iqaluit to replace the city's diesel power. Started by Nunavut's Crown utility Qulliq Energy, shelved in 2014, and revived by the Inuit-owned Nunavut Nukkiksautiit Corp.; Ottawa is expected to be the main funder.
Iqaluit Nukkiksautiit Hydro Project was first priced at $356 million in 2013 by Qulliq Energy Corporation. The latest official estimate is up to $500 million (2017, Johnny Mike, minister responsible for Qulliq Energy Corporation), 1.3 times the first price after adjusting for inflation.
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.3×the first quoted price released to the public
- First price 2013, Qulliq Energy Corporation
- Latest estimate 2017, Johnny Mike, minister responsible for Qulliq Energy Corporation
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,080
- Status
- Planning
- Owner
- Nunavut Nukkiksautiit Corporation
- Scope
- Changed in 2023
Every estimate
Government Project owner Other
3 public cost estimates from 2013 to 2024.
Schedule
- Original completion targetSet in 2025
- 2033
- Current completion targetSet in 2025
- 2030
- Delay
- 3 years early
A target given only as a year counts as the end of that year.
Location
Timeline
- 14 Nov 2025Schedule
Commissioning targeted for 2030 after fast-tracking
Nunavut Nukkiksautiit Corporation (Heather Shilton)Nunatsiaq News[4]
- 13 Nov 2025Milestone
$26M federal for design; referred to the Major Projects Office
Government of CanadaCanada's National Observer[5]
- 7 Nov 2025Schedule
Proponent: operational by 2033
Nunavut Nukkiksautiit CorporationNunatsiaq News[2]Nunatsiaq News[4]
- Oct 2024Cost
Reported: $400-500M
CBC didn't say who estimated it, so it isn't used as the official figure.
CBC News (estimator not named)CBC News[3]
- 2023Scope
New owner, new site: Kuugaluk River
Project taken over by Nunavut Nukkiksautiit Corp. and moved from the Jaynes Inlet/Armshow South sites to the Kuugaluk River.
Nunavut Nukkiksautiit CorporationCBC News[3]
- 2017Cost
Approaching $500M
Told to Nunavut's legislative assembly.
Johnny Mike, minister responsible for Qulliq Energy CorporationNunatsiaq News[2]
- 2014Status
Put on hold: too costly for QEC
Qulliq Energy CorporationQulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))[1]
- 2013Cost
About $356M for two sites
Jaynes Inlet and Armshow South.
Qulliq Energy Corporation (Government of Nunavut)Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))[1]First price
Sources
- Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3)), 8 Jun 2017
“As of 2013, the total cost of the project is estimated at approximately $356 million to construct both hydro development sites.”
“A 2013 capital estimate quoted the price of constructing the first phase of the hydro development at Jaynes Inlet to be $211.5 million and the second phase at Armshow South to be $144.5 million.”
“In 2014, the Iqaluit Hydroelectric project was put on hold due to the large capital investment required to proceed with the project which is beyond QEC’s funding and borrowing ability.”
- Nunatsiaq News, 7 Nov 2025
“In 2017, its cost was estimated to be “approaching $500 million,” Johnny Mike, then-minister for QEC, told the legislative assembly.”
“It would include an approximately 50-metre-high dam and a powerhouse and could be operational by 2033 generating 15 megawatts for about 100 years.”
- CBC News, 4 Feb 2025
“Nunavut Nukkiksautiit Corporation identified the Kuugaluk River (McKeand River South), 60 kilometres northwest of Iqaluit, as a possible site for the project after doing community consultations in 2023.”
“As of last fall, the project's price tag was between $400 and $500 million.”
- Nunatsiaq News, 14 Nov 2025
“Originally, proponents hoped to have the plant running by 2033.”
““We would be looking at a three-year construction window, so 2030 would be the target for commissioning,””
- Canada's National Observer, 14 Nov 2025
“Since February 2025, the federal government has allocated $26 million toward design, data collection and public engagement.”