Niagara Tunnel

A 10 km tunnel under the city of Niagara Falls carrying extra water from the Niagara River to OPG's Sir Adam Beck generating stations, bored by the machine known as Big Becky.

Niagara Tunnel was first priced at $985 million in 2005 by Ontario Power Generation. The latest official estimate is $1.6 billion (2010, Ontario Power Generation), 1.5 times the first price after adjusting for inflation. It was completed 3 years, 3 months after the original completion target of 2009.

Also called: Big Becky

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.5×the first quoted price released to the public

First price 2005, Ontario Power Generation
$1.6B
Latest estimate 2010, Ontario Power Generation
$2.3B

Adjusted for inflation to 2026 dollars.

Days since announced
7,790
Status
Complete
Owner
Ontario Power Generation
Scope
Unchanged

Every estimate

Project owner

2 public cost estimates from 2005 to 2010.

Schedule

Original completion target
Set in 2005
2009
Completed
Mar 2013
Delay
3 years, 3 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. Mar 2013
    Status

    Completed, under the revised budget

    Reported as finished $100M under the revised $1.6B budget and ahead of the revised schedule; still four years later and well above the original $985M.

    Ontario Power GenerationTunneling Online[2]

  2. Dec 2010
    Cost

    Revised budget $1.6B

    OPG rebaselined the project after the tunnel boring machine hit poor rock.

    Ontario Power GenerationElectricity Forum[1]

  3. Dec 2010
    Schedule

    Now 2013

    Ontario Power GenerationElectricity Forum[1]

  4. 2005
    Cost

    Original estimate $985M

    Ontario Power GenerationElectricity Forum[1]First price

  5. 2005
    Schedule

    Due by 2009

    Ontario Power GenerationElectricity Forum[1]

Sources

  1. Electricity Forum, 1 Dec 2010
    “The cost of the project has risen to $1.6 billion from the original estimate of $985 million.”
    “Big Becky, which started boring in 2006, was supposed to have completed the job by 2009.”
    “Although the boring will be completed early in the New Year, the project as a whole won’t be finished until 2013, as the rough tunnel must be lined before it can be used.”
  2. Tunneling Online, 18 Dec 2013
    “As Platts reported, “The Niagara Tunnel was safely completed in March 2013, nine months ahead of schedule and $100 million under its $1.6 billion budget.”