Broadway Subway
A 5.7-kilometre, six-station SkyTrain extension of the Millennium Line from VCC-Clark to Arbutus Street in Vancouver, mostly underground. Funded by the Province of B.C. with contributions from Canada and the City of Vancouver.
Broadway Subway was first priced at $1.98 billion in 2014 by TransLink. The latest official estimate is $2.95 billion (2025, the Province of British Columbia), 1.1 times the first price after adjusting for inflation. The opening target has moved 2 years, from 2025 to 2027.
Also called: Millennium Line Broadway Extension, Broadway SkyTrain
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.1×the first quoted price released to the public
- First price 2014, TransLink
- Latest estimate 2025, Province of British Columbia
Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,715
- Status
- Under construction
- Owner
- Province of British Columbia
- Scope
- Unchanged
Every estimate
Government Project owner
4 public cost estimates from 2014 to 2025.
Schedule
- Original opening targetSet in 2018
- 2025
- Current opening targetSet in 2025
- 2027
- Delay
- 2 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 3 Jan 2025Cost
Project cost now $2.954B
The sources found do not give the date of the increase from $2.83B.
Province of British Columbia (Infrastructure BC project page)Infrastructure BC[5]
- 3 Jan 2025Schedule
Opening in 2027
Province of British Columbia (Infrastructure BC project page)Infrastructure BC[5]
- 24 May 2024Schedule
Delayed again to fall 2027
Province of British Columbia (Ministry of Transportation)Global News[4]
- 25 Nov 2022Schedule
Delayed to early 2026 after strike
Province of British ColumbiaCBC News[3]
- 2 Feb 2021Cost
Budgeted at $2.83B at construction start
Province of British ColumbiaGlobal News[2]
- 30 Apr 2018Cost
Estimate rises to $2.83B
Global News said the 2014 figure would be $2.28B in 2018 dollars.
TransLinkGlobal News[1]
- 30 Apr 2018Schedule
Target completion in 2025
TransLinkGlobal News[1]
- 2014Cost
First budgeted at $1.98B in 2014
The first figure found, from TransLink's 2014 plan as reported by Global News in 2018. Global News reported it as the earlier budget for the same Broadway line to Arbutus Street.
TransLinkGlobal News[1]First price
Sources
- Global News, 30 Apr 2018
“The project was in 2014 budgeted to cost $1.98 billion.”
“Cost of Broadway subway line grows to an estimated $2.83 billion”
“The construction is expected to start in 2020, with the target completion date of 2025.”
- Global News, 2 Feb 2021
“The Broadway Subway Project is budgeted to cost $2.83 billion.”
- CBC News, 25 Nov 2022
“The B.C. government says the first phase of the Broadway Subway project in Vancouver has been delayed to early 2026 due to a strike in June.”
- Global News, 27 May 2024
“The Ministry of Transportation revealed Friday that the projected completion date for the Broadway subway has been pushed back to the fall of 2027.”
- Infrastructure BC, 3 Jan 2025
“The Broadway Subway Project will cost $2.954 billion, funded and delivered by the Government of B.C., with contributions from the Government of Canada and the City of Vancouver.”
“Construction of the subway will mostly involve tunneling, with the new extension opening in 2027.”