Roberts Bank Terminal 2

A new three-berth container terminal on reclaimed land at Roberts Bank in Delta, B.C., proposed by the Vancouver Fraser Port Authority, a federal port authority. Approved in 2023; construction is planned from 2028.

Roberts Bank Terminal 2 was first priced at $1.9 billion in 2015 by Port Metro Vancouver. The latest official estimate is $5.9 billion (2026, the Government of Canada), 2.3 times the first price after adjusting for inflation. The completion target has moved 11 years, from 2023 to 2034.

Also called: RBT2

Reviewed monthly. Last review: 5 Nov 2026. How we update

2.3×the first quoted price released to the public

First price 2015, Port Metro Vancouver
$2.6B
Latest estimate 2026, Government of Canada
$6B

Adjusted for inflation to 2026 dollars.

Days since announced
4,314
Status
Procurement
Owner
Vancouver Fraser Port Authority
Scope
Unchanged

Every estimate

Government Project owner Other

4 public cost estimates from 2015 to 2026.

Schedule

Original completion target
Set in 2015
2023
Current completion target
Set in 2026
2034
Delay
11 years

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 30 Oct 2026
    Cost

    Federal release: a $5.9B investment

    Government of Canada (Transport Canada)Indo-Canadian Voice (Government of Canada news release, reprinted in full)[8]

  2. 30 Oct 2026
    Schedule

    Commercial operations targeted for 2035

    Government of Canada (Transport Canada)Indo-Canadian Voice (Government of Canada news release, reprinted in full)[8]

  3. 30 Oct 2026
    Milestone

    Listed as a project of national interest

    Government of Canada (Transport Canada)Daily Hive[9]

  4. 20 Jul 2026
    Milestone

    TerraMarine joint venture picked to build the landmass and wharf

    Vancouver Fraser Port AuthorityYahoo Finance[7]

  5. 20 Jul 2026
    Schedule

    Completion now targeted for early 2034

    Vancouver Fraser Port AuthorityYahoo Finance[7]

  6. 14 May 2025
    Schedule

    Major construction to start in 2028

    Vancouver Fraser Port AuthorityDelta Optimist[6]

  7. 20 Apr 2023
    Status

    Federal approval

    Government of CanadaCBC News[2]

  8. 20 Apr 2023
    Cost

    'Over $2 billion'

    The article doesn't say who estimated it, so it isn't used as the official figure.

    Daily Hive (figure not attributed)Daily Hive[3]

  9. 20 Apr 2023
    Cost

    Widely reported: $3.5B

    Reported at federal approval without saying who estimated it, so not used as the official figure.

    The Globe and Mail; Global NewsThe Globe and Mail[4]Global News[5]

  10. 6 Feb 2015
    Cost

    About $1.9B

    From the environmental impact statement, in 2013 dollars.

    Port Metro Vancouver (now Vancouver Fraser Port Authority)Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)[1]First price

  11. 6 Feb 2015
    Schedule
  12. 6 Feb 2015
    Schedule

In the news

Links to outside coverage. All news

Sources

  1. Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates), 6 Feb 2015
    “The estimated economic cost is approximately $1.9 billion for building the new marine terminal, widening the causeway, dredging the dredge basin, expanding the existing tug basin, and testing and training on the container handling equipment.”
    “The Project would have the capacity to be fully operational beginning in 2024.”
    “This equipment is projected to be installed in the last construction year, 2023, and there will be on-site training and start-up measures undertaken by the Terminal Operator Concessionaire during this year too.”
  2. CBC News, 20 Apr 2023
    “The federal government has given the OK for a major new container terminal on Canada's West Coast”
  3. Daily Hive, 20 Apr 2023
    “The estimated cost of building Roberts Bank Terminal 2 is over $2 billion, with the project self-funded by the port authority.”
  4. The Globe and Mail, 20 Apr 2023
    “The federal government has approved the Port of Vancouver’s proposed $3.5-billion container terminal, saying the project will spur economic growth while complying with environmental rules.”
  5. Global News, 20 Apr 2023
    “Private investments and the Vancouver Fraser Port Authority will fund its estimated $3.5 billion cost.”
  6. Delta Optimist, 14 May 2025
    “Construction mobilization and early works are expected to occur in 2027, with major land reclamation works expected to begin in 2028.”
  7. Yahoo Finance, 20 Jul 2026
    “The Vancouver Fraser Port Authority has selected the TerraMarine joint venture (JV) as the preferred proponent for the landmass and wharf infrastructure component of the Roberts Bank Terminal 2 Project in Delta city of British Columbia.”
    “Completion is targeted for early 2034, and terminal operations are anticipated to begin in the mid-2030s.”
  8. Indo-Canadian Voice (Government of Canada news release, reprinted in full), 30 Oct 2026
    “Through collaboration with the Major Projects Office, the VFPA, and other federal partners, RBT2, a $5.9 billion investment in Canada’s trade infrastructure, is on a viable path to Final Investment Decision (FID) by mid-2027.”
    “Friday’s listing decision provides upfront certainty on the remaining applicable federal regulatory authorizations, and accelerates the project’s commercial operations by up to four years, from 2039 to 2035.”
  9. Daily Hive, 30 Oct 2026
    “The Government of Canada announced the formal designation today, noting that it could bring the superport into operation in 2035 instead of 2039 by speeding up the remaining federal approvals.”

How we count