Roberts Bank Terminal 2
A new three-berth container terminal on reclaimed land at Roberts Bank in Delta, B.C., proposed by the Vancouver Fraser Port Authority, a federal port authority. Approved in 2023; construction is planned from 2028.
Roberts Bank Terminal 2 was first priced at $1.9 billion in 2015 by Port Metro Vancouver. The latest official estimate is $5.9 billion (2026, the Government of Canada), 2.3 times the first price after adjusting for inflation. The completion target has moved 11 years, from 2023 to 2034.
Also called: RBT2
Reviewed monthly. Last review: 5 Nov 2026. How we update
2.3×the first quoted price released to the public
- First price 2015, Port Metro Vancouver
- Latest estimate 2026, Government of Canada
Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,314
- Status
- Procurement
- Owner
- Vancouver Fraser Port Authority
- Scope
- Unchanged
Every estimate
Government Project owner Other
4 public cost estimates from 2015 to 2026.
Schedule
- Original completion targetSet in 2015
- 2023
- Current completion targetSet in 2026
- 2034
- Delay
- 11 years
A target given only as a year counts as the end of that year.
Location
Timeline
- 30 Oct 2026Cost
Federal release: a $5.9B investment
Government of Canada (Transport Canada)Indo-Canadian Voice (Government of Canada news release, reprinted in full)[8]
- 30 Oct 2026Schedule
Commercial operations targeted for 2035
Government of Canada (Transport Canada)Indo-Canadian Voice (Government of Canada news release, reprinted in full)[8]
- 30 Oct 2026Milestone
Listed as a project of national interest
Government of Canada (Transport Canada)Daily Hive[9]
- 20 Jul 2026Milestone
TerraMarine joint venture picked to build the landmass and wharf
Vancouver Fraser Port AuthorityYahoo Finance[7]
- 20 Jul 2026Schedule
Completion now targeted for early 2034
Vancouver Fraser Port AuthorityYahoo Finance[7]
- 14 May 2025Schedule
Major construction to start in 2028
Vancouver Fraser Port AuthorityDelta Optimist[6]
- 20 Apr 2023Status
Federal approval
Government of CanadaCBC News[2]
- 20 Apr 2023Cost
'Over $2 billion'
The article doesn't say who estimated it, so it isn't used as the official figure.
Daily Hive (figure not attributed)Daily Hive[3]
- 20 Apr 2023Cost
Widely reported: $3.5B
Reported at federal approval without saying who estimated it, so not used as the official figure.
The Globe and Mail; Global NewsThe Globe and Mail[4]Global News[5]
- 6 Feb 2015Cost
About $1.9B
From the environmental impact statement, in 2013 dollars.
Port Metro Vancouver (now Vancouver Fraser Port Authority)Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)[1]First price
- 6 Feb 2015Schedule
Fully operational from 2024
Port Metro VancouverPort Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)[1]
- 6 Feb 2015Schedule
Construction to finish in 2023
Port Metro VancouverPort Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)[1]
In the news
- Carney grants new $5.9-billion Metro Vancouver superport national interest status
Daily Hive, 30 Oct 2026
Links to outside coverage. All news
Sources
- Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates), 6 Feb 2015
“The estimated economic cost is approximately $1.9 billion for building the new marine terminal, widening the causeway, dredging the dredge basin, expanding the existing tug basin, and testing and training on the container handling equipment.”
“The Project would have the capacity to be fully operational beginning in 2024.”
“This equipment is projected to be installed in the last construction year, 2023, and there will be on-site training and start-up measures undertaken by the Terminal Operator Concessionaire during this year too.”
- CBC News, 20 Apr 2023
“The federal government has given the OK for a major new container terminal on Canada's West Coast”
- Daily Hive, 20 Apr 2023
“The estimated cost of building Roberts Bank Terminal 2 is over $2 billion, with the project self-funded by the port authority.”
- The Globe and Mail, 20 Apr 2023
“The federal government has approved the Port of Vancouver’s proposed $3.5-billion container terminal, saying the project will spur economic growth while complying with environmental rules.”
- Global News, 20 Apr 2023
“Private investments and the Vancouver Fraser Port Authority will fund its estimated $3.5 billion cost.”
- Delta Optimist, 14 May 2025
“Construction mobilization and early works are expected to occur in 2027, with major land reclamation works expected to begin in 2028.”
- Yahoo Finance, 20 Jul 2026
“The Vancouver Fraser Port Authority has selected the TerraMarine joint venture (JV) as the preferred proponent for the landmass and wharf infrastructure component of the Roberts Bank Terminal 2 Project in Delta city of British Columbia.”
“Completion is targeted for early 2034, and terminal operations are anticipated to begin in the mid-2030s.”
- Indo-Canadian Voice (Government of Canada news release, reprinted in full), 30 Oct 2026
“Through collaboration with the Major Projects Office, the VFPA, and other federal partners, RBT2, a $5.9 billion investment in Canada’s trade infrastructure, is on a viable path to Final Investment Decision (FID) by mid-2027.”
“Friday’s listing decision provides upfront certainty on the remaining applicable federal regulatory authorizations, and accelerates the project’s commercial operations by up to four years, from 2039 to 2035.”
- Daily Hive, 30 Oct 2026
“The Government of Canada announced the formal designation today, noting that it could bring the superport into operation in 2035 instead of 2039 by speeding up the remaining federal approvals.”