Sturgeon Refinery
A bitumen refinery near Redwater, Alberta, built by the North West Redwater Partnership under a deal in which the province supplies most of the bitumen and pays processing tolls for decades. Alberta became a 50 per cent owner in 2021.
Sturgeon Refinery was first priced at $5.7 billion in 2012 by North West Redwater Partnership. The latest official estimate is $8.5 billion (2013, North West Redwater Partnership), 1.5 times the first price after adjusting for inflation.
Also called: North West Redwater, NWR refinery
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.5×the first quoted price released to the public
- First price 2012, North West Redwater Partnership
- Latest estimate 2013, North West Redwater Partnership
- Independent estimate 2017, AltaCorp Capital
The independent figure is in line with the latest official estimate.
Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,134
- Status
- Operational
- Owner
- North West Redwater Partnership
- Scope
- Unchanged
Every estimate
Project owner Other
4 public cost estimates from 2012 to 2020.
Schedule
- Opening targetSet in 2016
- 2017
- Delay
- None so far
A target given only as a year counts as the end of that year.
Location
Timeline
- 5 Jul 2021Milestone
Province becomes half-owner
Government of AlbertaCBC News[1]
- 2020Cost
Ended up at $10.1B
Reported by CBC without attribution, so shown as a media figure.
CBC NewsCBC News[1]
- 29 Jun 2017Cost
Analyst: $9.3B
AltaCorp Capital (analyst)Oil Sands Magazine[4]
- 5 Jan 2016Schedule
Slated to open in 2017
North West Redwater PartnershipCBC News[3]
- Dec 2013Cost
Raised to $8.5B
The province's estimate of the tolls it would pay to have its bitumen refined rose from $19B to $26B the following June.
North West Redwater PartnershipCBC News (opinion, Andrew Leach)[2]
- 8 Nov 2012Cost
Sanctioned: $5.7B
North West Redwater PartnershipCBC News[1]First price
Sources
- CBC News, 5 Jul 2021
“The cost of building the refinery was estimated at $5.7 billion when construction started in 2013 and ended up at $10.1 billion last year.”
“The deal announced Monday has North West Refining transferring its ownership stake to the government of Alberta, which gives the province an equal vote in the operations.”
- CBC News (opinion, Andrew Leach), 14 Sep 2020
“In December of 2013, the expected capital cost of the project was increased from $5.7 billion to $8.5 billion, and the following June, the government's estimate of the tolls we would all pay to refine our bitumen was increased from $19 billion to $26 billion.”
- CBC News, 5 Jan 2016
“It's slated to open in 2017.”
- Oil Sands Magazine, 29 Jun 2017
“According to AltaCorp Capital, the latest price tag for the Sturgeon Refinery is now $9.3 billion, up another $800 million from previous estimates.”