Overruns
← All projects

North Coast Transmission Line

A second 500-kilovolt line from Prince George to Terrace (phases 1 and 2), later extended north toward Bob Quinn Lake (phase 3), built by Crown utility BC Hydro to power LNG and mining projects on the North Coast.

North Coast Transmission Line was first priced at $3 billion in 2023 by BC Hydro. The latest official estimate is $6 billion (2025, the Government of British Columbia), 1.9 times the first price after adjusting for inflation.

Also called: NCTL

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.9×the first quoted price released to the public

First price 2023, BC Hydro
$3.3B
Latest estimate 2025, Government of British Columbia
$6.2B

Adjusted for inflation to 2026 dollars.

Days since announced
1,410
Status
Under construction
Owner
BC Hydro
Scope
Unchanged

Every estimate

Government Project owner

2 public cost estimates from 2023 to 2025.

Schedule

Completion target
Set in 2026
2032
Delay
None so far

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 3 Sep 2026
    Status

    Construction begins; $3.9B committed by Ottawa and B.C.

    $3.9B is funding, not a cost estimate.

    Government of Canada and Province of British ColumbiaGovernment of Canada news release, via BOE Report[5]

  2. 3 Sep 2026
    Schedule

    Phase 2 complete by winter 2032

    Phase 1 is due mid-2030.

    Government of CanadaReNew Canada[6]

  3. 20 Oct 2025
    Cost

    Phases 1 and 2 now $6B

    Government of British ColumbiaThe Tyee[3]Daily Hive[4]

  4. 21 Feb 2023
    Cost

    $3B

    For the Prince George–Terrace line, later phases 1 and 2.

    BC Hydro (Chris O'Riley, CEO)The Globe and Mail[2]First price

  5. 19 Jan 2023
    Announcement

    BC Hydro starts planning a second Prince George-Terrace line

    O'Riley said construction would likely not start this decade.

    BC Hydro (Chris O'Riley, CEO)Prince George Citizen (Glacier Media), via Powell River Peak[1]

Sources

  1. Prince George Citizen (Glacier Media), via Powell River Peak, 19 Jan 2023
    ““Today we announced the start of a process to look at twinning the 500,000 volt transmission line between Prince George and Terrace and that would support potential industrial development on the North Coast,” said BC Hydro president/CEO Chris O’Riley”
  2. The Globe and Mail, 21 Feb 2023
    “The time frame for a $3-billion transmission project in northern British Columbia could be accelerated to supply more hydroelectricity to industrial customers such as LNG Canada, BC Hydro’s chief executive officer says.”
  3. The Tyee, 21 Oct 2025
    “The government estimates the first two phases will cost $6 billion.”
  4. Daily Hive, 26 Oct 2025
    “The project’s estimated cost has risen from $3 billion to $6 billion, and the provincial government is seeking federal support to help cover a portion of the investment.”
  5. Government of Canada news release, via BOE Report, 3 Sep 2026
    “Under the agreement, the Government of Canada and the Province of British Columbia are committing $3.9 billion toward phases 1 and 2 of the project to deliver clean, reliable, and affordable electricity to communities across British Columbia.”
  6. ReNew Canada, 4 Sep 2026
    “Construction of Phase 2 is anticipated to begin in 2027 and be complete by winter 2032.”

How we count