Grays Bay Road and Port

A proposed ~230 km all-season road from the end of the Tibbitt-Contwoyto winter road to a deep-water port at Grays Bay on Nunavut's Coronation Gulf. The proponent is West Kitikmeot Resources Corp. (owned by the Kitikmeot Inuit Association); Ottawa funds pre-construction.

Grays Bay Road and Port was first priced at $550 million in 2016 by Kitikmeot Inuit Association and Government of Nunavut. The latest official estimate is $1 billion (2024, West Kitikmeot Resources Corp.), 1.5 times the first price after adjusting for inflation.

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.5×the first quoted price released to the public

First price 2016, Kitikmeot Inuit Association and Government of Nunavut
$730M
Latest estimate 2024, West Kitikmeot Resources Corp.
$1.1B

Adjusted for inflation to 2026 dollars.

Days since announced
3,985
Status
Planning
Owner
West Kitikmeot Resources Corp.
Scope
Unchanged

Every estimate

Government Project owner

3 public cost estimates from 2016 to 2024.

Schedule

Completion target
Set in 2024
2035
Delay
None so far

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 20 May 2026
    Milestone

    Up to $50M for pre-construction

    Government of CanadaNunatsiaq News[4]

  2. 15 Oct 2024
    Cost

    'Close to $1 billion'

    West Kitikmeot Resources Corp. (Brendan Bell, CEO)Nunatsiaq News[1]

  3. 15 Oct 2024
    Schedule

    Could be operational by 2035

    West Kitikmeot Resources Corp. (Brendan Bell, CEO)Nunatsiaq News[1]

  4. 9 Apr 2019
    Status

    Project restarts at $550M

    Kitikmeot Inuit AssociationNunatsiaq News[3]

  5. 16 Apr 2018
    Cost

    $527M (January 2018 economic assessment)

    The territorial minister gave $435M in the same story.

    Government of NunavutCBC News[2]

  6. 16 Apr 2018
    Status

    Federal funding denied; Nunavut pulls out

    Government of NunavutCBC News[2]

  7. 2016
    Cost

    $550M

    Reported in 2024; the 2016 source was not found.

    Kitikmeot Inuit Association and Government of NunavutNunatsiaq News[1]First price

Sources

  1. Nunatsiaq News, 15 Oct 2024
    “Grays Bay was first proposed by the Kitikmeot Inuit Association and the Government of Nunavut in 2016 as a $550-million “nation-building””
    “Since 2016, the estimated price tag for the project has nearly doubled to close to $1 billion due to inflation, Bell said.”
    “The proposed Grays Bay 230-kilometre all-season road and deepsea port that would link western Nunavut to the rest of Canada might be operational by 2035, says Brendan Bell, CEO of West Kitikmeot Resources Corp.”
  2. CBC News, 16 Apr 2018
    “The Nunavut government has pulled its resources out of the Grays Bay Road and Port Project, after its request for federal funding to cover three-quarters of the estimated $527-million price tag was denied by Ottawa last week.”
  3. Nunatsiaq News, 9 Apr 2019
    “The $550-million Grays Bay project would involve the construction of a 227-kilometre all-weather road running from the site of the defunct Jericho mine, which is located at the northern end of the Tibbit-Contwoyto winter road, to a deep-sea port at Grays Bay on Coronation Gulf.”
  4. Nunatsiaq News, 20 May 2026
    “Preconstruction work inched another step closer for the Grays Bay Road and Port project after the federal government announced up to $50 million in funding.”

How we count