Muskrat Falls
An 824-megawatt hydroelectric dam on the lower Churchill River in Labrador, with a transmission link to the island of Newfoundland, built by the provincial Crown corporation Nalcor Energy. Ottawa guaranteed the loans and later helped pay for the overrun.
Muskrat Falls was first priced at $5 billion in 2010 by Nalcor Energy. The latest official estimate is $10.1 billion (2017, Nalcor Energy), 1.8 times the first price after adjusting for inflation. It was completed 5 years, 4 months after the original opening target of 2017.
Also called: Lower Churchill Project (phase 1)
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.8×the first quoted price released to the public
- First price 2010, Nalcor Energy
- Latest estimate 2017, Nalcor Energy
Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,855
- Status
- Complete
- Owner
- Nalcor Energy, now Newfoundland and Labrador Hydro
- Scope
- Unchanged
Every estimate
Project owner
4 public cost estimates from 2010 to 2017.
Left out because they measure something else: $7.4B total including financing, 2012; $12.7B total including financing, 2017; $13.1B total including financing, 2020.
Schedule
- Original opening targetSet in 2014
- 2017
- Completed
- 12 Apr 2023
- Delay
- 5 years, 4 months
A target given only as a year counts as the end of that year.
Route
Timeline
- 12 Apr 2023Status
Project declared commissioned
With financing, the total is more than $13B.
Newfoundland and Labrador HydroThe Canadian Press, via Global News[2]
- 26 May 2020Cost
Up to $13.1B including financing
After a four-month pandemic shutdown of construction.
Nalcor Energy (Stan Marshall, CEO)CBC News[4]
- 23 Jun 2017Cost
Capital cost now $10.1B
Nalcor's CEO called the project a boondoggle.
Nalcor Energy (Stan Marshall, CEO)CBC News[3]
- 23 Jun 2017Cost
$12.7B including financing
Nalcor Energy (Stan Marshall, CEO)CBC News[3]
- 26 Jun 2014Cost
$6.99B
Nalcor Energy (Ed Martin, CEO)CBC News[1]
- 26 Jun 2014Schedule
Power expected in 2017
Nalcor EnergyCBC News[1]
- 17 Dec 2012Cost
Sanctioned at $6.2B
Capital cost only. With financing, the sanction figure was about $7.4B.
Nalcor EnergyCBC News[1]
- 17 Dec 2012Cost
About $7.4B including financing
Nalcor EnergyThe Canadian Press, via Global News[2]
- 18 Nov 2010Cost
Announced: $5B for Newfoundland and Labrador's share
Announced in November 2010 with Emera. Covers the dam and the transmission link to the island; Emera's Maritime Link is separate.
Nalcor EnergyCBC News[1]First price
Sources
- CBC News, 26 Jun 2014
“The share of expenses for Muskrat Falls that Newfoundland and Labrador ratepayers were initially expected to bear was $5 billion.”
“When the Muskrat Falls Project was sanctioned in December 2012, the estimated capital cost of the development was $6.2 billion.”
“This new $6.99-billion price tag is the second upwards shift since the megaproject was announced in late 2010.”
“Nalcor says the latest jump in construction costs will add $8 a month to the average electricity bill in the province when Muskrat comes on stream in 2017.”
- The Canadian Press, via Global News, 12 Apr 2023
“Muskrat Falls was officially approved in 2012 with an initial price tag of around $7.4 billion, which has ballooned to more than $13 billion.”
“Muskrat Falls hydroelectric project in N.L. considered commissioned: CEO”
- CBC News, 23 Jun 2017
“It's not only the capital cost of building Muskrat Falls that has risen — to $10.1 billion from $6.2 billion, plus financing.”
“Labrador's Muskrat Falls price tag now $12.7B: Worse than 1969 Quebec deal, CEO says”
- CBC News, 26 May 2020
“That could bring the total cost of the project from $12.7 billion to $13.1 billion.”