Overruns
← All projects

Muskrat Falls

An 824-megawatt hydroelectric dam on the lower Churchill River in Labrador, with a transmission link to the island of Newfoundland, built by the provincial Crown corporation Nalcor Energy. Ottawa guaranteed the loans and later helped pay for the overrun.

Muskrat Falls was first priced at $5 billion in 2010 by Nalcor Energy. The latest official estimate is $10.1 billion (2017, Nalcor Energy), 1.8 times the first price after adjusting for inflation. It was completed 5 years, 4 months after the original opening target of 2017.

Also called: Lower Churchill Project (phase 1)

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.8×the first quoted price released to the public

First price 2010, Nalcor Energy
$7.3B
Latest estimate 2017, Nalcor Energy
$13B

Adjusted for inflation to 2026 dollars.

Days since announced
5,855
Status
Complete
Owner
Nalcor Energy, now Newfoundland and Labrador Hydro
Scope
Unchanged

Every estimate

Project owner

4 public cost estimates from 2010 to 2017.

Left out because they measure something else: $7.4B total including financing, 2012; $12.7B total including financing, 2017; $13.1B total including financing, 2020.

Schedule

Original opening target
Set in 2014
2017
Completed
12 Apr 2023
Delay
5 years, 4 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 12 Apr 2023
    Status

    Project declared commissioned

    With financing, the total is more than $13B.

    Newfoundland and Labrador HydroThe Canadian Press, via Global News[2]

  2. 26 May 2020
    Cost

    Up to $13.1B including financing

    After a four-month pandemic shutdown of construction.

    Nalcor Energy (Stan Marshall, CEO)CBC News[4]

  3. 23 Jun 2017
    Cost

    Capital cost now $10.1B

    Nalcor's CEO called the project a boondoggle.

    Nalcor Energy (Stan Marshall, CEO)CBC News[3]

  4. 23 Jun 2017
    Cost

    $12.7B including financing

    Nalcor Energy (Stan Marshall, CEO)CBC News[3]

  5. 26 Jun 2014
    Cost

    $6.99B

    Nalcor Energy (Ed Martin, CEO)CBC News[1]

  6. 26 Jun 2014
    Schedule

    Power expected in 2017

    Nalcor EnergyCBC News[1]

  7. 17 Dec 2012
    Cost

    Sanctioned at $6.2B

    Capital cost only. With financing, the sanction figure was about $7.4B.

    Nalcor EnergyCBC News[1]

  8. 17 Dec 2012
    Cost

    About $7.4B including financing

    Nalcor EnergyThe Canadian Press, via Global News[2]

  9. 18 Nov 2010
    Cost

    Announced: $5B for Newfoundland and Labrador's share

    Announced in November 2010 with Emera. Covers the dam and the transmission link to the island; Emera's Maritime Link is separate.

    Nalcor EnergyCBC News[1]First price

Sources

  1. CBC News, 26 Jun 2014
    “The share of expenses for Muskrat Falls that Newfoundland and Labrador ratepayers were initially expected to bear was $5 billion.”
    “When the Muskrat Falls Project was sanctioned in December 2012, the estimated capital cost of the development was $6.2 billion.”
    “This new $6.99-billion price tag is the second upwards shift since the megaproject was announced in late 2010.”
    “Nalcor says the latest jump in construction costs will add $8 a month to the average electricity bill in the province when Muskrat comes on stream in 2017.”
  2. The Canadian Press, via Global News, 12 Apr 2023
    “Muskrat Falls was officially approved in 2012 with an initial price tag of around $7.4 billion, which has ballooned to more than $13 billion.”
    “Muskrat Falls hydroelectric project in N.L. considered commissioned: CEO”
  3. CBC News, 23 Jun 2017
    “It's not only the capital cost of building Muskrat Falls that has risen — to $10.1 billion from $6.2 billion, plus financing.”
    “Labrador's Muskrat Falls price tag now $12.7B: Worse than 1969 Quebec deal, CEO says”
  4. CBC News, 26 May 2020
    “That could bring the total cost of the project from $12.7 billion to $13.1 billion.”

How we count