Keeyask Generating Station

A 695-megawatt hydroelectric station on the Nelson River in northern Manitoba, built by Manitoba Hydro in partnership with four Cree Nations. All seven units were in service by March 2022.

Keeyask Generating Station was first priced at $5.6 billion in 2011 by Manitoba Hydro. The latest official estimate is $8.7 billion (2021, Manitoba Hydro), 1.3 times the first price after adjusting for inflation. It was completed 2 years, 3 months after the original opening target of 2019.

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.3×the first quoted price released to the public

First price 2011, Manitoba Hydro
$8B
Latest estimate 2021, Manitoba Hydro
$10B
Independent estimate 2017, MGF Project Services
up to $14B

The most recent independent estimate (MGF Project Services, 2017) came out well before the latest official figure, so the two aren’t compared.

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
5,606
Status
Complete
Owner
Keeyask Hydropower Limited Partnership
Scope
Unchanged

Every estimate

Project owner Other

6 public cost estimates from 2011 to 2021.

Schedule

Original opening target
Set in 2011
2019
Completed
9 Mar 2022
Delay
2 years, 3 months

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 9 Mar 2022
    Status

    Seventh and final unit online

    Some construction inside the powerhouse continued through late summer 2022.

    Keeyask Hydropower Limited PartnershipKeeyask Hydropower Limited Partnership[8]

  2. 18 Feb 2021
    Cost

    First unit produces power, budget still $8.7B

    Hydro reaffirmed the 2017 control budget as the first unit began producing electricity.

    Manitoba HydroCBC News[3]

  3. 19 Dec 2017
    Cost

    PUB consultant: could reach $10.5B

    Manitoba Hydro called this a worst-case scenario, not a projected outcome.

    MGF Project Services (consultant to the Manitoba Public Utilities Board)CBC News[7]

  4. 7 Mar 2017
    Cost

    Control budget raised to $8.7B

    Hydro blamed poor contractor productivity and foundation work once the bedrock was better understood.

    Manitoba Hydro (Kelvin Shepherd, CEO)CBC News[5]Global News[6]

  5. 7 Mar 2017
    Schedule

    In-service date moved to August 2021

    Manitoba HydroGlobal News[6]

  6. 21 Sep 2016
    Cost

    Board review: $7.2B to $7.8B

    From a review by Manitoba Hydro's board, released by the new provincial government. It also projected a delay of 21 to 31 months.

    Manitoba Hydro-Electric Board (review)Government of Manitoba[4]

  7. 16 Jul 2014
    Cost

    Construction starts at $6.5B

    The budget approved after the 2014 Needs For and Alternatives To review by the Public Utilities Board.

    Keeyask Hydropower Limited Partnership (Manitoba Hydro and four Cree Nations)Keeyask Hydropower Limited Partnership[2]

  8. 16 Jul 2014
    Schedule

    All seven units by 2020

    Keeyask Hydropower Limited PartnershipKeeyask Hydropower Limited Partnership[2]

  9. 16 Jul 2014
    Schedule

    First power set for November 2019

    Keeyask Hydropower Limited PartnershipCBC News[3]

  10. 25 Jul 2011
    Cost

    Early works begin on a $5.6B station

    The earliest public cost figure found for the station, quoted as infrastructure work started ahead of regulatory review.

    Manitoba HydroCanadian Consulting Engineer[1]First price

  11. 25 Jul 2011
    Schedule

    First unit targeted for 2019

    Manitoba HydroCanadian Consulting Engineer[1]

Sources

  1. Canadian Consulting Engineer, 25 Jul 2011
    “Work is beginning this summer on infrastructure to support the $5.6-billion Keeyask hydroelectric generating station on the Nelson River in Manitoba.”
    “There will be seven generator units, with 2019 targeted as the date for the first unit to go into service.”
  2. Keeyask Hydropower Limited Partnership, 16 Jul 2014
    “The first generator unit in-service date is targeted for 2019 with all units being commissioned by 2020 at a total cost of $6.5 billion.”
  3. CBC News, 18 Feb 2021
    “It was initially estimated to cost $6.5 billion and expected to be in service by November 2019.”
    “In March 2017, Hydro revised that cost estimate to its current control budget of $8.7 billion, which the Crown energy corporation says it's on track to meet.”
  4. Government of Manitoba, 21 Sep 2016
    “the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion, whereas Keeyask is expected to rise to between $7.2 and $7.8 billion from the current budget of $6.5 billion”
  5. CBC News, 7 Mar 2017
    “Dam project now expected to cost $8.7B; in-service date pushed back 21 months”
  6. Global News, 7 Mar 2017
    “In a news release sent Tuesday Manitoba Hydro said the previously approved budget of $6.5 billion had been revised to not only include rising costs, but a revised completion date.”
    “Instead of November 2019, the new ‘in-service date’ is August 2021.”
  7. CBC News, 19 Dec 2017
    “It found the Keeyask dam could cost as much as $10.5 billion due to the "contractor's poor productivity and increased indirect costs" associated with the project.”
  8. Keeyask Hydropower Limited Partnership, 9 Jun 2022
    “Wednesday, March 9, 2022, this is the final unit — of Keeyask’s total of seven units — to be brought online.”