Keeyask Generating Station
A 695-megawatt hydroelectric station on the Nelson River in northern Manitoba, built by Manitoba Hydro in partnership with four Cree Nations. All seven units were in service by March 2022.
Keeyask Generating Station was first priced at $5.6 billion in 2011 by Manitoba Hydro. The latest official estimate is $8.7 billion (2021, Manitoba Hydro), 1.3 times the first price after adjusting for inflation. It was completed 2 years, 3 months after the original opening target of 2019.
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.3×the first quoted price released to the public
- First price 2011, Manitoba Hydro
- Latest estimate 2021, Manitoba Hydro
- Independent estimate 2017, MGF Project Services
The most recent independent estimate (MGF Project Services, 2017) came out well before the latest official figure, so the two aren’t compared.
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,606
- Status
- Complete
- Owner
- Keeyask Hydropower Limited Partnership
- Scope
- Unchanged
Every estimate
Project owner Other
6 public cost estimates from 2011 to 2021.
Schedule
- Original opening targetSet in 2011
- 2019
- Completed
- 9 Mar 2022
- Delay
- 2 years, 3 months
A target given only as a year counts as the end of that year.
Location
Timeline
- 9 Mar 2022Status
Seventh and final unit online
Some construction inside the powerhouse continued through late summer 2022.
Keeyask Hydropower Limited PartnershipKeeyask Hydropower Limited Partnership[8]
- 18 Feb 2021Cost
First unit produces power, budget still $8.7B
Hydro reaffirmed the 2017 control budget as the first unit began producing electricity.
Manitoba HydroCBC News[3]
- 19 Dec 2017Cost
PUB consultant: could reach $10.5B
Manitoba Hydro called this a worst-case scenario, not a projected outcome.
MGF Project Services (consultant to the Manitoba Public Utilities Board)CBC News[7]
- 7 Mar 2017Cost
Control budget raised to $8.7B
Hydro blamed poor contractor productivity and foundation work once the bedrock was better understood.
Manitoba Hydro (Kelvin Shepherd, CEO)CBC News[5]Global News[6]
- 7 Mar 2017Schedule
In-service date moved to August 2021
Manitoba HydroGlobal News[6]
- 21 Sep 2016Cost
Board review: $7.2B to $7.8B
From a review by Manitoba Hydro's board, released by the new provincial government. It also projected a delay of 21 to 31 months.
Manitoba Hydro-Electric Board (review)Government of Manitoba[4]
- 16 Jul 2014Cost
Construction starts at $6.5B
The budget approved after the 2014 Needs For and Alternatives To review by the Public Utilities Board.
Keeyask Hydropower Limited Partnership (Manitoba Hydro and four Cree Nations)Keeyask Hydropower Limited Partnership[2]
- 16 Jul 2014Schedule
All seven units by 2020
Keeyask Hydropower Limited PartnershipKeeyask Hydropower Limited Partnership[2]
- 16 Jul 2014Schedule
First power set for November 2019
Keeyask Hydropower Limited PartnershipCBC News[3]
- 25 Jul 2011Cost
Early works begin on a $5.6B station
The earliest public cost figure found for the station, quoted as infrastructure work started ahead of regulatory review.
Manitoba HydroCanadian Consulting Engineer[1]First price
- 25 Jul 2011Schedule
First unit targeted for 2019
Manitoba HydroCanadian Consulting Engineer[1]
Sources
- Canadian Consulting Engineer, 25 Jul 2011
“Work is beginning this summer on infrastructure to support the $5.6-billion Keeyask hydroelectric generating station on the Nelson River in Manitoba.”
“There will be seven generator units, with 2019 targeted as the date for the first unit to go into service.”
- Keeyask Hydropower Limited Partnership, 16 Jul 2014
“The first generator unit in-service date is targeted for 2019 with all units being commissioned by 2020 at a total cost of $6.5 billion.”
- CBC News, 18 Feb 2021
“It was initially estimated to cost $6.5 billion and expected to be in service by November 2019.”
“In March 2017, Hydro revised that cost estimate to its current control budget of $8.7 billion, which the Crown energy corporation says it's on track to meet.”
- Government of Manitoba, 21 Sep 2016
“the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion, whereas Keeyask is expected to rise to between $7.2 and $7.8 billion from the current budget of $6.5 billion”
- CBC News, 7 Mar 2017
“Dam project now expected to cost $8.7B; in-service date pushed back 21 months”
- Global News, 7 Mar 2017
“In a news release sent Tuesday Manitoba Hydro said the previously approved budget of $6.5 billion had been revised to not only include rising costs, but a revised completion date.”
“Instead of November 2019, the new ‘in-service date’ is August 2021.”
- CBC News, 19 Dec 2017
“It found the Keeyask dam could cost as much as $10.5 billion due to the "contractor's poor productivity and increased indirect costs" associated with the project.”
- Keeyask Hydropower Limited Partnership, 9 Jun 2022
“Wednesday, March 9, 2022, this is the final unit — of Keeyask’s total of seven units — to be brought online.”