Canadian Surface Combatant

Fifteen River-class warships being built by Irving Shipbuilding in Halifax to replace the navy's Halifax-class frigates and retired destroyers. Construction began in 2024 and the full order of 15 is not due until 2050.

Canadian Surface Combatant was first priced at $26.2 billion in 2008 by the Government of Canada. The latest official estimate is $60 billion (2026, National Defence), 1.6 times the first price after adjusting for inflation. The first delivery target has moved 1 year, from 2030 to 2031.

Also called: CSC warships

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.6×the first quoted price released to the public

First price 2008, Government of Canada
$39B
Latest estimate 2026, National Defence
$61B
Watchdog estimate 2022, Parliamentary Budget Officer
$95B

The most recent independent estimate (Parliamentary Budget Officer, 2022) came out well before the latest official figure, so the two aren’t compared.

Adjusted for inflation to 2026 dollars.

Days since announced
6,907
Status
Under construction
Owner
National Defence
Scope
Unchanged

Every estimate

Government Watchdog

7 public cost estimates from 2008 to 2026.

Left out because they measure something else: $306B lifecycle, 2022; $22.2B first three ships only, 2025.

Schedule

Original first delivery target
Set in 2021
2030
Current first delivery target
Set in 2022
2031
Delay
1 year

A target given only as a year counts as the end of that year.

Route

No location on file.

Timeline

  1. 12 Jun 2026
    Cost

    About $60B for all 15 ships

    National DefenceThe Canadian Press, via CKOM[8]

  2. 8 Mar 2025
    Cost

    First three ships: $22.2B

    A subset of the fleet, not comparable with the 15-ship figures.

    National DefenceThe Canadian Press, via Sault Ste. Marie News[7]

  3. 27 Oct 2022
    Cost

    PBO: $84.5B to design and buy

    Development and acquisition only. The PBO said the update reflects revised production schedules and inflation projections.

    Parliamentary Budget OfficerParliamentary Budget Office[5]

  4. 27 Oct 2022
    Cost

    PBO: $306B over the life of the ships

    Includes development, acquisition, operations, sustainment and disposal over 65 years. Not comparable with the acquisition budget.

    Parliamentary Budget OfficerParliamentary Budget Office[6]Lifecycle cost

  5. 27 Oct 2022
    Schedule

    PBO: first ship delivered 2031-32

    Parliamentary Budget OfficerParliamentary Budget Office[5]

  6. 24 Feb 2021
    Cost

    PBO: $77.3B

    Parliamentary Budget OfficerThe Hill Times[4]

  7. 2 Feb 2021
    Schedule

    First ship now 2030-31

    Reported as years later than expected. The same report says the first ship was originally to be delivered in the mid-2020s.

    National DefenceThe Canadian Press, via Global News[2]

  8. 2019
    Cost

    PBO: $69.8B

    Parliamentary Budget OfficerDefense News[3]

  9. 1 Jun 2017
    Cost

    PBO: $61.8B for 15 ships

    Parliamentary Budget OfficerThe Canadian Press, via CBC News[1]

  10. 2017
    Cost

    Budget set at $60B in 2017

    Date is the year the budget was established, as described in a 2021 report.

    Government of Canada (Liberal government)The Canadian Press, via Global News[2]

  11. 2008
    Cost

    2008 budget of about $26.2B

    For 15 ships. The PBO said no detailed documentation exists for how this original figure was built.

    Government of Canada (Conservative government)The Canadian Press, via CBC News[1]First price

Sources

  1. The Canadian Press, via CBC News, 1 Jun 2017
    “more than twice the original 2008 budget of about $26.2 billion.”
    “The parliamentary budget officer estimates Ottawa will have to spend nearly $61.8 billion to replace 15 ships”
  2. The Canadian Press, via Global News, 2 Feb 2021
    “Crosby, however, was adamant that the project remains within the $60-billion budget established by the Liberal government in 2017.”
    ““We’re looking at the first ship being delivered to us in the early 2030s. … In this case, we’re really more specifically looking at the 2030-31 timeframe.””
  3. Defense News, 27 Oct 2022
    “The procurement cost ticked up to CA$69.8 billion in 2019, after Canada selected Lockheed Martin’s design for the ship, and then to CA$77.3 billion in 2021.”
  4. The Hill Times, 1 Mar 2021
    “The Feb. 24, 2021, report from the Parliamentary Budget Officer estimates that it will cost $77.3-billion to acquire 15 Canadian Surface Combatants.”
  5. Parliamentary Budget Office, 27 Oct 2022
    “The PBO’s latest estimates for the Development and Acquisition phases have jumped to $84.5 billion.”
    “The Operations and Sustainment phase is estimated at $219.8 billion and is slated to begin in 2031-32, with the delivery of the first ship to the Royal Canadian Navy.”
  6. Parliamentary Budget Office, 27 Oct 2022
    “Highlights The total life cycle cost of the CSC program is estimated to be $306.0 billion.”
  7. The Canadian Press, via Sault Ste. Marie News, 8 Mar 2025
    “The implementation contract is worth $8 billion for the first six years and only covers part of the tab for the first three ships, which will eventually cost $22.2 billion, to be built in Halifax.”
  8. The Canadian Press, via CKOM, 12 Jun 2026
    “The Department of National Defence has said all 15 are expected to cost about $60-billion, but in 2022 the Parliamentary Budget Officer suggested it could be as much as $80 billion.”