Hamilton LRT

A 14 km light rail line across Hamilton from McMaster University to the east end. Funded in 2015, cancelled by the province in 2019, and revived in 2021 at more than three times the original commitment.

Hamilton LRT was first priced at $1 billion in 2015 by the Province of Ontario. The latest official estimate is $3.4 billion (2021, Governments of Canada and Ontario), 3 times the first price after adjusting for inflation. The construction start target has moved 3 years, from 2021 to 2024.

Also called: B-Line LRT

Reviewed monthly. Last review: 5 Nov 2026. How we update

3×the first quoted price released to the public

First price 2015, Province of Ontario
$1.3B
Latest estimate 2021, Governments of Canada and Ontario
$4.1B

Adjusted for inflation to 2026 dollars.

Days since announced
4,205
Status
Procurement
Owner
Metrolinx
Scope
Unchanged

Every estimate

Government

2 public cost estimates from 2015 to 2021.

Left out because they measure something else: $5.5B+ total as stated by the province, 2019.

Schedule

Original construction start target
Set in 2019
2021
Current construction start target
Set in 2021
2024
Delay
3 years

A target given only as a year counts as the end of that year.

Route

Timeline

  1. May 2025
    Status

    Civil works tender issued

    As of November 2025 the federal-provincial funding agreement was still not final.

    MetrolinxThe Public Record[1]

  2. May 2021
    Cost

    Revived with $3.4B

    Governments of Canada and OntarioThe Public Record[1]

  3. 11 May 2021
    Status

    Revived

    Governments of Canada and OntarioGlobal News[4]

  4. May 2021
    Schedule

    Construction to begin in 2024

    Governments of Canada and OntarioThe Public Record[1]

  5. 16 Dec 2019
    Schedule

    Construction expected to start in 2021

    MetrolinxGlobal News[2]

  6. 16 Dec 2019
    Cost

    Province: approaching $5.5B, project cancelled

    The province did not break this figure down at the time, so it is not compared with the capital commitments.

    Province of Ontario (Transportation Minister Caroline Mulroney)Link2Build[3]

  7. 16 Dec 2019
    Status

    Cancelled

    Province of OntarioThe Public Record[1]

  8. May 2015
    Cost

    Province commits $1B

    Province of Ontario (Premier Kathleen Wynne)The Public Record[1]First price

Sources

  1. The Public Record, 15 Nov 2025
    “The project was first funded with a $1-billion provincial funding commitment announced in May 2015 by the Ontario Liberal government of Premier Kathleen Wynne.”
    “The current Conservative government under Premier Doug Ford cancelled the project in December 2019, citing escalating costs.”
    “The project was revived in May 2021 with a new total capital commitment of $3.4 billion, jointly funded by the federal and provincial governments, with each committing $1.7 billion.”
    “At the time, it was promised that construction would begin in 2024.”
    “The request for proposals for the Hamilton LRT civil and utilities works package was issued in May 2025.”
  2. Global News, 16 Dec 2019
    “Work on the line was expected to start in 2021.”
  3. Link2Build, 18 Dec 2019
    “The Conservatives confirmed their commitment to funding the project during the 2018 election, but Mulroney said at her announcement that the project price tag is now approaching $5.5 billion.”
  4. Global News, 11 May 2021
    “The federal and provincial governments have offered $3.4 billion to build the 14 kilometre line.”

How we count