George Massey Crossing
A replacement for the 1959 George Massey Tunnel under the Fraser River between Richmond and Delta. First planned as a 10-lane bridge, cancelled in 2017, and replaced by an eight-lane immersed tunnel.
George Massey Crossing was first priced at $3.5 billion in 2017 by the Province of British Columbia. The latest official estimate is $8.5 billion (2026, the Province of British Columbia), 1.9 times the first price after adjusting for inflation. The opening target has moved 9 months, from 2030 to Sep 2031.
Also called: Massey bridge
Reviewed monthly. Last review: 5 Nov 2026. How we update
1.9×the first quoted price released to the public
- First price 2017, Province of British Columbia
- Latest estimate 2026, Province of British Columbia
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,421
- Status
- Procurement
- Owner
- Province of British Columbia, with federal funding
- Scope
- Changed in 2017
Every estimate
Government
3 public cost estimates from 2017 to 2026.
Schedule
- Original opening targetSet in 2022
- 2030
- Current opening targetSet in 2026
- Sep 2031
- Delay
- 9 months
A target given only as a year counts as the end of that year.
Location
Timeline
- 6 Jul 2026Cost
Budget more than doubles to $8.5B
Province of British Columbia (Transportation Minister Mike Farnworth)Global News[3]
- 6 Jul 2026Schedule
Completion now September 2031
Province of British ColumbiaGlobal News[3]
- 18 Mar 2022Cost
Tunnel: $4.15B
Province of British ColumbiaCBC News[2]
- 18 Mar 2022Schedule
Tunnel to open in 2030
Province of British ColumbiaCBC News[2]
- 18 Mar 2022Status
First contractor chosen
As of July 2026 main construction was projected to start in 2027.
Province of British ColumbiaCBC News[2]
- 2017Scope
Bridge cancelled, tunnel chosen
The 10-lane bridge was cancelled; in 2020 the province chose an eight-lane immersed tunnel instead.
Province of British ColumbiaGlobal News[1]
- 2017Cost
10-lane bridge: $3.5B
The figure for the BC Liberal government's bridge, approved in 2012 and cancelled in 2017. Its own first cost figure is not yet sourced.
Province of British ColumbiaGlobal News[1]First price
In the news
- Layoffs begin as formal request made to pause Massey Tunnel environmental review
Vancouver Sun, 18 Nov 2026
- Union bracing for layoffs amid B.C. Conservative plan to pause Massey Tunnel replacement
CBC News, 18 Nov 2026
- Doerkson calls for Massey Tunnel work to halt, says bridge option could save billions
CTV News, 12 Nov 2026
- B.C. premier-designate wants to pause Massey Tunnel replacement work until new cabinet ready
CBC News, 12 Nov 2026
- Feds 'all in' on new Massey crossing, whether bridge or tunnel
Cloverdale Reporter, 2 Nov 2026
Links to outside coverage. All news
Sources
- Global News, 7 Sep 2022
“The government had secured environmental approvals and already spent about $100 million on preparatory work for the $3.5-billion project when the NDP came to power in 2017 and cancelled it.”
- CBC News, 18 Mar 2022
“The B.C. government says it's chosen a main contractor for part of the major $4.15-billion project to replace the 62-year-old George Massey Tunnel and build an interchange.”
“The new tunnel is expected to open to traffic in 2030, the NDP government said.”
- Global News, 6 Jul 2026
“The budget for the project to replace the George Massey Tunnel has more than doubled to $8.5 billion.”
“The completion date for the project has also been pushed back from December 2030 to September 2031.”