Deep Geological Repository for used nuclear fuel

An underground repository near Ignace and Wabigoon Lake Ojibway Nation in northwestern Ontario for all of Canada's used nuclear fuel, run by the Nuclear Waste Management Organization and paid for by the nuclear utilities, mostly public (Ontario Power Generation, Hydro-Québec, NB Power, Atomic Energy of Canada).

Deep Geological Repository for used nuclear fuel was first priced at $16.9 billion in 2003 by CTECH and Cogema Logistics, with Ontario Power Generation. The latest official estimate is $26 billion (2021, Nuclear Waste Management Organization), 1.3 times the first price after adjusting for inflation.

Also called: NWMO nuclear waste repository

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.3×the first quoted price released to the public

First price 2003, CTECH and Cogema Logistics, with Ontario Power Generation
$25B
Latest estimate 2021, Nuclear Waste Management Organization
$32B

Adjusted for inflation to 2026 dollars.

Days since announced
8,733
Status
Planning
Owner
Nuclear Waste Management Organization
Scope
Changed in 2021

Every estimate

Project owner

3 public cost estimates from 2003 to 2021.

Left out because they measure something else: $4.5B capital cost, 2024.

Schedule

Construction start target
Set in 2024
2033
Delay
None so far

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 21 May 2025
    Schedule

    Operations start 2045

    Nuclear Waste Management OrganizationEngineering News-Record[6]

  2. 28 Nov 2024
    Milestone

    Site chosen: Wabigoon Lake Ojibway Nation-Ignace area

    Nuclear Waste Management OrganizationCBC News[5]

  3. 10 Jul 2024
    Schedule

    Construction from 2033; operating early 2040s

    Nuclear Waste Management OrganizationCBC News[4]

  4. 2024
    Cost

    Construction: $4.5B (2020 dollars)

    Construction only, in 2020 dollars.

    Nuclear Waste Management OrganizationNuclear Waste Management Organization, Implementing Adaptive Phased Management 2024-28[3]

  5. 5 Oct 2021
    Scope

    Planned inventory raised to 5.5 million fuel bundles

    Reference inventory raised from 3.6 million to about 5.5 million used fuel bundles.

    Nuclear Waste Management OrganizationNuclear Waste Management Organization, Annual Report 2021[2]

  6. 5 Oct 2021
    Cost

    $26B over the program's life, for 5.5 million bundles

    In 2020 dollars. NWMO says most of the increase comes from the larger inventory.

    Nuclear Waste Management OrganizationNuclear Waste Management Organization, Annual Report 2021[2]Lifecycle cost

  7. Oct 2011
    Cost

    $17.9B lifecycle (2010 dollars)

    Nuclear Waste Management OrganizationNuclear Waste Management Organization, APM cost estimate summary report APM-REP-00440-0011[1]Lifecycle cost

  8. 2003
    Cost

    $16.9B over the program's life

    NWMO's 2003 estimate, restated in 2010 dollars. Covers building, running and transport over about 150 years, for 3.6 million fuel bundles.

    CTECH and Cogema Logistics, with Ontario Power Generation (for the nuclear fuel owners)Nuclear Waste Management Organization, APM cost estimate summary report APM-REP-00440-0011[1]First priceLifecycle cost

Sources

  1. Nuclear Waste Management Organization, APM cost estimate summary report APM-REP-00440-0011, 1 Oct 2011
    “The previous cost estimate for an APM deep geological repository and used fuel transportation system for 3.6 million used CANDU fuel bundles was $16.9 billion (2010$), with a present value of $6.9 billion (2010$).”
    “The 2011 reference APM cost estimate for 3.6 million used CANDU fuel bundles is $17.9 billion (2010$), with a present value of $7.0 billion (2010$).”
  2. Nuclear Waste Management Organization, Annual Report 2021, 5 Oct 2021
    “For planning purposes, our 2021 cost estimate is based on an expected volume of about 5.5 million fuel bundles, the anticipated volume at the end of the planned operation of Canada’s existing nuclear reactors.”
    “Based on this expected volume, the total lifecycle cost of the project – from the beginning of site selection in 2010 to the completion of the project – is approximately $26 billion (in 2020 dollars).”
  3. Nuclear Waste Management Organization, Implementing Adaptive Phased Management 2024-28, 1 Jan 2024
    “This figure covers the initial investment of $4.5 billion (in 2020 dollars) in construction costs over a 10-year period, as well as many decades of lifecycle activity, stretching well into the next century.”
  4. CBC News, 10 Jul 2024
    “Whichever municipality ends up being chosen, the site won't be operational for some time; construction is expected to start in 2033, and the site would be up and running by the early 2040s.”
  5. CBC News, 28 Nov 2024
    “Northwestern Ontario has been chosen for Canada's first deep geological repository, a multibillion-dollar project that aims to eventually store the country's nuclear waste.”
  6. Engineering News-Record, 21 May 2025
    “Design is set to complete by 2028, with construction to begin by 2033 after design and environmental impact reviews by Canadian and indigenous regulators, and operation startup set for 2045.”

How we count