Quebec City Tramway
A planned tramway in Quebec City, first announced by the City and the Quebec government in 2018. Funding comes from the federal, provincial and municipal governments, and CDPQ Infra, the infrastructure arm of Quebec's public pension fund manager, took over planning in 2024.
Quebec City Tramway was first priced at $3 billion in 2018 by Ville de Québec and Government of Quebec. The latest official estimate is $7.6 billion (2024, the Government of Quebec), 2.1 times the first price after adjusting for inflation. The opening target has moved 7 years, from 2026 to 2033.
Also called: TramCité, tramway de Québec
Reviewed monthly. Last review: 5 Nov 2026. How we update
2.1×the first quoted price released to the public
- First price 2018, Ville de Québec and Government of Quebec
- Latest estimate 2024, Government of Quebec
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,180
- Status
- Planning
- Owner
- Ville de Québec and Government of Quebec
- Scope
- Changed in 2024
Every estimate
Government Project owner Other
5 public cost estimates from 2018 to 2024.
Left out because they measure something else: $4.8B CDPQ Infra's portion only (tramway delivery), not the full $7.6B, 2026.
Schedule
- Original opening targetSet in 2019
- 2026
- Current opening targetSet in 2024
- 2033
- Delay
- 7 years
A target given only as a year counts as the end of that year.
Location
Timeline
- 28 Oct 2026Cost
CDPQ Infra's share of the $7.6B is $4.8B
CDPQ Infra's written statement says its 2024 estimate covered only the part under its responsibility. Not a new total; the $7.6B (full line, including land and City items) is unchanged.
CDPQ InfraLe Soleil[9]
- 16 Dec 2024Cost
Now $7.6B for the revised line
The minister said the new evaluation includes the costs of the preparatory and related work required to deliver the project. It is for the shorter 19 km line.
Government of Quebec (Transport Minister Geneviève Guilbault)The Canadian Press, via CTV News[6]
- 16 Dec 2024Scope
Reconfigured as 19 km TramCité line
Development agreement with CDPQ Infra as prime contractor. The first line is 19 km from Le Gendre to Charlesbourg, compared with the 23 km Cap-Rouge to Charlesbourg line announced in 2018.
Government of Quebec, Ville de Québec and CDPQ InfraRailway Gazette International[7]CBC News[8]
- 16 Dec 2024Schedule
Commissioning in 2033
Government of Quebec, Ville de Québec and CDPQ InfraThe Canadian Press, via CTV News[6]
- 12 Jun 2024Scope
Caisse plan phases the line
CDPQ Infra's CITE plan (June 2024) proposed a central tramway line from Cap-Rouge to Charlesbourg, with the D'Estimauville extension deferred to a later phase, and smaller tram cars and stations to cut cost.
CDPQ Infra (La Caisse)Quebec Chronicle-Telegraph[5]
- 1 Nov 2023Cost
City revises cost to $8.4B
Announced after the only consortium bidding for the infrastructure contract could not meet the deadline or guarantee financing.
Ville de Québec (Mayor Bruno Marchand)Quebec Chronicle-Telegraph[4]
- 12 Apr 2023Cost
About $3.97B before the 2023 revision
The article does not say who made this estimate.
Urban Transport MagazineUrban Transport Magazine[3]
- 19 Aug 2019Cost
Cost now $3.3B
Government of Canada, Quebec and Ville de QuébecCBC News[2]
- 19 Aug 2019Schedule
Service to start in 2026
Government of Canada, Quebec and Ville de QuébecCBC News[2]
- 16 Mar 2018Cost
Announced: $3B tramway network
Announced by Mayor Régis Labeaume and Premier Philippe Couillard.
Ville de Québec and Government of QuebecCTV News Montreal[1]First price
In the news
- Le tramway sera livré «au meilleur coût», assure CDPQ Infra
Le Soleil, 28 Oct 2026 (en français)
- Une mise à jour des coûts pour le tramway attendue en 2027
Radio X, 13 Oct 2026 (en français)
Links to outside coverage. All news
Sources
- CTV News Montreal, 16 Mar 2018
“Quebec City has laid out its plans for a $3 billion tramway network and wants Ottawa and Quebec to pay for it.”
- CBC News, 19 Aug 2019
“The project is expected to cost $3.3 billion in total, with contributions coming from the federal, provincial and municipal governments.”
“First announced in 2018, the tramway is scheduled to start running in 2026.”
- Urban Transport Magazine, 12 Apr 2023
“However, the overall tram project has currently an estimated cost of 3.965 billion Canadian dollars (ca 2.7 billion Euros).”
- Quebec Chronicle-Telegraph, 27 Nov 2023
“Though the projected $8.365-billion cost is more than double the initial estimate five years ago, Mayor Bruno Marchand has said the city is still “all in” on the tramway project.”
- Quebec Chronicle-Telegraph, 19 Jun 2024
“Under the Caisse plan, the D’Estimauville extension would be built in Phase 2, and a line from Charlesbourg to the Lebourgneuf sector in the northwest in Phase 3.”
- The Canadian Press, via CTV News, 16 Dec 2024
“However, she pointed out that the $7.6 billion figure represents the current estimate, and that this figure could change over time.”
“According to agreements signed between the government, Quebec City and CDPQ Infra, which will be the project's prime contractor, work is due to start in the summer of 2027, with commissioning scheduled for 2033.”
- Railway Gazette International, 17 Dec 2024
“The first line of the tramway, which has been named TramCité, will run 19 km from Le Gendre to Charlesbourg, via Sainte-Foy, Université Laval, Parliament Hill and Saint-Roch with 29 stops and an underground section.”
- CBC News, 16 Mar 2018
“The tramway would extend over 23 kilometres, including two sections that would run underground.”
- Le Soleil, 28 Oct 2026
“Dans sa déclaration, CDPQ Infra rappelle que son estimation de 2024 couvrait uniquement la portion pour la «réalisation du tramway» sous sa responsabilité, évaluée à 4,8 milliards de dollars.”