Quebec City Tramway

A planned tramway in Quebec City, first announced by the City and the Quebec government in 2018. Funding comes from the federal, provincial and municipal governments, and CDPQ Infra, the infrastructure arm of Quebec's public pension fund manager, took over planning in 2024.

Quebec City Tramway was first priced at $3 billion in 2018 by Ville de Québec and Government of Quebec. The latest official estimate is $7.6 billion (2024, the Government of Quebec), 2.1 times the first price after adjusting for inflation. The opening target has moved 7 years, from 2026 to 2033.

Also called: TramCité, tramway de Québec

Reviewed monthly. Last review: 5 Nov 2026. How we update

2.1×the first quoted price released to the public

First price 2018, Ville de Québec and Government of Quebec
$3.8B
Latest estimate 2024, Government of Quebec
$8.1B

Adjusted for inflation to 2026 dollars.

Days since announced
3,180
Status
Planning
Owner
Ville de Québec and Government of Quebec
Scope
Changed in 2024

Every estimate

Government Project owner Other

5 public cost estimates from 2018 to 2024.

Left out because they measure something else: $4.8B CDPQ Infra's portion only (tramway delivery), not the full $7.6B, 2026.

Schedule

Original opening target
Set in 2019
2026
Current opening target
Set in 2024
2033
Delay
7 years

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 28 Oct 2026
    Cost

    CDPQ Infra's share of the $7.6B is $4.8B

    CDPQ Infra's written statement says its 2024 estimate covered only the part under its responsibility. Not a new total; the $7.6B (full line, including land and City items) is unchanged.

    CDPQ InfraLe Soleil[9]

  2. 16 Dec 2024
    Cost

    Now $7.6B for the revised line

    The minister said the new evaluation includes the costs of the preparatory and related work required to deliver the project. It is for the shorter 19 km line.

    Government of Quebec (Transport Minister Geneviève Guilbault)The Canadian Press, via CTV News[6]

  3. 16 Dec 2024
    Scope

    Reconfigured as 19 km TramCité line

    Development agreement with CDPQ Infra as prime contractor. The first line is 19 km from Le Gendre to Charlesbourg, compared with the 23 km Cap-Rouge to Charlesbourg line announced in 2018.

    Government of Quebec, Ville de Québec and CDPQ InfraRailway Gazette International[7]CBC News[8]

  4. 16 Dec 2024
    Schedule

    Commissioning in 2033

    Government of Quebec, Ville de Québec and CDPQ InfraThe Canadian Press, via CTV News[6]

  5. 12 Jun 2024
    Scope

    Caisse plan phases the line

    CDPQ Infra's CITE plan (June 2024) proposed a central tramway line from Cap-Rouge to Charlesbourg, with the D'Estimauville extension deferred to a later phase, and smaller tram cars and stations to cut cost.

    CDPQ Infra (La Caisse)Quebec Chronicle-Telegraph[5]

  6. 1 Nov 2023
    Cost

    City revises cost to $8.4B

    Announced after the only consortium bidding for the infrastructure contract could not meet the deadline or guarantee financing.

    Ville de Québec (Mayor Bruno Marchand)Quebec Chronicle-Telegraph[4]

  7. 12 Apr 2023
    Cost

    About $3.97B before the 2023 revision

    The article does not say who made this estimate.

    Urban Transport MagazineUrban Transport Magazine[3]

  8. 19 Aug 2019
    Cost

    Cost now $3.3B

    Government of Canada, Quebec and Ville de QuébecCBC News[2]

  9. 19 Aug 2019
    Schedule

    Service to start in 2026

    Government of Canada, Quebec and Ville de QuébecCBC News[2]

  10. 16 Mar 2018
    Cost

    Announced: $3B tramway network

    Announced by Mayor Régis Labeaume and Premier Philippe Couillard.

    Ville de Québec and Government of QuebecCTV News Montreal[1]First price

In the news

Links to outside coverage. All news

Sources

  1. CTV News Montreal, 16 Mar 2018
    “Quebec City has laid out its plans for a $3 billion tramway network and wants Ottawa and Quebec to pay for it.”
  2. CBC News, 19 Aug 2019
    “The project is expected to cost $3.3 billion in total, with contributions coming from the federal, provincial and municipal governments.”
    “First announced in 2018, the tramway is scheduled to start running in 2026.”
  3. Urban Transport Magazine, 12 Apr 2023
    “However, the overall tram project has currently an estimated cost of 3.965 billion Canadian dollars (ca 2.7 billion Euros).”
  4. Quebec Chronicle-Telegraph, 27 Nov 2023
    “Though the projected $8.365-billion cost is more than double the initial estimate five years ago, Mayor Bruno Marchand has said the city is still “all in” on the tramway project.”
  5. Quebec Chronicle-Telegraph, 19 Jun 2024
    “Under the Caisse plan, the D’Estimauville extension would be built in Phase 2, and a line from Charlesbourg to the Lebourgneuf sector in the northwest in Phase 3.”
  6. The Canadian Press, via CTV News, 16 Dec 2024
    “However, she pointed out that the $7.6 billion figure represents the current estimate, and that this figure could change over time.”
    “According to agreements signed between the government, Quebec City and CDPQ Infra, which will be the project's prime contractor, work is due to start in the summer of 2027, with commissioning scheduled for 2033.”
  7. Railway Gazette International, 17 Dec 2024
    “The first line of the tramway, which has been named TramCité, will run 19 km from Le Gendre to Charlesbourg, via Sainte-Foy, Université Laval, Parliament Hill and Saint-Roch with 29 stops and an underground section.”
  8. CBC News, 16 Mar 2018
    “The tramway would extend over 23 kilometres, including two sections that would run underground.”
  9. Le Soleil, 28 Oct 2026
    “Dans sa déclaration, CDPQ Infra rappelle que son estimation de 2024 couvrait uniquement la portion pour la «réalisation du tramway» sous sa responsabilité, évaluée à 4,8 milliards de dollars.”

How we count