Arctic and Offshore Patrol Ships

Ice-capable patrol ships for the Royal Canadian Navy, built by Irving Shipbuilding in Halifax under the National Shipbuilding Strategy. Announced in 2007 for delivery from 2013; the first ship arrived in 2020.

Arctic and Offshore Patrol Ships was first priced at $3.1 billion in 2007 by the Government of Canada. The latest official estimate is $4.1 billion (2020, the Government of Canada), 1.1 times the first price after adjusting for inflation. The first delivery target has moved 5 years, from 2013 to 2018.

Also called: AOPS, Harry DeWolf class

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.1×the first quoted price released to the public

First price 2007, Government of Canada
$4.7B
Latest estimate 2020, Government of Canada
$5.1B

Adjusted for inflation to 2026 dollars.

Days since announced
7,083
Status
Under construction
Owner
Government of Canada
Scope
Changed in 2015

Every estimate

Government

3 public cost estimates from 2007 to 2020.

Schedule

Original first delivery target
Set in 2007
2013
Current first delivery target
Set in 2015
2018
Delay
5 years

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 31 Jul 2020
    Cost

    Budget $4.1B for six ships

    The date is when the figure was reported; the budget increase was decided earlier.

    Government of CanadaGlobal News[4]

  2. 31 Jul 2020
    Milestone

    First ship delivered

    Royal Canadian NavyGlobal News[4]

  3. 23 Jan 2015
    Schedule

    First ship now due 2018

    Government of CanadaDefense News[3]

  4. 16 Jan 2015
    Cost

    Budget raised to $3.5B, now for five ships

    Government of Canada officialsDefense News[3]

  5. 16 Jan 2015
    Scope

    Five ships instead of six to eight

    The fleet shrank from six to eight ships to five for the original budget; a sixth ship was added later with more money.

    Government of CanadaGlobal News[4]

  6. 9 Jul 2007
    Cost

    Announced: $3.1B for six to eight ships

    A further $4.3B was set aside for operations and maintenance over 25 years.

    Government of Canada (Prime Minister Stephen Harper)Defence Talk[1]First price

  7. 9 Jul 2007
    Schedule

    First ship due 2013

    Government of CanadaNunatsiaq News[2]

Sources

  1. Defence Talk, 11 Jul 2007
    “The estimated cost of acquiring the Arctic Offshore Patrol Ships is C$3.1 billion, with approximately C$4.3 billion provided for operations and maintenance over their 25-year lifespan.”
  2. Nunatsiaq News, 7 Mar 2012
    “The contract was originally supposed to be awarded in May 2009, with delivery of the first of eight ships set for 2013.”
  3. Defense News, 25 Jan 2015
    “The cost of the project to build the Arctic offshore patrol ships has also increased from $3.1 billion to $3.5 billion, government officials confirmed on Jan. 16.The official contract announcement with government and company representatives was held Jan. 23.The ships were originally announced in 2007 by Conservative Prime Minister Stephen Harper and were supposed to be in the water by 2013.”
    “The first ship will be ready by 2018.”
  4. Global News, 31 Jul 2020
    “After work started on the DeWolf in 2015, Irving said it would only be able to build five ships with the $3.1 billion budgeted for the project.”
    “The government ended up increasing the budget to $4.1 billion for six.”
    “The DeWolf is the first of six new Arctic and offshore patrol vessels to be built in decades for the Royal Canadian Navy to conduct military operations in the Arctics.But it arrives two years behind schedule and after a lengthy process.”