Surrey Langley SkyTrain

A 16 km, eight-station extension of the Expo Line from King George station in Surrey to Langley City. It replaced a planned Surrey light rail line in 2018.

Surrey Langley SkyTrain was first priced at $3.12 billion in 2019 by TransLink. The latest official estimate is $6 billion (2024, the Province of British Columbia), 1.6 times the first price after adjusting for inflation. The completion target has moved 10 months, from 2028 to Q4 2029.

Also called: Expo Line extension

Reviewed monthly. Last review: 5 Nov 2026. How we update

1.6×the first quoted price released to the public

First price 2019, TransLink
$3.9B
Latest estimate 2024, Province of British Columbia
$6.4B

Adjusted for inflation to 2026 dollars.

Days since announced
2,690
Status
Under construction
Owner
Province of British Columbia, with federal funding and TransLink
Scope
Unchanged

Every estimate

Government Project owner

4 public cost estimates from 2019 to 2024.

Schedule

Original completion target
Set in 2022
2028
Current completion target
Set in 2024
Q4 2029
Delay
10 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 15 Aug 2024
    Cost

    Now $6B

    Province of British ColumbiaCTV News[3]

  2. 15 Aug 2024
    Schedule

    Opening pushed to late 2029

    Province of British ColumbiaCTV News[3]

  3. 15 Aug 2024
    Status

    Under construction

    Province of British ColumbiaGlobal News[5]

  4. 14 Jul 2022
    Cost

    Business case approved: $4.01B

    Province of British Columbia (business case)CTV News[3]

  5. 14 Jul 2022
    Schedule

    Full line by 2028

    Province of British Columbia (Transportation Minister Rob Fleming)The Canadian Press, via CBC News[4]

  6. 31 Aug 2021
    Cost

    Budget $3.94B

    TransLinkCastanet[2]

  7. 19 Jul 2019
    Cost

    TransLink: $3.12B to Langley

    TransLink (CEO Kevin Desmond)CBC News[1]First price

  8. 19 Jul 2019
    Schedule

    First section to open 2025

    TransLinkCBC News[1]

Sources

  1. CBC News, 19 Jul 2019
    “TransLink CEO Kevin Desmond said Friday a full-length Surrey Langley SkyTrain would cost $3.12 billion but only $1.6 billion is currently available.”
    “Construction could begin in early 2022, with service beginning in 2025.”
  2. Castanet, 22 Sep 2021
    “In the most recent report, issued Aug. 31, noted funding is still being sought for the project, currently estimated to have a $3.94 billion budget.”
  3. CTV News, 16 Aug 2024
    “The price tag of the expansion is now estimated at $5.996 billion, up from the $4.01 billion outlined in the 2022 business case for the project.”
    “The opening date has been pushed back from late 2028 to late 2029, a move also being attributed – in part – to the "current market climate."”
  4. The Canadian Press, via CBC News, 14 Jul 2022
    “Rob Fleming says the project is expected to be completed by 2028, two years earlier than originally planned.”
  5. Global News, 15 Aug 2024
    “Early work on the project is already underway.”

How we count