Darlington New Nuclear Project

Four GE Vernova Hitachi BWRX-300 small modular reactors beside the Darlington station in Clarington, Ont., built by Ontario Power Generation, the province's wholly owned utility. Only the first unit has final approval.

Darlington New Nuclear Project was first priced at $20.9 billion in 2025 by the Government of Ontario / Ontario Power Generation. Later figures measure something different, so they are not compared. The opening target moved from 2028 to 2030, and in 2026 Ontario Power Generation said that target would not be met. No new date has been given.

Also called: OPG BWRX-300 reactors

Checked for new figures on 19 Nov 2026. How we update

No comparable estimate since the first price. Later figures measure something different.

First price 2025, Government of Ontario / Ontario Power Generation
$22B

Adjusted for inflation to 2026 dollars.

Days since announced
1,823
Status
Under construction
Owner
Ontario Power Generation
Scope
Unchanged

Every estimate

So far only the first price ($20.9B, 2025) measures this, so there is nothing to chart yet.

Left out because they measure something else: $7.7B capital cost (unit 1 incl. shared infrastructure), 2025.

Schedule

Original opening target
Set in 2021
2028
Current opening target
2030 target withdrawn in 2026
None
Delay
No new date given
2 years+

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 10 Nov 2026
    Milestone

    OPG: Unit 1 will miss its 2030 date and $7.7B budget

    OPG's Q3 2026 results (Nov 10) gave no new cost or date. It expects its assessment to be substantially complete by mid-2027.

    Ontario Power GenerationThe Globe and Mail[5]

  2. 24 Oct 2025
    Milestone

    $3B in federal and provincial equity

    Canada Growth Fund and Building Ontario FundWorld Nuclear News[4]

  3. 8 May 2025
    Cost

    $20.9B for four reactors

    In 2024 dollars. Only the first reactor has final approval.

    Government of Ontario / Ontario Power GenerationThe Globe and Mail[2]CBC News[3]First price

  4. 8 May 2025
    Cost

    Unit 1: $7.7B including shared infrastructure

    Government of Ontario / Ontario Power GenerationCBC News[3]

  5. 8 May 2025
    Status

    Province approves construction of the first unit

    Government of OntarioCBC News[3]

  6. 8 May 2025
    Schedule

    First unit on the grid in 2030

    Ontario Power GenerationCBC News[3]The Globe and Mail[2]

  7. 2 Dec 2021
    Announcement

    OPG picks the BWRX-300 for Darlington

    No cost given.

    Ontario Power GenerationWorld Nuclear News[1]

  8. 2 Dec 2021
    Schedule

    First reactor 'as early as 2028'

    Ontario Power GenerationWorld Nuclear News[1]

In the news

Links to outside coverage. All news

Sources

  1. World Nuclear News, 2 Dec 2021
    “Ontario Power Generation has selected the BWRX-300 small modular reactor for the Darlington new nuclear site, and will work with GE Hitachi Nuclear Energy to deploy the reactor.”
    “Canada's first commercial, grid-scale, SMR could be completed as early as 2028.”
  2. The Globe and Mail, 8 May 2025
    “All told, the 1,200-megawatt plant‘s estimated cost is $20.9-billion, expressed in 2024 dollars.”
    “The first reactor was to have been completed in 2028, but OPG has pushed that back by one year.”
  3. CBC News, 8 May 2025
    “It would be the first of four such reactors that OPG aims to build on the site, at a total project cost of $20.9 billion, in an effort to meet what's forecast to be a steep rise in demand for electricity in the province.”
    “The estimated construction cost of the initial reactor is $7.7 billion, which includes $1.6 billion of infrastructure to be shared across the project.”
    “Premier Doug Ford's government has given Ontario Power Generation the green light to start construction on Canada's first small modular reactor, a new nuclear energy technology to be built next door to the Darlington power plant.”
    “The timeline is to finish construction of the first reactor by the end of 2029, and connect it to the grid in 2030.”
  4. World Nuclear News, 24 Oct 2025
    “Canada Growth Fund Inc - a CAD15 billion arm's-length investment vehicle designed to attract private capital to build Canada's clean economy - has committed to invest up to CAD2 billion in the project, while Building Ontario Fund - a Crown agency with a mandate to catalyse investment in revenue-generating infrastructure projects across Ontario, backed by CAD8 billion in funding from the province - will invest CAD1 billion.”
  5. The Globe and Mail, 13 Nov 2026
    “In quarterly financial statements released Tuesday, OPG said the first reactor unit would not be completed within its previously disclosed $7.7-billion budget.”
    “OPG had previously targeted an in-service date of October 2030. The delay could ultimately prove shorter than a year, depending on the outcome of an assessment that is expected to be completed by mid-2027.”