West Coast Oil Pipeline
A proposed one-million-barrel-a-day oil pipeline from Bruderheim, Alta., to a deepwater port near Delta, B.C., along a southern route. Proposed by the Government of Alberta; the ownership group is Trans Mountain Corp. (federal), the Alberta Petroleum Marketing Commission and Pembina. Designated in the national interest on Oct. 1, 2026.
West Coast Oil Pipeline was first priced at $35.2 billion to $43.7 billion in 2026 by the Government of Alberta. No newer official estimate has been published.
Also called: Pacific Link pipeline
Reviewed monthly. Last review: 5 Nov 2026. How we update
No new estimate since the first price.
- First price 2026, Government of Alberta
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 424
- Status
- Planning
- Owner
- Government of Alberta
- Scope
- Unchanged
Every estimate
So far only the first price ($35.2–43.7B, 2026) measures this, so there is nothing to chart yet.
Schedule
- Original completion targetSet in 2026
- 2032
- Current completion targetSet in 2026
- 2032
- Delay
- None
A target given only as a year counts as the end of that year.
Route
Timeline
- 1 Oct 2026Milestone
First project listed in the national interest
Government of Canada (Prime Minister Mark Carney) and AlbertaCBC News[4]
- 1 Oct 2026Schedule
Running by 2032-33
Government of Canada (senior official)CBC News[4]
- 2 Jul 2026Cost
$35.2–43.7B
Government of Alberta (submission to the Major Projects Office)CBC News[2]The Canadian Press, via BOE Report[3]First price
- 2 Jul 2026Schedule
Completed between 2032 and 2034
Government of Alberta (submission to the Major Projects Office)CBC News[2]
- 1 Oct 2025Announcement
Alberta says it will propose the pipeline itself
No cost given. Alberta put $14M into the proposal.
Government of Alberta (Premier Danielle Smith)CBC News[1]
In the news
Links to outside coverage. All news
Sources
- CBC News, 2 Oct 2025
“On Wednesday, Smith said the provincial government will propose its own project, with help from an advisory group that includes the pipeline companies South Bow, Enbridge and Trans Mountain.”
- CBC News, 3 Jul 2026
“The estimated cost of the project, according to the Alberta government's submission, would be $35.2 billion to $43.7 billion, including contingencies.”
“It expects the approximately 1,200- to 1,250-kilometre pipeline project to be completed between 2032 and 2034.”
- The Canadian Press, via BOE Report, 1 Oct 2026
“The preliminary price tag is estimated at a range of $35.2 billion to $43.7 billion.”
- CBC News, 1 Oct 2026
“Listing the West Coast Pacific Link oil pipeline on Schedule 1 of the Building Canada Act means the federal government has moved from considering whether it should be built to how it will be built by fast-tracking and consolidating the approval process, including environmental assessments.”
“1, 2027, allowing construction to begin, with a view to having the pipeline up and running by 2032-33.”