Samuel De Champlain Bridge
A cable-stayed replacement for the aging Champlain Bridge between Montreal and its South Shore, built as a public-private partnership with the Signature on the St. Lawrence consortium. Federal costs include the bridge, a Nuns' Island span and Highway 15 work.
Samuel De Champlain Bridge was first priced at $5 billion in 2011 by the Government of Canada. The latest official estimate is $4.23 billion (2015, the Government of Canada), below the first price in dollars as announced. It opened 6 months after the original completion target of 2018.
On budgetOpened in 2019 below the 2011 estimate, about six months late.
Also called: New Champlain Bridge, pont Samuel-De Champlain
Reviewed monthly. Last review: 5 Nov 2026. How we update
The latest figure is below the first price.
- First price 2011, Government of Canada
- Latest estimate 2015, Government of Canada
Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,534
- Status
- Operational
- Owner
- Infrastructure Canada
- Scope
- Unchanged
Every estimate
Government Other
3 public cost estimates from 2011 to 2019.
Left out because they measure something else: $1.3–2B bridge only, replacement, 2010.
Schedule
- Original completion targetSet in 2015
- 2018
- Opened
- 24 Jun 2019
- Delay
- 6 months
A target given only as a year counts as the end of that year.
Location
Timeline
- 26 Jun 2019Cost
About $4.4B after $235M added
Press figure. Federal question period notes put the project agreement at $4.212B including the extra $235M, over a 34-year term including operations, so the final cost is not settled in the sources found.
The Canadian PressThe Canadian Press, via CFJC Today[6]Sum of $4.2B + $0.235B
- 24 Jun 2019Status
Opened to traffic in June 2019
Open to traffic in both directions on July 1, 2019, per federal question period notes.
The Canadian PressThe Canadian Press, via Canada's National Observer[5]
- 13 Apr 2018Schedule
Opening reset to Dec. 21, 2018
Part of a settlement between Ottawa and the consortium.
Government of Canada and Signature on the St. LawrenceCBC News[4]
- 19 Jun 2015Cost
Project contract announced at $4.23B
Covers the new bridge, a new Nuns' Island span and widening of Highway 15, as described by CBC.
Government of Canada (Infrastructure Minister Denis Lebel)CBC News[3]
- 19 Jun 2015Schedule
Bridge to be built by 2018
The project agreement later cited by officials called for opening in December 2018.
Government of Canada (Infrastructure Minister Denis Lebel)CBC News[3]
- 5 Oct 2011Cost
Replacement announced at about $5B
Reported on the day Ottawa announced it would replace the bridge. Global also noted that a new bridge had previously been pegged at around $1.3B.
Government of Canada (Transport Minister Denis Lebel)The Canadian Press, via Global News[2]First price
- 2010Cost
Engineering report: at least $1.3B for a bridge
From a 2010 engineering report, before Ottawa had committed to a replacement. Not an official government estimate, and narrower in scope than the 2011 figure.
Delcan (engineering report)The Canadian Press, via CTV News[1]
Sources
- The Canadian Press, via CTV News, 6 Oct 2011
“The same report said that a replacement bridge would cost at least $1.3 billion, while a tunnel would cost $1.9 billion, however those numbers could climb as high as $2 billion for the bridge and $3 billion for the tunnel.”
- The Canadian Press, via Global News, 5 Oct 2011
“Building a new span to Montreal’s south shore could take as long as 10 years and cost $5 billion, but Transport Minister Denis Lebel suggested it would also create 30,000 jobs and be paid for by a toll system.”
- CBC News, 19 Jun 2015
“Federal Infrastructure Minister Denis Lebel announced Friday afternoon that the new Champlain Bridge will cost $4.23 billion.”
“New Champlain Bridge will be built by 2018, Lebel says”
- CBC News, 13 Apr 2018
“The new Champlain Bridge is expected to be ready for Dec. 21, 2018.”
- The Canadian Press, via Canada's National Observer, 25 Jun 2019
“Montreal's expensive new Samuel De Champlain Bridge opened to traffic for the first time this morning, about six months behind schedule.”
- The Canadian Press, via CFJC Today, 26 Jun 2019
“It was originally scheduled to open last December, but various delays pushed back the opening and added another $235 million to the original $4.2 billion price tag.”