Darlington Nuclear Refurbishment

The mid-life overhaul of all four CANDU reactors at OPG's Darlington station in Clarington, Ontario, extending their life to at least 2055. One of the few megaprojects here delivered on its budget.

Darlington Nuclear Refurbishment was first priced at $12.8 billion in 2016 by Ontario Power Generation. No newer official estimate has been published.

On budgetFinished in 2026 under its budget and ahead of schedule, according to the Ontario government.

Also called: DNR

Reviewed monthly. Last review: 5 Nov 2026. How we update

No new estimate since the first price.

First price 2016, Ontario Power Generation
$17B

Adjusted for inflation to 2026 dollars.

Days since announced
3,975
Status
Complete
Owner
Ontario Power Generation
Scope
Unchanged

Every estimate

So far only the first price ($12.8B, 2016) measures this, so there is nothing to chart yet.

Schedule

Original completion target
Set in 2016
2026
Completed
2 Feb 2026
Delay
None

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 2 Feb 2026
    Status

    Construction complete, ahead of schedule and under budget

    The province said the project finished four months early and $150M under the $12.8B budget. A final cost figure has not been published as a single number.

    Province of OntarioNucNet[3]

  2. Oct 2016
    Status

    Unit 2 taken offline, work begins

    Ontario Power GenerationNuclear News (American Nuclear Society)[1]

  3. 2016
    Cost

    Budget $12.8B

    OPG's budget at the start of execution. Earlier planning-stage figures are not yet sourced.

    Ontario Power GenerationNuclear News (American Nuclear Society)[1]First price

  4. 2016
    Schedule

    Execution 2016 to 2026

    Ontario Power GenerationReNew Canada[2]

Sources

  1. Nuclear News (American Nuclear Society), 3 Feb 2026
    “The 10-year megaproject, budgeted at C$12.8 billion (about $9.4 billion), was also 10 years in the planning.”
    “Work commenced in earnest in October 2016, when Unit 2 was taken off line (Nuclear News, December 2016, p. 45).Unit 2, the plant's first reactor to undergo refurbishment, returned to service in June 2020.”
  2. ReNew Canada, 22 Jan 2020
    “About The Project The Darlington Nuclear Refurbishment Project was managed in three distinct phases: Initiation Phase (2007Ð2009); Definition Phase (2010-2015); and Execution Phase (2016-2026).”
  3. NucNet, 3 Feb 2026
    “The construction phase of refurbishment of the fourth Candu reactor at the Darlington nuclear power station in Ontario, Canada, has been completed with the overall project four months ahead of schedule and CAD150m (€92m, $109m) under the CAD12.8bn budget.”