Regina Bypass

A 61 km highway bypass around the south and east of Regina with 12 overpasses, delivered as a public-private partnership. The total jumped before the contract was signed, then the project finished on time.

Regina Bypass was first priced at $1.88 billion in 2015 by the Government of Saskatchewan. Later figures measure something different, so they are not compared. It was completed 1 month after the original completion target of Q3 2019.

On budgetOpened in October 2019 at its contracted price and on schedule.

Also called: Regina Bypass Partners

Reviewed monthly. Last review: 5 Nov 2026. How we update

No comparable estimate since the first price. Later figures measure something different.

First price 2015, Government of Saskatchewan
$2.5B

Adjusted for inflation to 2026 dollars.

Days since announced
4,134
Status
Complete
Owner
Government of Saskatchewan, with federal funding
Scope
Unchanged

Every estimate

So far only the first price ($1.88B, 2015) measures this, so there is nothing to chart yet.

Left out because they measure something else: $1.2B as quoted (earlier estimate), 2015.

Schedule

Original completion target
Set in 2015
Q3 2019
Completed
29 Oct 2019
Delay
1 month

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 29 Oct 2019
    Status

    Fully open, on schedule

    Government of SaskatchewanGlobal News[3]

  2. 5 Aug 2015
    Cost

    Earlier estimate about $1.2B

    Unattributed in the report. The opposition cited other earlier figures ($400M, $700M to $800M); none is yet traced to a government statement.

    Global NewsGlobal News[1]

  3. 5 Aug 2015
    Cost

    P3 total: $1.88B

    Government of SaskatchewanGlobal News[1]First price

  4. 5 Aug 2015
    Schedule

    Finished by fall 2019

    Government of SaskatchewanCJME[2]

Sources

  1. Global News, 5 Aug 2015
    “Originally estimated to cost approximately $1.2 billion, the new higher price-tag isn’t sitting well with the opposition.”
    “The $1.88 billion investment is expected to cover all project costs – design, construction, finance, operations and maintenance.”
  2. CJME, 5 Aug 2015
    “All construction on the massive project is still scheduled to be finished in the fall of 2019.”
  3. Global News, 28 Oct 2019
    “The Saskatchewan government says the Regina Bypass will officially open to motorists on Tuesday, Oct. 29, as a ceremony marked the grand opening on Monday.”

How we count