Port Lands Flood Protection
A new mouth for the Don River and a new island in Toronto's Port Lands to protect 240 hectares from flooding, paid for equally by Ottawa, Ontario and Toronto and run by Waterfront Toronto.
Port Lands Flood Protection was first priced at $1.25 billion in 2016 by Waterfront Toronto. The latest official estimate is $1.25 billion (2024, Waterfront Toronto), the same as the first price.
On budgetFinished in 2025 within its budget.
Also called: Ookwemin Minising, Villiers Island
Reviewed monthly. Last review: 5 Nov 2026. How we update
Finished on budget.
- First price 2016, Waterfront Toronto
- Latest estimate 2024, Waterfront Toronto
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,692
- Status
- Complete
- Owner
- Waterfront Toronto
- Scope
- Unchanged
Every estimate
Project owner
2 public cost estimates from 2016 to 2024.
Location
Timeline
- 30 Sep 2025Status
Substantially complete
City of TorontoCity of Toronto (staff report to Executive Committee)[3]
- 27 Jan 2024Cost
Still $1.25B
Waterfront TorontoThe Globe and Mail[2]
- 20 Oct 2016Cost
$1.25B, up from $975M
An earlier $975M estimate is not yet traced to its original statement and date (see RESEARCH_TODO), so it is not the baseline.
Waterfront TorontoInsurance Business[1]First price
Sources
- Insurance Business, 21 Oct 2016
“The cost of the flood protection project as part of the development of eastern Toronto’s Port Lands has risen from $975m to $1.25bn, it was confirmed yesterday.”
- The Globe and Mail, 27 Jan 2024
“This $1.25-billion effort involves, quite literally, building a new river.”
- City of Toronto (staff report to Executive Committee), 24 Feb 2026
“This report provides an update on the Port Lands Flood Protection project, which reached substantial completion on September 30, 2025.”