Ontario Line

A planned 15.6 km subway line in Toronto from Exhibition Place through downtown to the Ontario Science Centre, announced by the Ontario government in 2019 and delivered by Metrolinx.

Ontario Line was first priced at $10.9 billion in 2019 by the Government of Ontario. Later figures measure something different, so they are not compared. The completion target has moved 4 years, from 2027 to 2031.

Reviewed monthly. Last review: 5 Nov 2026. How we update

No comparable estimate since the first price. Later figures measure something different.

First price 2019, Government of Ontario
$14B

Adjusted for inflation to 2026 dollars.

Days since announced
2,790
Status
Under construction
Owner
Metrolinx
Scope
Unchanged

Every estimate

So far only the first price ($10.9B, 2019) measures this, so there is nothing to chart yet.

Left out because they measure something else: $17–19B contracts including financing and 30-year operations and maintenance, 2022; $27.2B total to build and operate, 2024; $34B total as reported by CTV News (basis not stated), 2026.

Schedule

Original completion target
Set in 2019
2027
Current completion target
Set in 2022
2031
Delay
4 years

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 11 Aug 2026
    Cost

    Current cost about $34B

    CTV reports Metrolinx would not give a target opening date from February 2026 and said the line was on track for completion in the "early 2030s".

    Metrolinx (CEO Michael Lindsay)CTV News[4]

  2. 21 Jun 2024
    Cost

    $27.2B to build and operate

    Metrolinx (rapid transit project report)Global News[2]

  3. 24 Nov 2022
    Schedule

    Completion now expected in 2031

    Infrastructure OntarioCTV News[1]

  4. 23 Nov 2022
    Cost

    Contracts total $17B to $19B

    Adds the $6B southern stations and tunnels contract and the $9B trains, systems and operations contract to an estimate for the northern contract. Not comparable with the construction-only $10.9B.

    Infrastructure Ontario (contract awards)Global News[3]

  5. Apr 2019
    Cost

    Announced at $10.9B

    Construction only, according to Global News. It did not include the cost of running the line for 30 years.

    Government of Ontario (Premier Doug Ford)CTV News[1]Global News[2]First price

  6. Apr 2019
    Schedule

    Completion by 2027

    Government of Ontario (Premier Doug Ford)CTV News[1]

In the news

Links to outside coverage. All news

Sources

  1. CTV News, 24 Nov 2022
    “When the Ford government first unveiled plans for the 15.6-kilometre relief subway line in 2019, it pegged the cost at $10.9 billion and said that it would be completed by 2027.”
    “However, new documents released by Infrastructure Ontario this month show that two contracts totalling $15 billion have already been awarded for the project, which is now expected to be completed in 2031.”
  2. Global News, 21 Jun 2024
    “When the project was first unveiled by Premier Ford, in 2019, the province pegged the cost of building the line at $10.9 billion, a number the government said was only for construction and did not capture the money needed to run the line for 30 years.”
    “A Metrolinx rapid transit project report prepared for late June shows the Ontario Line is now set to cost taxpayers $27.2 billion to build and operate, a 43 per cent increase from two years ago.”
  3. Global News, 23 Nov 2022
    “In total, the contracts amount to between $17 and $19 billion, depending on the final value of the northern portions of the line.”
  4. CTV News, 12 Aug 2026
    “Lindsay confirmed at an unrelated press conference on Tuesday that the awarding of a $4.32 billion contract for three-kilometres of tunneling underneath Pape Avenue and the construction of two underground stations has pushed the current cost of the Ontario Line to around $34 billion.”
    “That is more than three times the original $10.9 billion cost estimate that was first shared for the project back in 2019.”

How we count