Ottawa LRT Stage 1
A 12.5 km light rail line with a downtown tunnel from Tunney's Pasture to Blair, built under a fixed-price contract with the Rideau Transit Group. It opened more than a year late and its failures led to a public inquiry.
Ottawa LRT Stage 1 was first priced at $2.1 billion in 2010 by the City of Ottawa. The latest official estimate is $2.13 billion (2012, the City of Ottawa), the same as the first price. It opened 9 months after the original completion target of 2018.
Also called: Confederation Line, O-Train Line 1
Reviewed monthly. Last review: 5 Nov 2026. How we update
No increase so far.
- First price 2010, City of Ottawa
- Latest estimate 2012, City of Ottawa
Adjusted for inflation to 2026 dollars.
- Days since announced
- 6,017
- Status
- Operational
- Owner
- City of Ottawa, with federal and provincial funding
- Scope
- Unchanged
Every estimate
Government
3 public cost estimates from 2010 to 2012.
Schedule
- Original completion targetSet in 2010
- 2018
- Opened
- 14 Sep 2019
- Delay
- 9 months
A target given only as a year counts as the end of that year.
Route
Timeline
- 14 Sep 2019Status
Opened to the public
Opened 15 months after the original handover date; a provincial public inquiry followed in 2022.
City of OttawaGlobal News[4]
- 19 Dec 2012Cost
Fixed price $2.13B with Rideau Transit Group
City of OttawaCBC News[3]
- 19 Dec 2012Schedule
Handover due May 24, 2018
The contract handover date; the first of four missed handover dates.
City of OttawaGlobal News[4]
- 7 Jul 2011Schedule
Completion end of 2017
City of OttawaCBC News[2]
- 7 Jul 2011Cost
Tunnel moved to Queen Street, still $2.1B
City of Ottawa (Mayor Jim Watson)CBC News[2]
- 9 Jun 2010Cost
Phase one estimated at $2.1B
Earlier figures of $1.4B and $1.8B are reported without dates; see RESEARCH_TODO.
City of OttawaRailway Track & Structures[1]First price
- 9 Jun 2010Schedule
Completion expected 2018
City of OttawaRailway Track & Structures[1]
Sources
- Railway Track & Structures, 9 Jun 2010
“Now, the total cost for phase one is estimated at C$2.1 billion.”
“Construction on the first phase of the project is expected to begin in 2013, with a completion date of 2018.”
- CBC News, 7 Jul 2011
“The project is slated to be completed at the end of 2017.”
“The cost of the project also drops to $1.74 billion in 2009 dollars, or $2.1 billion in inflation adjusted dollars.”
- CBC News, 19 Dec 2012
“The Rideau Transit Group will build the 12.5-kilometre line for a fixed price of $2.13 billion.”
- Global News, 23 Aug 2019
“RTG missed four official handover dates over the last 15 months: May 24, 2018, Nov. 2, 2018, Mar. 31, 2019 and Aug. 16, 2019.”
“Ottawa residents can start riding the light-rail trains on the long-delayed Confederation Line on Sept. 14, the mayor of Ottawa announced on Friday.”