Ottawa LRT Stage 1

A 12.5 km light rail line with a downtown tunnel from Tunney's Pasture to Blair, built under a fixed-price contract with the Rideau Transit Group. It opened more than a year late and its failures led to a public inquiry.

Ottawa LRT Stage 1 was first priced at $2.1 billion in 2010 by the City of Ottawa. The latest official estimate is $2.13 billion (2012, the City of Ottawa), the same as the first price. It opened 9 months after the original completion target of 2018.

Also called: Confederation Line, O-Train Line 1

Reviewed monthly. Last review: 5 Nov 2026. How we update

No increase so far.

First price 2010, City of Ottawa
$3.1B
Latest estimate 2012, City of Ottawa
$3B

Adjusted for inflation to 2026 dollars.

Days since announced
6,017
Status
Operational
Owner
City of Ottawa, with federal and provincial funding
Scope
Unchanged

Every estimate

Government

3 public cost estimates from 2010 to 2012.

Schedule

Original completion target
Set in 2010
2018
Opened
14 Sep 2019
Delay
9 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 14 Sep 2019
    Status

    Opened to the public

    Opened 15 months after the original handover date; a provincial public inquiry followed in 2022.

    City of OttawaGlobal News[4]

  2. 19 Dec 2012
    Cost

    Fixed price $2.13B with Rideau Transit Group

    City of OttawaCBC News[3]

  3. 19 Dec 2012
    Schedule

    Handover due May 24, 2018

    The contract handover date; the first of four missed handover dates.

    City of OttawaGlobal News[4]

  4. 7 Jul 2011
    Schedule

    Completion end of 2017

    City of OttawaCBC News[2]

  5. 7 Jul 2011
    Cost

    Tunnel moved to Queen Street, still $2.1B

    City of Ottawa (Mayor Jim Watson)CBC News[2]

  6. 9 Jun 2010
    Cost

    Phase one estimated at $2.1B

    Earlier figures of $1.4B and $1.8B are reported without dates; see RESEARCH_TODO.

    City of OttawaRailway Track & Structures[1]First price

  7. 9 Jun 2010
    Schedule

    Completion expected 2018

    City of OttawaRailway Track & Structures[1]

Sources

  1. Railway Track & Structures, 9 Jun 2010
    “Now, the total cost for phase one is estimated at C$2.1 billion.”
    “Construction on the first phase of the project is expected to begin in 2013, with a completion date of 2018.”
  2. CBC News, 7 Jul 2011
    “The project is slated to be completed at the end of 2017.”
    “The cost of the project also drops to $1.74 billion in 2009 dollars, or $2.1 billion in inflation adjusted dollars.”
  3. CBC News, 19 Dec 2012
    “The Rideau Transit Group will build the 12.5-kilometre line for a fixed price of $2.13 billion.”
  4. Global News, 23 Aug 2019
    “RTG missed four official handover dates over the last 15 months: May 24, 2018, Nov. 2, 2018, Mar. 31, 2019 and Aug. 16, 2019.”
    “Ottawa residents can start riding the light-rail trains on the long-delayed Confederation Line on Sept. 14, the mayor of Ottawa announced on Friday.”

How we count