The Ottawa Hospital new Civic campus
A new 641-room hospital campus at Dow's Lake beside the Central Experimental Farm, to replace the Civic campus. Built under a progressive public-private partnership with EllisDon and PCL; most of the money comes from Ontario.
The Ottawa Hospital new Civic campus was first priced at $2.8 billion in 2021 by The Ottawa Hospital. The latest official estimate is $2.8 billion (2024, The Ottawa Hospital), the same as the first price.
Also called: new Civic campus
Reviewed monthly. Last review: 5 Nov 2026. How we update
No increase so far.
- First price 2021, The Ottawa Hospital
- Latest estimate 2024, The Ottawa Hospital
Adjusted for inflation to 2026 dollars.
- Days since announced
- 2,035
- Status
- Procurement
- Owner
- The Ottawa Hospital
- Scope
- Unchanged
Every estimate
Project owner
2 public cost estimates from 2021 to 2024.
Left out because they measure something else: up to $10B provincial investment (as quoted; Ministry of Health would not confirm), 2026.
Schedule
- Opening targetSet in 2021
- 2028
- Delay
- None so far
A target given only as a year counts as the end of that year.
Location
Timeline
- 27 Oct 2026Cost
Minister: province investing 'just shy of $10 billion'
David Piccini, Ontario Minister of InfrastructureCTV News Ottawa[4]
- 12 Feb 2025Milestone
Cost and opening date in question
The Ottawa HospitalCBC News[3]
- 20 Feb 2024Cost
Builders chosen, still $2.8B
The Ottawa HospitalOttawa Business Journal[2]
- 20 Feb 2024Schedule
Construction to finish in 2028
The Ottawa HospitalOttawa Business Journal[2]
- 20 Feb 2024Status
Progressive P3 development phase
The Ottawa Hospital and Infrastructure OntarioOttawa Business Journal[2]
- 4 May 2021Cost
$2.8B new campus
The Ottawa HospitalGlobal News[1]First price
- 4 May 2021Schedule
Open in 2028
The Ottawa HospitalGlobal News[1]
In the news
- Why will Ottawa’s new hospital now cost $10B? No one can explain exactly why
Ottawa Citizen, 18 Nov 2026
- Minister's office says city has ‘important role to play’ in evolving Ottawa hospital cost
CBC News, 3 Nov 2026
- Minister hints at soaring new cost for Civic hospital replacement
CBC News, 29 Oct 2026
- Provincial investment into Ottawa Hospital Civic Campus now $10 billion, minister says
CTV News Ottawa, 28 Oct 2026
Links to outside coverage. All news
Sources
- Global News, 4 May 2021
“The Ottawa Hospital on Tuesday morning showed a first look at plans for its new Civic campus, a long-awaited $2.8-billion project with designs influenced by lessons from the COVID-19 pandemic.”
“The new site, set to open to the public in 2028, will be built just down Carling Avenue from the existing Civic campus, coming to a head at Preston Street and Prince of Wales Drive.”
- Ottawa Business Journal, 20 Feb 2024
“Partners for the $2.8-billion project were chosen after a 14-month selection process.”
“Construction of the new Civic campus is slated to start later this year and is expected to be completed in 2028.”
- CBC News, 12 Feb 2025
“It remains to be seen if the original $2.8-billion price tag or 2028 target opening date for the new Civic campus will hold.”
- CTV News Ottawa, 28 Oct 2026
““The investments that we’re making that are putting members to work right now on an investment of just shy of $10 billion towards the hospital,” Piccini said in response to a question from Ottawa MPP Stephen Blais.”