Hazel McCallion Line
An 18 km light rail line along Hurontario Street from Port Credit in Mississauga to the Brampton Gateway terminal, built by Mobilinx for Metrolinx. Due in 2022, it has no opening date.
Hazel McCallion Line was first priced at $1.6 billion in 2015 by the Province of Ontario. Later figures measure something different, so they are not compared. The opening target has moved 1 year, 9 months, from 2022 to Sep 2024.
Also called: Line 10
Reviewed monthly. Last review: 5 Nov 2026. How we update
No comparable estimate since the first price. Later figures measure something different.
- First price 2015, Province of Ontario
Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,240
- Status
- Under construction
- Owner
- Metrolinx
- Scope
- Changed in 2019
Every estimate
So far only the first price ($1.6B, 2015) measures this, so there is nothing to chart yet.
Left out because they measure something else: $4.6B project total as quoted (includes long-term operations and maintenance contract), 2019.
Schedule
- Original opening targetSet in 2015
- 2022
- Current opening targetSet in 2024
- Sep 2024
- Delay
- 1 year, 9 months
A target given only as a year counts as the end of that year.
Route
Timeline
- 12 Aug 2026Milestone
Construction into 2027, no opening date
MetrolinxINsauga[4]
- 18 Jan 2024Schedule
Scheduled for September 2024
MetrolinxCBC News[2]
- 13 Mar 2020Status
Construction begins
MetrolinxUrbanToronto[3]
- 13 Mar 2020Schedule
Completion projected for 2024
MetrolinxUrbanToronto[3]
- 2019Scope
Downtown loop cut
The Mississauga City Centre loop (three stations) was cut to save money; the Brampton downtown extension had already been dropped.
MetrolinxCBC News[2]
- 2019Cost
$4.6B project
Includes the builder's long-term operations and maintenance contract, so it is not compared with the $1.6B capital estimate.
MetrolinxCBC News[2]
- 21 Apr 2015Cost
Province funds the estimated $1.6B
Province of OntarioSteve Munro[1]First price
- 21 Apr 2015Schedule
Service by 2022
Province of OntarioSteve Munro[1]
Sources
- Steve Munro, 21 Apr 2015
“The Transit Project Assessment for this route was approved in August 2014, but the debate remained on who would pay the estimated $1.6-billion cost.”
“If the Hurontario-Main project proceeds as expected, detailed design will get underway soon, construction will begin in 2018, and revenue service would start in 2022.”
- CBC News, 18 Jan 2024
“Then, in 2019, Metrolinx removed the Mississauga loop from the line's design, citing financial pressures associated with the $4.6 billion project.”
“Metrolinx started rail track installation for the project last year, which is currently scheduled to open in September 2024.”
- UrbanToronto, 27 Oct 2025
“With both the City Centre Loop and Brampton extension cancelled, construction began shortly thereafter on March 13, 2020, with the line’s completion projected for 2024.”
- INsauga, 12 Aug 2026
“Metrolinx declined to provide an estimated date for when the new line would be open for passengers.”